 "schemaVersion": "1.0.0",
 "constitutionVersion": "1.0.0",
 "createdAt": "2026-08-12T00:00:00Z",
 "description": "Append-only Evidence Passport records. Old revisions are immutable; corrections create a new revision and preserve the previous permalink.",
 "entity": {
  "type": "project",
  "id": "cairo-north-smart-metering",
  "title": "North Cairo's JICA-Funded Smart Meter Rollout",
  "canonicalUrl": "https://1001smartcities.org/projects/cairo-north-smart-metering/"
 },
 "currentRevisionId": "2026-08-21-source-dates",
 "revisions": [
  {
   "id": "2026-08-20-claim-baseline",
   "createdAt": "2026-08-21T12:00:00Z",
   "effectiveAt": "2026-07-26",
   "changeType": "baseline",
   "summary": "Created the first structured Evidence Passport with 10 claims and 10 source dossiers.",
   "preparedBy": {
    "type": "automation",
    "label": "AI-assisted evidence preparation",
    "humanApproved": false
   },
   "review": {
    "status": "unreviewed",
    "by": null,
    "date": null,
    "note": "Awaiting operator and domain-expert review; publication of this revision implies neither."
   },
   "changes": [
    {
     "operation": "add",
     "path": "/evidencePassport",
     "summary": "Added claim-level evidence mapping and source dossiers."
    },
    {
     "operation": "add",
     "path": "/revisionHistory",
     "summary": "Established a permanent, hash-addressed baseline revision."
    }
   ],
   "snapshotHash": "sha256:778820ece4684081608541bd1e1e3f9b2047ce100594cadb00b07c931afa20f5",
   "snapshot": {
    "asOf": "2026-07-26",
    "projectFingerprint": "sha256:ac1382c03d9d6cf18ea0b9ee20ec5b953e15fa91f0895c95a059f8f0919f91e2",
    "assurance": {
     "status": "unreviewed",
     "scope": "evidence-passport-revision",
     "statement": "AI-assisted structural preparation. This revision has not been reviewed by a human or subject-matter expert.",
     "machineChecks": [
      "schema",
      "publication-diff-contract",
      "material-project-fingerprint",
      "claim-text-drift",
      "source-reference-resolution",
      "complete-source-dossier",
      "snapshot-hash"
     ]
    },
    "projectState": {
     "status": "construction",
     "outcome": "ongoing",
     "evidenceGrade": "official",
     "timeline": {
      "started": 2020,
      "ended": null
     }
    },
    "governance": {
     "operator": "North Cairo Electricity Distribution Company (NCEDC), a subsidiary of the state-owned Egyptian Electricity Holding Company; delivered by Elsewedy Electric T&D with Toyota Tsusho, meters by Iskraemeco",
     "actorTypes": [
      "utility"
     ],
     "fundingModel": "public",
     "fundingDescription": "Japanese ODA loan via JICA to the Egyptian Electricity Holding Company; part of a package of about US$226M also covering Alexandria and North Delta",
     "cost": "about JPY 10bn (about US$96M) for the North Cairo EPC contract; the Ministry of Electricity put the North Cairo package including the control centre at about US$90M",
     "ownership": null,
     "decisionRights": null,
     "exitConditions": null
    },
    "claims": [
     {
      "id": "clm-60966a5af44c50aa",
      "field": "snippet",
      "text": "North Cairo Electricity Distribution Company, the state distributor for Cairo Governorate and southern Qalyubia, is replacing about 490,000 mechanical meters with remotely read ones in the sectors under its Helmiyet el-Zaytoun control centre, which is itself being rebuilt",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-13cc491423f97cca",
       "src-3e07126100005763"
      ],
      "supportNote": "The governorate lists the company among its own entities and defines its service area as Cairo Governorate plus the southern extension of Qalyubia. The ministry account gives the deployment footprint — Helmiya, Matariya, Marg — the 490,000 meters, and the new sector control centre.",
      "caveat": "The governorate page carries no subscriber numbers and nothing on this project; it anchors the scope only.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-ff71c668683a08cc",
      "field": "snippet",
      "text": "Elsewedy Electric T&D and Toyota Tsusho signed the engineering contract on 30 November 2020, financed by a Japanese ODA loan through JICA",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-075af533ffc3773f",
       "src-caebafe77de4285d",
       "src-e3d5663ede4fe481"
      ],
      "supportNote": "The contractor announcement verifies the client, the consortium, the distribution management system, approximately 500,000 meters, a contract worth about JPY 10bn and the Japanese ODA financing. The press account dates the signing to 30 November 2020 and values the North Cairo component at about US$96M. The ministry's loan record covers the wider Electricity Distribution System Improvement Project for Alexandria, North Cairo and North Delta at JPY 24,762M.",
      "caveat": "A dating discrepancy runs through the sources: the ministry record puts the loan signature at 10 February 2022 while press reports refer to a 2016 loan agreement. The entry therefore asserts only the engineering contract date, not a loan date.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-22ae6360e87f3d71",
      "field": "snippet",
