North Cairo's JICA-Funded Smart Meter Rollout

Revision 2026-08-21-source-dates · effective 2026-07-26

Current revision. This is the snapshot used by the live entity page.

unreviewed

Record the publication date of each source that states one; a source that publishes no date is marked null, and one that shows only a revision carries `updated` instead.

sha256:cabaf847bce0435a75cf62be386511e195187e4603182e310469f9dd6c2bd305

Change set

  • replace /snapshot/projectFingerprint — Updated projectFingerprint to the current sourced project record.
  • replace /snapshot/sources — Updated sources to the current sourced project record.
10
of 10 claims mapped
10
source dossiers
5
publication dates recorded
0
archives linked
0
exact locators
0
content captures hashed

Claims, one by one

The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.

Claim 1 clm-60966a5af44c50aa quantitative
North Cairo Electricity Distribution Company, the state distributor for Cairo Governorate and southern Qalyubia, is replacing about 490,000 mechanical meters with remotely read ones in the sectors under its Helmiyet el-Zaytoun control centre, which is itself being rebuilt
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The governorate lists the company among its own entities and defines its service area as Cairo Governorate plus the southern extension of Qalyubia. The ministry account gives the deployment footprint — Helmiya, Matariya, Marg — the 490,000 meters, and the new sector control centre.
Caveat
The governorate page carries no subscriber numbers and nothing on this project; it anchors the scope only.

Sources carrying this claim

  1. Cairo Governorate — North Cairo Electricity Distribution Company
  2. Al-Masry Al-Youm — ministry on the 490,000-meter replacement (press)
Claim 2 clm-ff71c668683a08cc quantitative
Elsewedy Electric T&D and Toyota Tsusho signed the engineering contract on 30 November 2020, financed by a Japanese ODA loan through JICA
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The contractor announcement verifies the client, the consortium, the distribution management system, approximately 500,000 meters, a contract worth about JPY 10bn and the Japanese ODA financing. The press account dates the signing to 30 November 2020 and values the North Cairo component at about US$96M. The ministry's loan record covers the wider Electricity Distribution System Improvement Project for Alexandria, North Cairo and North Delta at JPY 24,762M.
Caveat
A dating discrepancy runs through the sources: the ministry record puts the loan signature at 10 February 2022 while press reports refer to a 2016 loan agreement. The entry therefore asserts only the engineering contract date, not a loan date.

Sources carrying this claim

  1. Toyota Tsusho — contract announcement (contractor)
  2. Daily News Egypt — Japan-Egypt signing, 30 November 2020 (press)
  3. Ministry of International Cooperation — loan record (authority)
Claim 3 clm-22ae6360e87f3d71 descriptive
This is not a prepayment scheme. The company describes a meter with no top-up card: consumption is read remotely, the subscriber receives an SMS bill and pays online, the meter flags tampering, and the utility can cut supply without a site visit
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The April 2025 announcement describes a meter that works without a top-up card, with an SMS bill paid online, electronic theft detection, remote disconnection for non-payment and replacement at no cost to the subscriber. The vendor's project page is decisive on the mechanism question: it describes remote reading only and mentions no prepayment functionality, alongside the IE.5 and IE.7 meters, G3-PLC or cellular modems, data concentrators, head-end system and five years of operation and maintenance.
Caveat
Vendor material is used for specification, not for outcomes.

Sources carrying this claim

  1. Masrawy — installation begins, 23 April 2025 (press, operator statements)
  2. Iskraemeco — NCEDC project page (vendor)
Claim 4 clm-35a3043d5784fa84 descriptive
A separate and larger conversion to prepaid card meters runs alongside it at the same company
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The chairman's 2024/25 plan is the sentence that separates the two programmes: 217,000 smart meters — 190,000 through the donor project and 27,000 for large subscribers — alongside 317,000 conversions to prepaid meters.
Caveat
Operator statements relayed by the press. Without this separation the two tracks are routinely reported as one programme.

