Línea 2 — Lima's Automated Underground Metro
This overview was generated with AI from the public sources listed below and checked against them before publication. It has not had a complete human fact-check — treat it as a starting point and follow the sources.
How this atlas is made · What “last verified” means · What “source-checked” means · The full record behind this page
✎ Corrected 21 Aug 2026 Publication date recorded for 9 sources. · 3 revisions in all What changed →
Billed by its concessionaire as Peru's first underground, GoA4-automated metro, Línea 2 opened a five-station, five-kilometre stretch in December 2023 — five of the 27 stations promised under a 2014 concession. Trains are commanded from a central control room. The remaining stages are now due in 2029 and October 2030.
what does this mean?
The strongest source is the operator's or the city's own reporting — an official report, dataset or press release. It grades who did the looking — not how well the project went. All four grades →📊 Impact
19.6 million passengers between December 2023 and 14 June 2026, with a record 1,823,089 in May 2026 (concessionaire figures reported to Ositrán's rail users' council). Stage 1A had an original target of February 2017 in the comptroller's 2018 review; it opened in December 2023, and stages 1B and 2 stood at 96% and 91% complete in August 2026.
🎓 Lesson
Driverless trains were the procurable part; the tunnels and the timetable were not. A July 2026 regulator file shows the ministry and the concessionaire arguing over whether the scheduled interval of four minutes 34 seconds may be met with a statistical tolerance. No source found dates the day staff stopped riding along — the contract required a train operator aboard for the first three months of service.
Sources
Show 4 more sourcesShow fewer
📅 How old is the evidence?
Two clocks, kept apart: when this entry’s sources were published, and what has happened to its record in the atlas. Documented span: since 2023. 6 of 9 sources carry a publication date, from 7 December 2023 to 12 August 2026.
When the sources were published
- Agencia Andina · pressAgencia Andina — inside the control room of Lima's first driverless train (December 2023)
- Urban Transport Magazine · pressUrban Transport Magazine — opening of Lima's line 2 (December 2023)
- Infobae · pressInfobae — all five stations closed by a power failure (June 2025)
- Revista Construir · pressRevista Construir — 19.6m passengers reported to Ositrán (June 2026)
- Infobae · pressInfobae — MTC vs concessionaire on the service regularity index (July 2026)
- La República (Perú) · pressLa República — Line 2 stages 1B and 2 pass 90% (August 2026)
What happened to this record
Show your work What this page rests on and what it can’t tell you · all 12 claims with their sources · the forensic record
Evidence Passport · public beta 12 addressable claims, 9 source dossiers, one permanent baseline. The passport is unreviewed — an AI-assisted structural migration, not a human or expert endorsement. Every revision keeps a permanent copy under revision history.
Inspect the claims, one by one — verbatim text, sources and caveats for all 12
The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-6ee05cb4dd034a45
quantitative
Billed by its concessionaire as Peru's first underground, GoA4-automated metro
Sources carrying this claim
clm-2f2f4baae111e316
quantitative
opened a five-station, five-kilometre stretch in December 2023
Sources carrying this claim
clm-be54b13bbd3c33e1
quantitative
five of the 27 stations promised under a 2014 concession
Sources carrying this claim
clm-b21586b1ea2d8435
descriptive
Trains are commanded from a central control room
Sources carrying this claim
clm-4244f705daccd148
quantitative
The remaining stages are now due in 2029 and October 2030
Sources carrying this claim
clm-c20c9966892b32b3
quantitative
19.6 million passengers between December 2023 and 14 June 2026
Sources carrying this claim
clm-29bf27c5b3ba7450
quantitative
a record 1,823,089 in May 2026
Sources carrying this claim
clm-306c6e77bb37a464
descriptive
(concessionaire figures reported to Ositrán's rail users' council)
Sources carrying this claim
clm-52128820b6dbd9f5
quantitative
Stage 1A had an original target of February 2017 in the comptroller's 2018 review
Sources carrying this claim
clm-57b4ec712c9531e9
quantitative
stages 1B and 2 stood at 96% and 91% complete in August 2026
Sources carrying this claim
clm-70a92b0c62de244a
quantitative
A July 2026 regulator file shows the ministry and the concessionaire arguing over whether the scheduled interval of four minutes 34 seconds may be met with a statistical tolerance
Sources carrying this claim
clm-92a6383415ed2fb3
descriptive
the contract required a train operator aboard for the first three months of service
Sources carrying this claim
Forensic record — source dossiers, gaps, hashes and the exact revision this page renders
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:388f3dfee23a51044477c0a1e08b084285d7b13fd527546f20d581c10978340a
- 12
- of 12 claims mapped
- 9
- source dossiers
- 6
- publication dates recorded
- 0
- archives linked
- 0
- exact locators
- 0
- content captures hashed
Governance facts carried by the record
- Operator
- Sociedad Concesionaria Metro de Lima Línea 2 S.A. (concessionaire; MTC contracting authority, ATU service oversight, Ositrán regulator)
- Actor types
- private, national-government
- Funding model
- ppp
- Funding description
- Co-financed concession (Peruvian state, MTC)
- Cost
- ≈US$4.53bn investment commitment (concessionaire, excl. VAT)
- Ownership
- Not recorded
- Decision rights
- Not recorded
- Exit conditions
- Not recorded
9 source dossiers
Metro de Lima Línea 2 — project page (concessionaire)
- Stable source ID
src-cadf6070042bce01- Publisher
- Name not classified · metrolima2.com
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-17
- Dossier created
- 2026-08-21
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
GoA4 claim, 27 km / 27 stations, stage 1A opened 21 December 2023 with 5 stations over 5 km, US$4,531M investment commitment, platform screen doors.