      "text": "This is not a prepayment scheme. The company describes a meter with no top-up card: consumption is read remotely, the subscriber receives an SMS bill and pays online, the meter flags tampering, and the utility can cut supply without a site visit",
      "statementKind": "descriptive",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-8f3ca69dd7dd95f9",
       "src-e57aff04c6e20b7c"
      ],
      "supportNote": "The April 2025 announcement describes a meter that works without a top-up card, with an SMS bill paid online, electronic theft detection, remote disconnection for non-payment and replacement at no cost to the subscriber. The vendor's project page is decisive on the mechanism question: it describes remote reading only and mentions no prepayment functionality, alongside the IE.5 and IE.7 meters, G3-PLC or cellular modems, data concentrators, head-end system and five years of operation and maintenance.",
      "caveat": "Vendor material is used for specification, not for outcomes.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-35a3043d5784fa84",
      "field": "snippet",
      "text": "A separate and larger conversion to prepaid card meters runs alongside it at the same company",
      "statementKind": "descriptive",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-44033cfcc64746fd"
      ],
      "supportNote": "The chairman's 2024/25 plan is the sentence that separates the two programmes: 217,000 smart meters — 190,000 through the donor project and 27,000 for large subscribers — alongside 317,000 conversions to prepaid meters.",
      "caveat": "Operator statements relayed by the press. Without this separation the two tracks are routinely reported as one programme.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-a3d3cc6b4749c2a3",
      "field": "snippet",
      "text": "Toyota Tsusho expected the system to start operating in mid-2023 and the ministry described a 30-month build; installation actually began in Hadayek el-Qubba in April 2025, in a first phase of roughly 50,000 meters",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-075af533ffc3773f",
       "src-3e07126100005763",
       "src-8f3ca69dd7dd95f9"
      ],
      "supportNote": "The contractor states operation was expected to commence in mid-2023; the ministry described a 30-month implementation period from November 2020; and the April 2025 announcement records the start of installation in Hadayek el-Qubba in a first phase of about 50,000 meters against the 490,000 target.",
      "caveat": null,
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-e20d89b3b636d689",
      "field": "snippet",
      "text": "The promised cuts in outages and distribution losses remain projections, and no cumulative installed figure has been published",
      "statementKind": "descriptive",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-caebafe77de4285d",
       "src-3e07126100005763"
      ],
      "supportNote": "The signing report's figures for blackout reduction and theft prevention are stated as expectations at signing, not measured results, and are deliberately not used as impact. The ministry account reports no installed count, and none appears in any other source reached.",
      "caveat": "A negative finding across the sources reached.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-a8fd239cce7d95ec",
      "field": "impact",
      "text": "within a three-company programme of roughly 965,000 meters costing about US$226M that also serves Alexandria and North Delta",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-3e07126100005763",
       "src-e3d5663ede4fe481"
      ],
      "supportNote": "The ministry account gives the wider three-company programme at about 965,000 meters for about US$226M. The loan record confirms the same three beneficiaries: Alexandria, North Cairo and North Delta.",
      "caveat": null,
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-10595664b62d4ce3",
      "field": "impact",
      "text": "Chairman Hesham Afifi set a 2024/25 target of 217,000 smart meters — 190,000 through the JICA project and 27,000 for large subscribers — alongside 317,000 conversions to prepaid cards",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-44033cfcc64746fd"
      ],
      "supportNote": "The chairman gives the fiscal 2024/25 plan: 217,000 smart meters, of which 190,000 through the donor project and 27,000 for large subscribers, plus 317,000 conversions to prepaid meters.",
      "caveat": "A target, not a delivery figure, and an operator statement relayed by the press.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-17706a5b253da48e",
      "field": "impact",
      "text": "Every figure here is a utility, ministry or contractor statement relayed by the press; no audit and no independent evaluation of loss reduction, outage frequency or collection performance was located",
      "statementKind": "descriptive",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-c2bf434939c3fcbb",
       "src-8f3ca69dd7dd95f9"
      ],
      "supportNote": "The one peer-reviewed treatment located concerns the separate nationwide prepaid-card rollout rather than this project, and is cited to show that the prepaid track has drawn critical academic scrutiny while this one has none. Every operational figure in the entry originates with the utility, the ministry or the contractor.",