Sources carrying this claim

  1. Youm7 — NCEDC chairman on 2024/25 targets, 8 May 2024 (press, operator statements)
Claim 5 clm-a3d3cc6b4749c2a3 quantitative
Toyota Tsusho expected the system to start operating in mid-2023 and the ministry described a 30-month build; installation actually began in Hadayek el-Qubba in April 2025, in a first phase of roughly 50,000 meters
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The contractor states operation was expected to commence in mid-2023; the ministry described a 30-month implementation period from November 2020; and the April 2025 announcement records the start of installation in Hadayek el-Qubba in a first phase of about 50,000 meters against the 490,000 target.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Toyota Tsusho — contract announcement (contractor)
  2. Al-Masry Al-Youm — ministry on the 490,000-meter replacement (press)
  3. Masrawy — installation begins, 23 April 2025 (press, operator statements)
Claim 6 clm-e20d89b3b636d689 descriptive
The promised cuts in outages and distribution losses remain projections, and no cumulative installed figure has been published
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The signing report's figures for blackout reduction and theft prevention are stated as expectations at signing, not measured results, and are deliberately not used as impact. The ministry account reports no installed count, and none appears in any other source reached.
Caveat
A negative finding across the sources reached.

Sources carrying this claim

  1. Daily News Egypt — Japan-Egypt signing, 30 November 2020 (press)
  2. Al-Masry Al-Youm — ministry on the 490,000-meter replacement (press)
Claim 7 clm-a8fd239cce7d95ec quantitative
within a three-company programme of roughly 965,000 meters costing about US$226M that also serves Alexandria and North Delta
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The ministry account gives the wider three-company programme at about 965,000 meters for about US$226M. The loan record confirms the same three beneficiaries: Alexandria, North Cairo and North Delta.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Al-Masry Al-Youm — ministry on the 490,000-meter replacement (press)
  2. Ministry of International Cooperation — loan record (authority)
Claim 8 clm-10595664b62d4ce3 quantitative
Chairman Hesham Afifi set a 2024/25 target of 217,000 smart meters — 190,000 through the JICA project and 27,000 for large subscribers — alongside 317,000 conversions to prepaid cards
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The chairman gives the fiscal 2024/25 plan: 217,000 smart meters, of which 190,000 through the donor project and 27,000 for large subscribers, plus 317,000 conversions to prepaid meters.
Caveat
A target, not a delivery figure, and an operator statement relayed by the press.

Sources carrying this claim

  1. Youm7 — NCEDC chairman on 2024/25 targets, 8 May 2024 (press, operator statements)
Claim 9 clm-17706a5b253da48e descriptive
Every figure here is a utility, ministry or contractor statement relayed by the press; no audit and no independent evaluation of loss reduction, outage frequency or collection performance was located
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The one peer-reviewed treatment located concerns the separate nationwide prepaid-card rollout rather than this project, and is cited to show that the prepaid track has drawn critical academic scrutiny while this one has none. Every operational figure in the entry originates with the utility, the ministry or the contractor.
Caveat
The academic source's fetch was blocked; title, author, journal, volume and argument were confirmed via the publisher listing and search. It contains no figures used in this entry.

Sources carrying this claim

  1. Salwa Ismail, Antipode 58(1), 2026 — prepaid meters in Egypt (peer-reviewed)
  2. Masrawy — installation begins, 23 April 2025 (press, operator statements)
Claim 10 clm-d18e6099314cec84 descriptive
Reading a country's metering statistics without separating the two produces a number that means nothing
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The same company plans 217,000 remotely read meters and 317,000 prepaid-card conversions in a single year, and the vendor page confirms the donor-financed meters carry no prepayment function — two different instruments with different consequences for the household, counted together in any national total.
Caveat
The conclusion is the entry's own, drawn from the two documented tracks.

