Hafslund Celsio (formerly Hafslund Oslo Celsio)
Permanent project revision
Revision 2026-10-05-baseline · effective 2026-10-05
Current revision. This is the snapshot used by the live entity page.
Created the first structured Evidence Passport with 20 claims and 6 source dossiers.
sha256:6009803554d9d79968aa7889250e4548c5a347a5fd3f456bdd0afa63e57e60b0
add /evidencePassport — Added claim-level evidence mapping and source dossiers.add /revisionHistory — Established a permanent, hash-addressed baseline revision.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-2ff4dfe11feea738
descriptive
Hafslund Celsio (formerly Hafslund Oslo Celsio)
clm-fc8e823c2c6d17b6
descriptive
is fitting its Klemetsrud waste-to-energy plant
clm-a9d91578b2e3a612
descriptive
Oslo's single largest greenhouse-gas emitter
clm-2e8780d3a04a1a6a
quantitative
source of 17% of the city's direct emissions
clm-962a32f6593f1db0
descriptive
whose heat goes into district heating
clm-4a27bdb2d781a3b5
quantitative
Paused in 2023 over rising costs
clm-0dd1cb3766da6d1a
quantitative
the project restarted after a January 2025 investment decision
clm-fd83b4ff8a6f51fe
descriptive
civil works are under way
clm-723c57a9c698d9bd
quantitative
construction of the capture facility itself was scheduled to start in spring 2026
clm-38f0a0fd1435c037
quantitative
operation is targeted for the third quarter of 2029
clm-9a9444f77d683e77
quantitative
with captured CO2 shipped to offshore storage
clm-1007b3a30e8f9423
quantitative
Designed to capture 350,000 tonnes of CO2 a year
clm-76aed0bf193de674
quantitative
about 90% of the flue-gas CO2 from the plant
clm-1470993a351307f5
quantitative
roughly 200,000 tonnes of it biogenic and so counted as negative emissions
clm-f13a2aa51ec70fe4
descriptive
since the capture facility itself has not been built
clm-92ba25f198255084
quantitative
Captured CO2 is to be taken to the Port of Oslo and shipped to the Northern Lights terminal in Øygarden for permanent storage beneath the North Sea seabed.
clm-02d85206d7d41034
quantitative
work stopped in 2023 when cost estimates exceeded the ceiling in the state funding agreement
clm-551a468e741ad6ae
descriptive
resumed only after a cost-reduction phase
clm-18cab717d7d18e54
descriptive
a revised deal under which the state carries no further overrun risk
clm-28ad4c0f3c333469
quantitative
pays NOK 900 million of its support only once the plant is completed
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:6009803554d9d79968aa7889250e4548c5a347a5fd3f456bdd0afa63e57e60b0
src-d860998c97e2689bOfficial state programme page: current owner, construction status, 350,000 t/yr capacity, Q3 2029 target, 2023 pause.
src-7a816c75d4f6c84bOperator's own release: 24 Jan 2025 FID, capacity, full funding breakdown by state/municipality/company.
src-8f02e70c12d101f9State agency page confirming Klemetsrud's place in the Longship programme and the Northern Lights transport/storage link.
src-79e40c9bbb28725cCity of Oslo's own account of the plant's 17% share of the city's direct emissions and the 2023 delay.
src-51d75243fd19fb4eDocuments the spring 2023 pause over rising cost estimates.
src-85beb9d1ee4bdb29Gassnova news item on the restart: under the revised support agreement the state gives no further grants or risk relief if costs overrun, and NOK 900 million of the state support is paid as a start-up grant on completion.