      "caveat": "The academic source's fetch was blocked; title, author, journal, volume and argument were confirmed via the publisher listing and search. It contains no figures used in this entry.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-d18e6099314cec84",
      "field": "lesson",
      "text": "Reading a country's metering statistics without separating the two produces a number that means nothing",
      "statementKind": "descriptive",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-44033cfcc64746fd",
       "src-e57aff04c6e20b7c"
      ],
      "supportNote": "The same company plans 217,000 remotely read meters and 317,000 prepaid-card conversions in a single year, and the vendor page confirms the donor-financed meters carry no prepayment function — two different instruments with different consequences for the household, counted together in any national total.",
      "caveat": "The conclusion is the entry's own, drawn from the two documented tracks.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     }
    ],
    "sources": [
     {
      "id": "src-13cc491423f97cca",
      "title": "Cairo Governorate — North Cairo Electricity Distribution Company",
      "url": "https://www.cairo.gov.eg/ar/governorate-entities/companies/north-cairo-electricity-distribution-company/",
      "publisher": {
       "name": null,
       "domain": "cairo.gov.eg",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-60966a5af44c50aa"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Authority, and the scope anchor: the governorate lists NCEDC among its own entities and defines its service area as Cairo Governorate plus the southern extension of Qalyubia. Carries no subscriber numbers and nothing on this project.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-075af533ffc3773f",
      "title": "Toyota Tsusho — contract announcement (contractor)",
      "url": "https://www.toyota-tsusho.com/english/press/detail/201201_004720.html",
      "publisher": {
       "name": null,
       "domain": "toyota-tsusho.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-ff71c668683a08cc",
       "clm-a3d3cc6b4749c2a3"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Verifies the client (EEHC and NCEDC), the consortium with Elsewedy Electric, the Hitachi ABB distribution management system, approximately 500,000 meters to be replaced, a contract worth approximately JPY 10bn, and financing by a Japanese ODA loan through JICA. Also the source of the missed schedule: it states operation was expected to commence in mid-2023.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-caebafe77de4285d",
      "title": "Daily News Egypt — Japan-Egypt signing, 30 November 2020 (press)",
      "url": "https://www.dailynewsegypt.com/2020/11/30/japan-egypt-sign-agreement-for-north-cairo-electricity-distribution-management-advanced-meters/",
      "publisher": {
       "name": null,
       "domain": "dailynewsegypt.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-ff71c668683a08cc",
       "clm-e20d89b3b636d689"
      ],
      "temporal": {
       "publishedAt": "2020-11-30",
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "publication-and-record-dates-recorded"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Dates the signing to 30 November 2020 and values the North Cairo component at about US$96M. Its figures for blackout reduction and theft prevention are stated as expectations at signing, not measured results, and are not used as impact in this entry.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-3e07126100005763",
      "title": "Al-Masry Al-Youm — ministry on the 490,000-meter replacement (press)",
      "url": "https://www.almasryalyoum.com/news/details/2100231",
      "publisher": {
       "name": null,
       "domain": "almasryalyoum.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-60966a5af44c50aa",
       "clm-a3d3cc6b4749c2a3",
       "clm-e20d89b3b636d689",
       "clm-a8fd239cce7d95ec"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Gives the deployment footprint (Helmiya, Matariya, Marg), the 490,000 meters, about US$90M with JICA financing, the new Helmiya sector control centre, a 30-month implementation period from November 2020, and the wider three-company programme of about 965,000 meters for about US$226M. Reports no installed count.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-e57aff04c6e20b7c",
      "title": "Iskraemeco — NCEDC project page (vendor)",
      "url": "https://iskraemeco.com/project/improving-energy-efficiency-and-reliability-of-distribution-networks-in-egypt-north-cairo-electricity-distribution-company/",
      "publisher": {
       "name": null,
       "domain": "iskraemeco.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-22ae6360e87f3d71",
       "clm-d18e6099314cec84"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Technical detail: IE.5 single-phase and IE.7 three-phase meters, G3-PLC or GPRS/3G/4G modems, AC750 data concentrators, head-end system, five-year operation and maintenance. Decisive on the mechanism question: it describes remote reading only and mentions no prepayment functionality. Vendor material, so used for specification, not for outcomes.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-77901fa1fc0b5db1",
      "title": "Iskraemeco — factory acceptance test milestone (vendor)",