Sources carrying this claim

  1. Youm7 — NCEDC chairman on 2024/25 targets, 8 May 2024 (press, operator statements)
  2. Iskraemeco — NCEDC project page (vendor)

Source dossiers and revision state

This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.

unreviewed Revision 2026-08-21-source-dates effective 2026-07-26 · created 2026-08-22

Awaiting operator and domain-expert review; publication of this revision implies neither.

sha256:cabaf847bce0435a75cf62be386511e195187e4603182e310469f9dd6c2bd305
10
of 10 claims mapped
10
source dossiers
5
publication dates recorded
0
archives linked
0
exact locators
0
content captures hashed

Governance facts carried by the record

Operator
North Cairo Electricity Distribution Company (NCEDC), a subsidiary of the state-owned Egyptian Electricity Holding Company; delivered by Elsewedy Electric T&D with Toyota Tsusho, meters by Iskraemeco
Actor types
utility
Funding model
public
Funding description
Japanese ODA loan via JICA to the Egyptian Electricity Holding Company; part of a package of about US$226M also covering Alexandria and North Delta
Cost
about JPY 10bn (about US$96M) for the North Cairo EPC contract; the Ministry of Electricity put the North Cairo package including the control centre at about US$90M
Ownership
Not recorded
Decision rights
Not recorded
Exit conditions
Not recorded

10 source dossiers

Cairo Governorate — North Cairo Electricity Distribution Company cairo.gov.eg · 1 linked claim

Open original source ↗

Stable source ID
src-13cc491423f97cca
Publisher
Name not classified · cairo.gov.eg
Type / language
web-page · language not classified
Published
Not recorded
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-22
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Fetched. Authority, and the scope anchor: the governorate lists NCEDC among its own entities and defines its service area as Cairo Governorate plus the southern extension of Qalyubia. Carries no subscriber numbers and nothing on this project.

Descriptive only — not page/paragraph exact
Toyota Tsusho — contract announcement (contractor) toyota-tsusho.com · 2 linked claims

Open original source ↗

Stable source ID
src-075af533ffc3773f
Publisher
Name not classified · toyota-tsusho.com
Type / language
web-page · language not classified
Published
Not recorded
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-22
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Fetched. Verifies the client (EEHC and NCEDC), the consortium with Elsewedy Electric, the Hitachi ABB distribution management system, approximately 500,000 meters to be replaced, a contract worth approximately JPY 10bn, and financing by a Japanese ODA loan through JICA. Also the source of the missed schedule: it states operation was expected to commence in mid-2023.

Descriptive only — not page/paragraph exact
Daily News Egypt — Japan-Egypt signing, 30 November 2020 (press) dailynewsegypt.com · 2 linked claims

Open original source ↗

Stable source ID
src-caebafe77de4285d
Publisher
Name not classified · dailynewsegypt.com
Type / language
web-page · language not classified
Published
Not recorded
Updated
2020-11-30
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-22
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Fetched. Dates the signing to 30 November 2020 and values the North Cairo component at about US$96M. Its figures for blackout reduction and theft prevention are stated as expectations at signing, not measured results, and are not used as impact in this entry.

Descriptive only — not page/paragraph exact
Al-Masry Al-Youm — ministry on the 490,000-meter replacement (press) almasryalyoum.com · 4 linked claims

Open original source ↗

Stable source ID
src-3e07126100005763
Publisher
Name not classified · almasryalyoum.com
Type / language
web-page · language not classified
Published
2020-11-30
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-22
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Fetched. Gives the deployment footprint (Helmiya, Matariya, Marg), the 490,000 meters, about US$90M with JICA financing, the new Helmiya sector control centre, a 30-month implementation period from November 2020, and the wider three-company programme of about 965,000 meters for about US$226M. Reports no installed count.

Descriptive only — not page/paragraph exact
Iskraemeco — NCEDC project page (vendor) iskraemeco.com · 2 linked claims

Open original source ↗

Stable source ID
src-e57aff04c6e20b7c
Publisher
Name not classified · iskraemeco.com
Type / language
web-page · language not classified
Published
2024-12-20
Updated
2025-01-16
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-22
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Fetched. Technical detail: IE.5 single-phase and IE.7 three-phase meters, G3-PLC or GPRS/3G/4G modems, AC750 data concentrators, head-end system, five-year operation and maintenance. Decisive on the mechanism question: it describes remote reading only and mentions no prepayment functionality. Vendor material, so used for specification, not for outcomes.