La República — Line 2 stages 1B and 2 pass 90% (August 2026)
- Stable source ID
src-ab8d2a2abddd8edd- Publisher
- Name not classified · larepublica.pe
- Type / language
- web-page · language not classified
- Published
- 2026-08-12
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-17
- Dossier created
- 2026-08-21
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Only the five stage-1A stations operate; 96% / 91% stage progress; the 2018 Contraloría original targets; the 2029 and October 2030 reference dates.
Revista Construir — 19.6m passengers reported to Ositrán (June 2026)
- Stable source ID
src-635876563e45df6a- Publisher
- Name not classified · construir.com.pe
- Type / language
- web-page · language not classified
- Published
- 2026-06-21
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-17
- Dossier created
- 2026-08-21
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Concessionaire figures presented to Ositrán's rail users' council (session 38): 19.6m since December 2023, cut-off 14 June 2026; May 2026 record of 1,823,089.
Ositrán — Line 2 carried more than 19 million passengers
- Stable source ID
src-2a67c469d6d8c184- Publisher
- Name not classified · gob.pe
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-17
- Dossier created
- 2026-08-21
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
The regulator's own publication of the ridership figure. gob.pe answers automated fetches with HTTP 418 (bot wall, not dead); existence and content confirmed by search.
- Claims linked
Infobae — MTC vs concessionaire on the service regularity index (July 2026)
- Stable source ID
src-454df9296b3e45a9- Publisher
- Name not classified · infobae.com
- Type / language
- web-page · language not classified
- Published
- 2026-07-13
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-17
- Dossier created
- 2026-08-21
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Ositrán Informe Conjunto N° 00110-2026-IC-OSITRAN of 7 July 2026: scheduled interval 4 min 34 s; the concessionaire seeks tolerance to 6 min 28 s.
- Claims linked
Agencia Andina — inside the control room of Lima's first driverless train (December 2023)
- Stable source ID
src-93c46d839130e3d1- Publisher
- Name not classified · andina.pe
- Type / language
- web-page · language not classified
- Published
- 2023-12-07
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-17
- Dossier created
- 2026-08-21
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
State news agency, 7 December 2023: the contract requires a train operator's direct assistance in the first three months; the Puesto Central de Operaciones commands trains remotely.
- Claims linked
Urban Transport Magazine — opening of Lima's line 2 (December 2023)
- Stable source ID
src-a9cb8687474e47d4- Publisher
- Name not classified · urban-transport-magazine.com
- Type / language
- web-page · language not classified
- Published
- 2023-12-21
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-17
- Dossier created
- 2026-08-21
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Free passenger service from 21 December 2023, 5 stops over 5 km; Hitachi (AnsaldoBreda) supplying 35 six-car trains, 5 then in service.
- Claims linked
- Background source; no baseline claim points here
Infobae — all five stations closed by a power failure (June 2025)
- Stable source ID
src-9779aed9acae1e13- Publisher
- Name not classified · infobae.com
- Type / language
- web-page · language not classified
- Published
- 2025-06-29
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-17
- Dossier created
- 2026-08-21
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Reliability counterweight: ATU suspended service at all stations over 'un problema en el suministro de energía'.
- Claims linked
- Background source; no baseline claim points here
Ositrán — concession factsheet, Sociedad Concesionaria Metro de Lima Línea 2 S.A.
- Stable source ID
src-3f69de60ab7c79b0- Publisher
- Name not classified · ositran.gob.pe
- Type / language
- pdf · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-17
- Dossier created
- 2026-08-21
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Regulator factsheet for the 2014 concession (contract signed 28 April 2014, 35-year co-financed term). The PDF resisted text extraction; content confirmed via search and the 2014 award record.
- Claims linked
Known limits of this passport
- Publisher names and source languages have not yet been classified; domains are recorded without guessing.
- Existing source notes are descriptive locators, not page- or paragraph-exact citations.
- A missing archive, publication date or content hash is shown as null rather than inferred.
- The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim.
Continue exploring
Compare this project
Explore the wider context