Wiener Netze Smart Meter Rollout

Every published revision of this Evidence file, newest first. Old versions keep their URL and content hash.

  1. unreviewed

    2026-10-05-p4-quality-run

    Quality run to P4: claim array, source dates, present-tense audit. The rollout is essentially complete (Wiener Netze, 30 March 2026: ~1.6 million installed, ~46,000 legacy meters left); no later count found. The national figure in impact was mis-dated: E-Control's final monitoring report (APA, 20 Nov 2025) gives 96.9% at the end of 2024, not ~97% at the end of 2025.

    Effective
    2026-10-05
    Snapshot
    sha256:c603ae12632567b7…
  2. unreviewed

    2026-08-21-evidence-baseline

    Created the first structured Evidence Passport with 11 claims and 6 source dossiers.

    Effective
    2026-07-22
    Snapshot
    sha256:41069917736d706a…