      "url": "https://iskraemeco.com/project/an-important-milestone-was-reached-in-a-project-to-modernize-and-digitize-the-electricity-distribution-networks-in-north-cairo/",
      "publisher": {
       "name": null,
       "domain": "iskraemeco.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "background",
      "claimRefs": [],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Records the factory acceptance test of the IE.5 single-phase meters at Kranj, Slovenia, with NCEDC, TEPSCO, EEHC and Elsewedy Electric T&D present. The page carries no date, so it cannot be used to date progress; it is included only as confirmation that the meters reached acceptance testing.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-8f3ca69dd7dd95f9",
      "title": "Masrawy — installation begins, 23 April 2025 (press, operator statements)",
      "url": "https://www.masrawy.com/news/news_egypt/details/2025/4/23/2775749/",
      "publisher": {
       "name": null,
       "domain": "masrawy.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-22ae6360e87f3d71",
       "clm-a3d3cc6b4749c2a3",
       "clm-17706a5b253da48e"
      ],
      "temporal": {
       "publishedAt": "2025-04-23",
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "publication-and-record-dates-recorded"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. The most recent dated status found: NCEDC announces the start of installation in Hadayek el-Qubba, a first phase of about 50,000 meters against a 490,000 target under the Helmiyet el-Zaytoun control centre. Describes the meter as working without a top-up card, with an SMS bill paid via Fawry or online, electronic theft detection, remote disconnection for non-payment, and replacement at no cost to the subscriber.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-44033cfcc64746fd",
      "title": "Youm7 — NCEDC chairman on 2024/25 targets, 8 May 2024 (press, operator statements)",
      "url": "https://www.youm7.com/story/2024/5/8/%D9%83%D9%87%D8%B1%D8%A8%D8%A7%D8%A1-%D8%B4%D9%85%D8%A7%D9%84-%D8%A7%D9%84%D9%82%D8%A7%D9%87%D8%B1%D8%A9-%D9%86%D8%B3%D8%AA%D9%87%D8%AF%D9%81-%D8%AA%D8%B1%D9%83%D9%8A%D8%A8-217-%D8%A3%D9%84%D9%81-%D8%B9%D8%AF%D8%A7%D8%AF-%D8%B0%D9%83%D9%89-%D8%AE%D9%84%D8%A7%D9%84/6568260",
      "publisher": {
       "name": null,
       "domain": "youm7.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-35a3043d5784fa84",
       "clm-10595664b62d4ce3",
       "clm-d18e6099314cec84"
      ],
      "temporal": {
       "publishedAt": "2024-05-08",
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "publication-and-record-dates-recorded"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Chairman Hesham Afifi gives the FY2024/25 plan: 217,000 smart meters, of which 190,000 through the JICA project and 27,000 for large subscribers, plus 317,000 conversions to prepaid meters. This is the sentence that separates the two programmes and prevents them being reported as one.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-e3d5663ede4fe481",
      "title": "Ministry of International Cooperation — loan record (authority)",
      "url": "https://moic.gov.eg/project/161",
      "publisher": {
       "name": null,
       "domain": "moic.gov.eg",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-ff71c668683a08cc",
       "clm-a8fd239cce7d95ec"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Records the Electricity Distribution System Improvement Project for Alexandria, North Cairo and North Delta: donor Japan, loan of JPY 24,762M, beneficiary the Ministry of Electricity and Renewable Energy, locations including Cairo. Flagged discrepancy: this page dates the loan signature to 10 February 2022, while press reports refer to a 2016 loan agreement and an EPC contract signed in November 2020. The entry therefore asserts only the EPC contract date, not a loan date.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-c2bf434939c3fcbb",
      "title": "Salwa Ismail, Antipode 58(1), 2026 — prepaid meters in Egypt (peer-reviewed)",
      "url": "https://onlinelibrary.wiley.com/doi/10.1111/anti.70113",
      "publisher": {
       "name": null,
       "domain": "onlinelibrary.wiley.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-17706a5b253da48e"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetch blocked (HTTP 403); title, author, journal, volume and argument confirmed via the publisher listing and search results. Concerns the SEPARATE nationwide prepaid-card rollout, not this AMI project, and is cited only to show that the prepaid track has drawn peer-reviewed critical scrutiny while this one has none. Contains no figures used in this entry.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     }
    ],
    "coverage": {
     "claimsTotal": 10,
     "claimsMapped": 10,
     "sourcesTotal": 10,
     "sourcesUsedByClaims": 9,
     "sourcesWithPublicationDate": 3,
     "sourcesWithArchive": 0,
     "sourcesWithExactLocator": 0,
     "sourcesWithContentHash": 0
    },
    "limits": [
     "Publisher names and source languages have not yet been classified; domains are recorded without guessing.",
     "Existing source notes are descriptive locators, not page- or paragraph-exact citations.",
     "A missing archive, publication date or content hash is shown as null rather than inferred.",
     "The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim."