Descriptive only — not page/paragraph exact
Iskraemeco — factory acceptance test milestone (vendor) iskraemeco.com · background

Open original source ↗

Stable source ID
src-77901fa1fc0b5db1
Publisher
Name not classified · iskraemeco.com
Type / language
web-page · language not classified
Published
2024-12-20
Updated
2025-01-16
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-22
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Fetched. Records the factory acceptance test of the IE.5 single-phase meters at Kranj, Slovenia, with NCEDC, TEPSCO, EEHC and Elsewedy Electric T&D present. The page carries no date, so it cannot be used to date progress; it is included only as confirmation that the meters reached acceptance testing.

Descriptive only — not page/paragraph exact
Claims linked
Background source; no baseline claim points here
Masrawy — installation begins, 23 April 2025 (press, operator statements) masrawy.com · 3 linked claims

Open original source ↗

Stable source ID
src-8f3ca69dd7dd95f9
Publisher
Name not classified · masrawy.com
Type / language
web-page · language not classified
Published
2025-04-23
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-22
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Fetched. The most recent dated status found: NCEDC announces the start of installation in Hadayek el-Qubba, a first phase of about 50,000 meters against a 490,000 target under the Helmiyet el-Zaytoun control centre. Describes the meter as working without a top-up card, with an SMS bill paid via Fawry or online, electronic theft detection, remote disconnection for non-payment, and replacement at no cost to the subscriber.

Descriptive only — not page/paragraph exact
Youm7 — NCEDC chairman on 2024/25 targets, 8 May 2024 (press, operator statements) youm7.com · 3 linked claims

Open original source ↗

Stable source ID
src-44033cfcc64746fd
Publisher
Name not classified · youm7.com
Type / language
web-page · language not classified
Published
2024-05-08
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-22
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Fetched. Chairman Hesham Afifi gives the FY2024/25 plan: 217,000 smart meters, of which 190,000 through the JICA project and 27,000 for large subscribers, plus 317,000 conversions to prepaid meters. This is the sentence that separates the two programmes and prevents them being reported as one.

Descriptive only — not page/paragraph exact
Ministry of International Cooperation — loan record (authority) moic.gov.eg · 2 linked claims

Open original source ↗

Stable source ID
src-e3d5663ede4fe481
Publisher
Name not classified · moic.gov.eg
Type / language
web-page · language not classified
Published
Not recorded
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-22
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Fetched. Records the Electricity Distribution System Improvement Project for Alexandria, North Cairo and North Delta: donor Japan, loan of JPY 24,762M, beneficiary the Ministry of Electricity and Renewable Energy, locations including Cairo. Flagged discrepancy: this page dates the loan signature to 10 February 2022, while press reports refer to a 2016 loan agreement and an EPC contract signed in November 2020. The entry therefore asserts only the EPC contract date, not a loan date.

Descriptive only — not page/paragraph exact
Salwa Ismail, Antipode 58(1), 2026 — prepaid meters in Egypt (peer-reviewed) onlinelibrary.wiley.com · 1 linked claim

Open original source ↗

Stable source ID
src-c2bf434939c3fcbb
Publisher
Name not classified · onlinelibrary.wiley.com
Type / language
web-page · language not classified
Published
Not recorded
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-22
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Fetch blocked (HTTP 403); title, author, journal, volume and argument confirmed via the publisher listing and search results. Concerns the SEPARATE nationwide prepaid-card rollout, not this AMI project, and is cited only to show that the prepaid track has drawn peer-reviewed critical scrutiny while this one has none. Contains no figures used in this entry.

Descriptive only — not page/paragraph exact
Known limits of this passport
  • Publisher names and source languages have not yet been classified; domains are recorded without guessing.
  • Existing source notes are descriptive locators, not page- or paragraph-exact citations.
  • A missing archive, publication date or content hash is shown as null rather than inferred.
  • The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim.