Nansha Port Phase IV Automated Container Terminal
This overview was generated with AI from the public sources listed below and checked against them before publication. It has not had a complete human fact-check — treat it as a starting point and follow the sources.
15 sourced claims on this page, none individually verified yet — turn on “Sources in the text” to see each one.
How this atlas is made · What “last verified” means · What “source-checked” means · The full record behind this page
✎ Corrected 27 Sep 2026 3 sources added. What changed →
Guangzhou's Nansha terminal was billed as the Greater Bay Area's first fully automated terminal — an AI "Super Brain" routes driverless IGVs between robotic cranes, and throughput doubled year-on-year by 2024.
what does this mean?
The strongest source is the operator's or the city's own reporting — an official report, dataset or press release. It grades who did the looking — not how well the project went. All four grades →Part of 1001 Smart Cities — 1,216 documented projects · 🏙️ 7 more in Guangzhou · 🚗 Autonomous vehicles guide · 🚲 Mobility projects
Guangzhou Port Group's Nansha Phase IV terminal, opened 28 July 2022, was presented at its opening as the Guangdong-Hong Kong-Macao Greater Bay Area's first fully automated container terminal: automated quay cranes hand containers to intelligent guided vehicles (IGVs) routed by an AI scheduling system the operator calls the terminal's "Super Brain," with automated yard cranes replacing on-site crews. State media also call it China's first fully automated terminal for river-sea-rail multimodal transport; it has four 100,000-tonne berths and 4.9 million TEU/year design capacity. Container throughput through the automated terminal reached 1.81 million TEUs between January and mid-August 2024, up 102.7% year-on-year, and the operator reports roughly 70% lower manpower needs than a conventional terminal; Phase V won Ministry of Transport approval for its deep-water shoreline in March 2025 and began full construction on 15 May 2026, though neither announcement says whether it will be automated. In May 2026 Phase IV was cleared to receive foreign-flagged vessels.
📊 Impact
1.81 million TEUs handled by the automated terminal from January to mid-August 2024, up 102.7% year-on-year; operator-reported ~70% lower manpower requirement than a conventional terminal (Guangzhou Port Group / state media, 2022–2024).
🎓 Lesson
A doubling in a terminal's second full year measures the ramp toward design capacity, not a gain from automation: the comparison is against the same months of 2023, when four new berths were still filling. The design figure the operator gives — 4.9 million TEUs a year — is the one the throughput is climbing toward. The number that would settle the automation question is moves per crane hour against a comparable conventional terminal, and nobody publishes it. What is published is a manpower saving of about 70%, quoted by the terminal's own general manager, with no independent measurement anywhere in the sourcing. The commitment is real regardless: Phase V won its shoreline approval in March 2025 and went into full construction in May 2026, a bet made on operating experience the operator has and the public does not — though neither announcement says whether Phase V repeats the automated design.
Sources
Show 1 more sourcesShow fewer
📅 How old is the evidence?
Two clocks, kept apart: when this entry’s sources were published, and what has happened to its record in the atlas. Documented span: since 2022. 6 of 6 sources carry a publication date, from 1 August 2022 to 25 May 2026.
When the sources were published
- GDToday · pressGDToday/newsgd.com (press)
- China Daily · pressChina Daily Nansha (press, 21 Aug 2024)
- China Daily · pressChina Daily / Invest in China (press)
- Guangzhou Daily (广州日报) · pressGuangzhou Daily — Nansha Phase V shoreline approved (12 March 2025)
- Guangzhou Municipal People's Government · city governmenteGuangzhou — Construction begins on Phase V of Nansha Port (18 May 2026)
- China Daily · pressChina Daily Nansha (press, 25 May 2026)
What happened to this record
- Entered the record
- 3 sources added
- Sources last read
Show your work What this page rests on and what it can’t tell you · all 15 claims with their sources · the forensic record
Evidence file · public beta 15 addressable claims, 6 source dossiers, one permanent baseline. The file is unreviewed — an AI-assisted structural migration, not a human or expert endorsement. Every revision keeps a permanent copy under revision history.
Inspect the claims, one by one — verbatim text, sources and caveats for all 15
The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-241e8af29ce47d83
quantitative
Guangzhou Port Group's Nansha Phase IV terminal, opened 28 July 2022, was presented at its opening as the Guangdong-Hong Kong-Macao Greater Bay Area's first fully automated container terminal
Sources carrying this claim
clm-ce07d12cff4b6569
descriptive
automated quay cranes hand containers to intelligent guided vehicles (IGVs) routed by an AI scheduling system the operator calls the terminal's "Super Brain," with automated yard cranes replacing on-site crews
Sources carrying this claim
clm-f4a10994167d2856
descriptive
State media also call it China's first fully automated terminal for river-sea-rail multimodal transport
Sources carrying this claim
clm-a8bc7cbc56c87b5a
quantitative
it has four 100,000-tonne berths and 4.9 million TEU/year design capacity
Sources carrying this claim
clm-b2519ca8119d1241
quantitative
Container throughput through the automated terminal reached 1.81 million TEUs between January and mid-August 2024, up 102.7% year-on-year
Sources carrying this claim
clm-1f221da78fec2327
quantitative
the operator reports roughly 70% lower manpower needs than a conventional terminal
Sources carrying this claim
clm-6c20c64d277e85c0
quantitative
Phase V won Ministry of Transport approval for its deep-water shoreline in March 2025
Sources carrying this claim
clm-3d2749e0dbee9743
quantitative
began full construction on 15 May 2026
Sources carrying this claim
clm-c17027dc3605e04a
descriptive
though neither announcement says whether it will be automated
Sources carrying this claim
clm-691c1f34e9512c7c
quantitative
In May 2026 Phase IV was cleared to receive foreign-flagged vessels.