    ]
   }
  },
  {
   "id": "2026-08-21-source-dates",
   "createdAt": "2026-08-22T02:12:00Z",
   "effectiveAt": "2026-07-26",
   "changeType": "update",
   "summary": "Record the publication date of each source that states one; a source that publishes no date is marked null, and one that shows only a revision carries `updated` instead.",
   "preparedBy": {
    "type": "automation",
    "label": "AI-assisted evidence preparation",
    "humanApproved": false
   },
   "review": {
    "status": "unreviewed",
    "by": null,
    "date": null,
    "note": "Awaiting operator and domain-expert review; publication of this revision implies neither."
   },
   "changes": [
    {
     "operation": "replace",
     "path": "/snapshot/projectFingerprint",
     "summary": "Updated projectFingerprint to the current sourced project record."
    },
    {
     "operation": "replace",
     "path": "/snapshot/sources",
     "summary": "Updated sources to the current sourced project record."
    }
   ],
   "snapshotHash": "sha256:cabaf847bce0435a75cf62be386511e195187e4603182e310469f9dd6c2bd305",
   "snapshot": {
    "asOf": "2026-07-26",
    "projectFingerprint": "sha256:500cfa79a642b5afecc908f85bfcdae4c6bd23260d35d5632cdbc53375284fd4",
    "assurance": {
     "status": "unreviewed",
     "scope": "evidence-passport-revision",
     "statement": "AI-assisted structural preparation. This revision has not been reviewed by a human or subject-matter expert.",
     "machineChecks": [
      "schema",
      "publication-diff-contract",
      "material-project-fingerprint",
      "claim-text-drift",
      "source-reference-resolution",
      "complete-source-dossier",
      "snapshot-hash"
     ]
    },
    "projectState": {
     "status": "construction",
     "outcome": "ongoing",
     "evidenceGrade": "official",
     "timeline": {
      "started": 2020,
      "ended": null
     }
    },
    "governance": {
     "operator": "North Cairo Electricity Distribution Company (NCEDC), a subsidiary of the state-owned Egyptian Electricity Holding Company; delivered by Elsewedy Electric T&D with Toyota Tsusho, meters by Iskraemeco",
     "actorTypes": [
      "utility"
     ],
     "fundingModel": "public",
     "fundingDescription": "Japanese ODA loan via JICA to the Egyptian Electricity Holding Company; part of a package of about US$226M also covering Alexandria and North Delta",
     "cost": "about JPY 10bn (about US$96M) for the North Cairo EPC contract; the Ministry of Electricity put the North Cairo package including the control centre at about US$90M",
     "ownership": null,
     "decisionRights": null,
     "exitConditions": null
    },
    "claims": [
     {
      "id": "clm-60966a5af44c50aa",
      "field": "snippet",
      "text": "North Cairo Electricity Distribution Company, the state distributor for Cairo Governorate and southern Qalyubia, is replacing about 490,000 mechanical meters with remotely read ones in the sectors under its Helmiyet el-Zaytoun control centre, which is itself being rebuilt",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-13cc491423f97cca",
       "src-3e07126100005763"
      ],
      "supportNote": "The governorate lists the company among its own entities and defines its service area as Cairo Governorate plus the southern extension of Qalyubia. The ministry account gives the deployment footprint — Helmiya, Matariya, Marg — the 490,000 meters, and the new sector control centre.",
      "caveat": "The governorate page carries no subscriber numbers and nothing on this project; it anchors the scope only.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-ff71c668683a08cc",
      "field": "snippet",
      "text": "Elsewedy Electric T&D and Toyota Tsusho signed the engineering contract on 30 November 2020, financed by a Japanese ODA loan through JICA",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-075af533ffc3773f",
       "src-caebafe77de4285d",
       "src-e3d5663ede4fe481"
      ],
      "supportNote": "The contractor announcement verifies the client, the consortium, the distribution management system, approximately 500,000 meters, a contract worth about JPY 10bn and the Japanese ODA financing. The press account dates the signing to 30 November 2020 and values the North Cairo component at about US$96M. The ministry's loan record covers the wider Electricity Distribution System Improvement Project for Alexandria, North Cairo and North Delta at JPY 24,762M.",
      "caveat": "A dating discrepancy runs through the sources: the ministry record puts the loan signature at 10 February 2022 while press reports refer to a 2016 loan agreement. The entry therefore asserts only the engineering contract date, not a loan date.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-22ae6360e87f3d71",
      "field": "snippet",
      "text": "This is not a prepayment scheme. The company describes a meter with no top-up card: consumption is read remotely, the subscriber receives an SMS bill and pays online, the meter flags tampering, and the utility can cut supply without a site visit",
      "statementKind": "descriptive",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-8f3ca69dd7dd95f9",
       "src-e57aff04c6e20b7c"
      ],
