clm-0b0916d3a0d917e6
quantitative
Siemens led a consortium with Landis+Gyr and Iskraemeco (selected 2017)
Permanent project revision
Revision 2026-08-21-evidence-baseline · effective 2026-07-22
Current revision. This is the snapshot used by the live entity page.
Created the first structured Evidence Passport with 11 claims and 6 source dossiers.
sha256:41069917736d706a62adc7645221e986ed4cf2544e409bd138771ce0940e0557
add /evidencePassport — Added claim-level evidence mapping and source dossiers.add /revisionHistory — Established a permanent, hash-addressed baseline revision.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-0b0916d3a0d917e6
quantitative
Siemens led a consortium with Landis+Gyr and Iskraemeco (selected 2017)
clm-0df4d1a7864ca62a
quantitative
to swap Vienna-area electricity meters for smart meters from November 2018
clm-26a02673e3a44f91
quantitative
Wiener Netze hit Austria's 95% legal target in December 2024
clm-6c9acccf8ea63d4e
quantitative
cut remaining legacy meters to about 46,000
clm-6aff12715b58be2c
quantitative
of ~1.6 million
clm-572e802c946f400f
quantitative
by March 2026
clm-bd752a29a051ec60
quantitative
~1.6 million electricity meters in Wiener Netze's service area
clm-36154b0f178a12e6
quantitative
Austria's 95% legal smart-meter target
clm-3e247e029960cc65
quantitative
reached in December 2024
clm-bae20532638b2d21
quantitative
about 46,000 legacy meters still outstanding by March 2026
clm-60081551eed2d41a
quantitative
Austria's national rate stood at about 97% at the end of 2025 per regulator E-Control
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:41069917736d706a62adc7645221e986ed4cf2544e409bd138771ce0940e0557
src-28c9c4c28d5f5604Current 2026 status: remaining legacy meters, enforcement phase.
src-2f24a33bdde3a1e6Official press release corroborating the 2026 rollout status.
src-e82b2d9e946e8211Independent press confirming the 95% legal target was reached December 2024.
src-00a83da0d5fa3f8bVendor project page: consortium partners, rollout start.
src-78d25006d3b2edadLegal basis: ElWOG 2010 / IME-VO 2022.
src-3c6290d0524b498fNational context via regulator E-Control: ~97% of Austrian metering points digital by end of 2025.