Sources carrying this claim
clm-912bfbfab2cd91ea
quantitative
1.81 million TEUs handled by the automated terminal from January to mid-August 2024, up 102.7% year-on-year
Sources carrying this claim
clm-f58d1110fec15269
quantitative
operator-reported ~70% lower manpower requirement than a conventional terminal
Sources carrying this claim
clm-ba59faa20c0c11da
quantitative
The design figure the operator gives — 4.9 million TEUs a year
Sources carrying this claim
clm-1cfcdd2fe54ed547
quantitative
What is published is a manpower saving of about 70%, quoted by the terminal's own general manager
Sources carrying this claim
clm-d2729b6cd4bb7f26
quantitative
Phase V won its shoreline approval in March 2025 and went into full construction in May 2026
Sources carrying this claim
Forensic record — source dossiers, gaps, hashes and the exact revision this page renders
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:1ea6e763455eccd648820ba320710368223f348a0c9553c3233ed52c3bd5f278
- 15
- of 15 claims mapped
- 6
- source dossiers
- 6
- publication dates recorded
- 0
- archives linked
- 0
- exact locators
- 0
- content captures hashed
Governance facts carried by the record
- Operator
- Guangzhou Port Group
- Actor types
- utility
- Funding model
- public
- Funding description
- Not recorded
- Cost
- Not recorded
- Ownership
- Not recorded
- Decision rights
- Not recorded
- Exit conditions
- Not recorded
6 source dossiers
GDToday/newsgd.com (press)
- Stable source ID
src-a3b656520eb61e2d- Publisher
- Name not classified · newsgd.com
- Type / language
- web-page · language not classified
- Published
- 2022-08-01
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Published 1 August 2022. Source for the opening date, the IGV and crane choreography, and two operator statements from He Yeke, general manager of Nansha Phase IV: four 100,000-tonne berths with a total annual handling capacity of 4.9 million TEUs, and 'The automated terminal saves about 70 percent of manpower and guarantees a higher level of safety for production.'
China Daily / Invest in China (press)
- Stable source ID
src-90b1382770766142- Publisher
- Name not classified · investinchina.chinadaily.com.cn
- Type / language
- web-page · language not classified
- Published
- 2024-12-26
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Nansha Port area passes 20 million TEUs in 2024; the fully automated Phase IV terminal passed completion acceptance in November 2024, and construction of Phase V was under way. It does not give a throughput figure for the automated terminal itself.
- Claims linked
- Background source; no baseline claim points here
China Daily Nansha (press, 21 Aug 2024)
- Stable source ID
src-81370bec638a4b5c- Publisher
- Name not classified · nansha.guangdong.chinadaily.com.cn
- Type / language
- web-page · language not classified
- Published
- 2024-08-21
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
From the start of 2024 to mid-August, the Phase IV terminal handled 1.81 million TEUs, up 102.7% year on year; describes the 'Super Brain' scheduling system and calls the terminal China's first fully automated terminal for river-sea-rail multimodal transport. Published before Phase V was approved.
Guangzhou Daily — Nansha Phase V shoreline approved (12 March 2025)
- Stable source ID
src-516e0d6f860365bd- Publisher
- Name not classified · gzdaily.dayoo.com
- Type / language
- web-page · language not classified
- Published
- 2025-03-12
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Guangzhou Daily front page: the Ministry of Transport has approved use of deep-water port shoreline for Nansha Phase V — four 200,000-tonne container berths, 15 barge berths, design capacity above 6 million TEU a year. Says nothing about automation.
eGuangzhou — Construction begins on Phase V of Nansha Port (18 May 2026)
- Stable source ID
src-4ee9113cd898ae37- Publisher
- Name not classified · eguangzhou.gov.cn
- Type / language
- web-page · language not classified
- Published
- 2026-05-18
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Guangzhou's official English portal: full-scale construction of Nansha Phase V began on 15 May 2026, with an estimated investment of 14.447 billion yuan and a design capacity of 6.7 million TEU a year. The announcement does not describe the terminal's level of automation.
China Daily Nansha (press, 25 May 2026)
- Stable source ID
src-a55495088c6237b7- Publisher
- Name not classified · nansha.guangdong.chinadaily.com.cn
- Type / language
- web-page · language not classified
- Published
- 2026-05-25
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
The Phase IV terminal was among three Nansha terminals approved to receive foreign-flagged vessels on 22 May 2026; the article calls it the world's first fully automated river-sea intermodal container terminal.
- Claims linked
Known limits of this file
- Publisher names and source languages have not yet been classified; domains are recorded without guessing.
- Existing source notes are descriptive locators, not page- or paragraph-exact citations.
- A missing archive, publication date or content hash is shown as null rather than inferred.
- The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim.
Continue exploring
Compare this project
Explore the wider context
📎 Cite this project
1001 Smart Cities (2026). “Nansha Port Phase IV Automated Container Terminal” — Guangzhou, China. The Smart City Atlas. https://1001smartcities.org/projects/guangzhou-nansha-port-terminal/ (last verified 2026-09-27). Data: CC BY 4.0.
The underlying data is free to reuse with attribution — see the open data page.