      "supportNote": "The April 2025 announcement describes a meter that works without a top-up card, with an SMS bill paid online, electronic theft detection, remote disconnection for non-payment and replacement at no cost to the subscriber. The vendor's project page is decisive on the mechanism question: it describes remote reading only and mentions no prepayment functionality, alongside the IE.5 and IE.7 meters, G3-PLC or cellular modems, data concentrators, head-end system and five years of operation and maintenance.",
      "caveat": "Vendor material is used for specification, not for outcomes.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-35a3043d5784fa84",
      "field": "snippet",
      "text": "A separate and larger conversion to prepaid card meters runs alongside it at the same company",
      "statementKind": "descriptive",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-44033cfcc64746fd"
      ],
      "supportNote": "The chairman's 2024/25 plan is the sentence that separates the two programmes: 217,000 smart meters — 190,000 through the donor project and 27,000 for large subscribers — alongside 317,000 conversions to prepaid meters.",
      "caveat": "Operator statements relayed by the press. Without this separation the two tracks are routinely reported as one programme.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-a3d3cc6b4749c2a3",
      "field": "snippet",
      "text": "Toyota Tsusho expected the system to start operating in mid-2023 and the ministry described a 30-month build; installation actually began in Hadayek el-Qubba in April 2025, in a first phase of roughly 50,000 meters",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-075af533ffc3773f",
       "src-3e07126100005763",
       "src-8f3ca69dd7dd95f9"
      ],
      "supportNote": "The contractor states operation was expected to commence in mid-2023; the ministry described a 30-month implementation period from November 2020; and the April 2025 announcement records the start of installation in Hadayek el-Qubba in a first phase of about 50,000 meters against the 490,000 target.",
      "caveat": null,
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-e20d89b3b636d689",
      "field": "snippet",
      "text": "The promised cuts in outages and distribution losses remain projections, and no cumulative installed figure has been published",
      "statementKind": "descriptive",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-caebafe77de4285d",
       "src-3e07126100005763"
      ],
      "supportNote": "The signing report's figures for blackout reduction and theft prevention are stated as expectations at signing, not measured results, and are deliberately not used as impact. The ministry account reports no installed count, and none appears in any other source reached.",
      "caveat": "A negative finding across the sources reached.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-a8fd239cce7d95ec",
      "field": "impact",
      "text": "within a three-company programme of roughly 965,000 meters costing about US$226M that also serves Alexandria and North Delta",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-3e07126100005763",
       "src-e3d5663ede4fe481"
      ],
      "supportNote": "The ministry account gives the wider three-company programme at about 965,000 meters for about US$226M. The loan record confirms the same three beneficiaries: Alexandria, North Cairo and North Delta.",
      "caveat": null,
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-10595664b62d4ce3",
      "field": "impact",
      "text": "Chairman Hesham Afifi set a 2024/25 target of 217,000 smart meters — 190,000 through the JICA project and 27,000 for large subscribers — alongside 317,000 conversions to prepaid cards",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-44033cfcc64746fd"
      ],
      "supportNote": "The chairman gives the fiscal 2024/25 plan: 217,000 smart meters, of which 190,000 through the donor project and 27,000 for large subscribers, plus 317,000 conversions to prepaid meters.",
      "caveat": "A target, not a delivery figure, and an operator statement relayed by the press.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-17706a5b253da48e",
      "field": "impact",
      "text": "Every figure here is a utility, ministry or contractor statement relayed by the press; no audit and no independent evaluation of loss reduction, outage frequency or collection performance was located",
      "statementKind": "descriptive",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-c2bf434939c3fcbb",
       "src-8f3ca69dd7dd95f9"
      ],
      "supportNote": "The one peer-reviewed treatment located concerns the separate nationwide prepaid-card rollout rather than this project, and is cited to show that the prepaid track has drawn critical academic scrutiny while this one has none. Every operational figure in the entry originates with the utility, the ministry or the contractor.",
      "caveat": "The academic source's fetch was blocked; title, author, journal, volume and argument were confirmed via the publisher listing and search. It contains no figures used in this entry.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-d18e6099314cec84",
      "field": "lesson",
      "text": "Reading a country's metering statistics without separating the two produces a number that means nothing",
      "statementKind": "descriptive",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-44033cfcc64746fd",
