Dortmund led the three-city NOX-Block project with Schwerte and Iserlohn
Permanent project revision
Revision 2026-08-20-source-dates-r2 · effective 2026-08-15
Current revision. This is the snapshot used by the live entity page.
Record the publication date of each source that states one; sources that publish no date are marked null.
sha256:de41979cf778112f97726850edd718e7cc7d8618927c74cf83102e797261cd8e
replace /snapshot/projectFingerprint — Updated projectFingerprint to the current sourced project record.replace /snapshot/sources — Updated sources to the current sourced project record.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-02626a76c377b780
descriptive
Dortmund led the three-city NOX-Block project with Schwerte and Iserlohn
clm-08083e27cca129fb
quantitative
a federal subsidy of about €10 million
clm-887ae20f32eb12c0
quantitative
The first lamppost charger went live in December 2019
clm-bb9883b8e054a015
quantitative
by late 2022 utility DEW21 and contractor SPIE had 320 points running at up to 11 kilowatts
clm-73da2284f3ae4d5a
descriptive
TU Dortmund and the University of Wuppertal studied the effects on the grid
clm-f7a856bdcb05a281
quantitative
The 2021 rollout announcement had spoken of up to 500 points for Dortmund
clm-8b647f0167e8db10
quantitative
completion reports count 320 and declare the goals met, without explaining the gap
clm-97c58deeb3d15cfe
quantitative
in summer 2025 the utility extended the kerbside idea with charging curbstones on Betenstraße
clm-a2eb408ccb197387
quantitative
ten units that logged over 3,000 charging sessions at about 5.5 percent utilisation
clm-9639c0d794929877
quantitative
DEW21 frames 5.5 percent as a very good value for inner-city charging
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:de41979cf778112f97726850edd718e7cc7d8618927c74cf83102e797261cd8e
src-d38127e22463ef43Trade press at rollout start, July 2021: 680 points planned across three cities (500 Dortmund, 100 Schwerte, 80 Iserlohn), ≈€10M federal funding, StraBelDo consortium (DEW21 + SPIE), Ebee hardware, TU Dortmund and BU Wuppertal as research partners.
src-2b633157ae392e06State e-mobility agency on completion: first charger December 2019, all 320 installed by late 2022, 11 kW, on time and on budget per the project; grid-impact research role of the universities.
src-4ac3ac91e3ad9cb8Local press, 2025/26: ten charging curbstones on Betenstraße since summer 2025, over 3,000 sessions, ≈5.5% utilisation described as a very good value, comparable to the existing lamppost points.
src-72005050817d18a8City project page (authority). The site blocks automated retrieval; project facts here are cross-checked against the trade and state-agency sources above.