       "src-e57aff04c6e20b7c"
      ],
      "supportNote": "The same company plans 217,000 remotely read meters and 317,000 prepaid-card conversions in a single year, and the vendor page confirms the donor-financed meters carry no prepayment function — two different instruments with different consequences for the household, counted together in any national total.",
      "caveat": "The conclusion is the entry's own, drawn from the two documented tracks.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     }
    ],
    "sources": [
     {
      "id": "src-13cc491423f97cca",
      "title": "Cairo Governorate — North Cairo Electricity Distribution Company",
      "url": "https://www.cairo.gov.eg/ar/governorate-entities/companies/north-cairo-electricity-distribution-company/",
      "publisher": {
       "name": null,
       "domain": "cairo.gov.eg",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-60966a5af44c50aa"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Authority, and the scope anchor: the governorate lists NCEDC among its own entities and defines its service area as Cairo Governorate plus the southern extension of Qalyubia. Carries no subscriber numbers and nothing on this project.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-075af533ffc3773f",
      "title": "Toyota Tsusho — contract announcement (contractor)",
      "url": "https://www.toyota-tsusho.com/english/press/detail/201201_004720.html",
      "publisher": {
       "name": null,
       "domain": "toyota-tsusho.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-ff71c668683a08cc",
       "clm-a3d3cc6b4749c2a3"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Verifies the client (EEHC and NCEDC), the consortium with Elsewedy Electric, the Hitachi ABB distribution management system, approximately 500,000 meters to be replaced, a contract worth approximately JPY 10bn, and financing by a Japanese ODA loan through JICA. Also the source of the missed schedule: it states operation was expected to commence in mid-2023.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-caebafe77de4285d",
      "title": "Daily News Egypt — Japan-Egypt signing, 30 November 2020 (press)",
      "url": "https://www.dailynewsegypt.com/2020/11/30/japan-egypt-sign-agreement-for-north-cairo-electricity-distribution-management-advanced-meters/",
      "publisher": {
       "name": null,
       "domain": "dailynewsegypt.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-ff71c668683a08cc",
       "clm-e20d89b3b636d689"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": "2020-11-30",
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Dates the signing to 30 November 2020 and values the North Cairo component at about US$96M. Its figures for blackout reduction and theft prevention are stated as expectations at signing, not measured results, and are not used as impact in this entry.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-3e07126100005763",
      "title": "Al-Masry Al-Youm — ministry on the 490,000-meter replacement (press)",
      "url": "https://www.almasryalyoum.com/news/details/2100231",
      "publisher": {
       "name": null,
       "domain": "almasryalyoum.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-60966a5af44c50aa",
       "clm-a3d3cc6b4749c2a3",
       "clm-e20d89b3b636d689",
       "clm-a8fd239cce7d95ec"
      ],
      "temporal": {
       "publishedAt": "2020-11-30",
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "publication-and-record-dates-recorded"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Gives the deployment footprint (Helmiya, Matariya, Marg), the 490,000 meters, about US$90M with JICA financing, the new Helmiya sector control centre, a 30-month implementation period from November 2020, and the wider three-company programme of about 965,000 meters for about US$226M. Reports no installed count.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-e57aff04c6e20b7c",
      "title": "Iskraemeco — NCEDC project page (vendor)",
      "url": "https://iskraemeco.com/project/improving-energy-efficiency-and-reliability-of-distribution-networks-in-egypt-north-cairo-electricity-distribution-company/",
      "publisher": {
       "name": null,
       "domain": "iskraemeco.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-22ae6360e87f3d71",
       "clm-d18e6099314cec84"
      ],
      "temporal": {
       "publishedAt": "2024-12-20",
       "updatedAt": "2025-01-16",
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "publication-and-record-dates-recorded"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Technical detail: IE.5 single-phase and IE.7 three-phase meters, G3-PLC or GPRS/3G/4G modems, AC750 data concentrators, head-end system, five-year operation and maintenance. Decisive on the mechanism question: it describes remote reading only and mentions no prepayment functionality. Vendor material, so used for specification, not for outcomes.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-77901fa1fc0b5db1",
      "title": "Iskraemeco — factory acceptance test milestone (vendor)",
      "url": "https://iskraemeco.com/project/an-important-milestone-was-reached-in-a-project-to-modernize-and-digitize-the-electricity-distribution-networks-in-north-cairo/",
      "publisher": {
       "name": null,
       "domain": "iskraemeco.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "background",
      "claimRefs": [],
      "temporal": {
       "publishedAt": "2024-12-20",
       "updatedAt": "2025-01-16",
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "publication-and-record-dates-recorded"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Records the factory acceptance test of the IE.5 single-phase meters at Kranj, Slovenia, with NCEDC, TEPSCO, EEHC and Elsewedy Electric T&D present. The page carries no date, so it cannot be used to date progress; it is included only as confirmation that the meters reached acceptance testing.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-8f3ca69dd7dd95f9",
      "title": "Masrawy — installation begins, 23 April 2025 (press, operator statements)",
      "url": "https://www.masrawy.com/news/news_egypt/details/2025/4/23/2775749/",
      "publisher": {
       "name": null,
       "domain": "masrawy.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-22ae6360e87f3d71",
       "clm-a3d3cc6b4749c2a3",
       "clm-17706a5b253da48e"
      ],
      "temporal": {
       "publishedAt": "2025-04-23",
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "publication-and-record-dates-recorded"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. The most recent dated status found: NCEDC announces the start of installation in Hadayek el-Qubba, a first phase of about 50,000 meters against a 490,000 target under the Helmiyet el-Zaytoun control centre. Describes the meter as working without a top-up card, with an SMS bill paid via Fawry or online, electronic theft detection, remote disconnection for non-payment, and replacement at no cost to the subscriber.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-44033cfcc64746fd",
      "title": "Youm7 — NCEDC chairman on 2024/25 targets, 8 May 2024 (press, operator statements)",
      "url": "https://www.youm7.com/story/2024/5/8/%D9%83%D9%87%D8%B1%D8%A8%D8%A7%D8%A1-%D8%B4%D9%85%D8%A7%D9%84-%D8%A7%D9%84%D9%82%D8%A7%D9%87%D8%B1%D8%A9-%D9%86%D8%B3%D8%AA%D9%87%D8%AF%D9%81-%D8%AA%D8%B1%D9%83%D9%8A%D8%A8-217-%D8%A3%D9%84%D9%81-%D8%B9%D8%AF%D8%A7%D8%AF-%D8%B0%D9%83%D9%89-%D8%AE%D9%84%D8%A7%D9%84/6568260",
      "publisher": {
       "name": null,
       "domain": "youm7.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-35a3043d5784fa84",
       "clm-10595664b62d4ce3",
       "clm-d18e6099314cec84"
      ],
      "temporal": {
       "publishedAt": "2024-05-08",
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "publication-and-record-dates-recorded"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Chairman Hesham Afifi gives the FY2024/25 plan: 217,000 smart meters, of which 190,000 through the JICA project and 27,000 for large subscribers, plus 317,000 conversions to prepaid meters. This is the sentence that separates the two programmes and prevents them being reported as one.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-e3d5663ede4fe481",
      "title": "Ministry of International Cooperation — loan record (authority)",
      "url": "https://moic.gov.eg/project/161",
      "publisher": {
       "name": null,
       "domain": "moic.gov.eg",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-ff71c668683a08cc",
       "clm-a8fd239cce7d95ec"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Records the Electricity Distribution System Improvement Project for Alexandria, North Cairo and North Delta: donor Japan, loan of JPY 24,762M, beneficiary the Ministry of Electricity and Renewable Energy, locations including Cairo. Flagged discrepancy: this page dates the loan signature to 10 February 2022, while press reports refer to a 2016 loan agreement and an EPC contract signed in November 2020. The entry therefore asserts only the EPC contract date, not a loan date.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-c2bf434939c3fcbb",
      "title": "Salwa Ismail, Antipode 58(1), 2026 — prepaid meters in Egypt (peer-reviewed)",
      "url": "https://onlinelibrary.wiley.com/doi/10.1111/anti.70113",
      "publisher": {
       "name": null,
       "domain": "onlinelibrary.wiley.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-17706a5b253da48e"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetch blocked (HTTP 403); title, author, journal, volume and argument confirmed via the publisher listing and search results. Concerns the SEPARATE nationwide prepaid-card rollout, not this AMI project, and is cited only to show that the prepaid track has drawn peer-reviewed critical scrutiny while this one has none. Contains no figures used in this entry.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     }
    ],
    "coverage": {
     "claimsTotal": 10,
     "claimsMapped": 10,
     "sourcesTotal": 10,
     "sourcesUsedByClaims": 9,
     "sourcesWithPublicationDate": 5,
     "sourcesWithArchive": 0,
     "sourcesWithExactLocator": 0,
     "sourcesWithContentHash": 0
    },
    "limits": [
     "Publisher names and source languages have not yet been classified; domains are recorded without guessing.",
     "Existing source notes are descriptive locators, not page- or paragraph-exact citations.",
     "A missing archive, publication date or content hash is shown as null rather than inferred.",
     "The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim."
    ]
   }
  }
 ]
}