EFCOS: Metro Manila's Flood Telemetry and Floodway Gates
This overview was generated with AI from the public sources listed below and checked against them before publication. It has not had a complete human fact-check — treat it as a starting point and follow the sources.
7 sourced claims on this page, none individually verified yet — turn on “Sources in the text” to see each one.
How this atlas is made · What “last verified” means · What “source-checked” means · The full record behind this page
✎ Updated 22 Aug 2026 Publication date recorded for 9 sources. What changed →
Metro Manila publishes its river levels minute by minute, and says its gauges give 90 minutes of warning. The flood defences they warn about became the country's biggest corruption case — 421 projects flagged as ghosts.
what does this mean?
The strongest source is the operator's or the city's own reporting — an official report, dataset or press release. It grades who did the looking — not how well the project went. All four grades →Part of 1001 Smart Cities — 1,167 documented projects · 🏙️ 9 more in Manila · 🌊 Flood resilience guide · 🌱 Environment projects
The MMDA's Effective Flood Control Operation System, built with Japanese aid in 1993 and rehabilitated by JICA in 2014-2016, telemeters rainfall and river levels across the Pasig-Marikina basin from a control room at Rosario Pumping Station. Readings publish live on PAGASA's basin site with alert, alarm and critical thresholds. Crews decide how many Manggahan Floodway gates to open, keyed to the Sto. Niño gauge upstream. The defences those gauges warn about are another matter: a 2025 government validation flagged 421 flood-control projects nationwide as ghosts, and in May 2026 the Ombudsman charged a senator, a former public works secretary and two Metro Manila district engineers with plunder.
📊 Impact
The MMDA says mountain rain gauges give roughly 90 minutes of warning before water levels rise in the Marikina and Pasig rivers. An operator statement, not independently measured.
🎓 Lesson
Sensing and concrete are procured, funded and audited separately. Metro Manila measures its floods in public, minute by minute, while the works those measurements warn about became the country's largest corruption case.
Sources
Show 4 more sourcesShow fewer
📅 How old is the evidence?
Two clocks, kept apart: when this entry’s sources were published, and what has happened to its record in the atlas. Documented span: since 1993. 3 of 9 sources carry a publication date, from 29 October 2025 to 1 June 2026.
When the sources were published
- SunStar · pressSunStar — timeline of the flood control scandal
- GMA News · pressGMA News — 14 of 421 ghost flood control projects confirmed non-existent (19 Jan 2026)
- Manila Bulletin · pressManila Bulletin — anti-graft court orders arrests in the plunder case (1 Jun 2026)
What happened to this record
- Sources last read
- Entered the record
- Publication date recorded for 9 sources
Show your work What this page rests on and what it can’t tell you · all 7 claims with their sources · the forensic record
Evidence Passport · public beta 7 addressable claims, 9 source dossiers, one permanent baseline. The passport is unreviewed — an AI-assisted structural migration, not a human or expert endorsement. Every revision keeps a permanent copy under revision history.
Inspect the claims, one by one — verbatim text, sources and caveats for all 7
The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-6774b626101cc5a0
quantitative
The MMDA's Effective Flood Control Operation System, built with Japanese aid in 1993 and rehabilitated by JICA in 2014-2016, telemeters rainfall and river levels across the Pasig-Marikina basin from a control room at Rosario Pumping Station
Sources carrying this claim
clm-d40fc3d2d354c605
descriptive
Readings publish live on PAGASA's basin site with alert, alarm and critical thresholds
Sources carrying this claim
clm-7e0f7ddea8046dfe
descriptive
Crews decide how many Manggahan Floodway gates to open, keyed to the Sto. Niño gauge upstream
Sources carrying this claim
clm-9b9c3109a847735c
quantitative
a 2025 government validation flagged 421 flood-control projects nationwide as ghosts
Sources carrying this claim
clm-0b9055a22797d476
quantitative
in May 2026 the Ombudsman charged a senator, a former public works secretary and two Metro Manila district engineers with plunder
Sources carrying this claim
clm-93faf163c46875dc
quantitative
The MMDA says mountain rain gauges give roughly 90 minutes of warning before water levels rise in the Marikina and Pasig rivers
Sources carrying this claim
clm-4d06f3299a3d0e3b
descriptive
Metro Manila measures its floods in public, minute by minute, while the works those measurements warn about became the country's largest corruption case
Sources carrying this claim
Forensic record — source dossiers, gaps, hashes and the exact revision this page renders
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:c0d57f526ff25c47715df46269961d93867b8fd5e1b64f388dec8ffaf2a5cd76
- 7
- of 7 claims mapped
- 9
- source dossiers
- 4
- publication dates recorded
- 0
- archives linked
- 0
- exact locators
- 0
- content captures hashed
Governance facts carried by the record
- Operator
- Metropolitan Manila Development Authority (EFCOS unit), with PAGASA publishing the readings
- Actor types
- regional-government, national-government
- Funding model
- mixed
- Funding description
- Japanese development aid for the telemetry and its 2014-2016 restoration; MMDA operating budget
- Cost
- Not recorded
- Ownership
- Not recorded
- Decision rights
- Not recorded
- Exit conditions
- Not recorded
9 source dossiers
PAGASA — Pasig-Marikina-Tullahan flood forecasting and warning system (water level)
- Stable source ID
src-84ac08de89a28c6b- Publisher
- Name not classified · pasig-marikina-tullahanffws.pagasa.dost.gov.ph
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-22
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Primary and live: publishes real-time river levels for the Marikina, Pasig and Tullahan with alert, alarm and critical elevation columns and a legend distinguishing PAGASA stations from MMDA stations. Rendered with a 26 July 2026 timestamp, confirming the system is running.
- Claims linked
Official Gazette — MMDA flood reduction measures in Metro Manila
- Stable source ID
src-cafa7999c0b865ca- Publisher
- Name not classified · officialgazette.gov.ph
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-22
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Government briefing establishing that EFCOS is designed for operating the Manggahan Floodway and the Napindan Hydraulic Control Structure, fed by telemetered observation stations with units at the public works central office, PAGASA, Napindan and Rosario, plus warning posts along the floodway. Direct fetch returns 403; existence and wording confirmed via search.
- Claims linked
Inquirer — Metro gets a tweaked early flood warning system (2016)
- Stable source ID
src-e61a10c60e4b1bce- Publisher
- Name not classified · newsinfo.inquirer.net
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-22
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Supports the JICA-funded 2014-2016 rehabilitation, the March 2016 turnover to the MMDA, the control base at Rosario Pumping Station in Pasig, and the roughly 90-minute lead-time claim, quoted from the MMDA chairman.
- Claims linked
De La Salle University — thesis on the Manggahan and Napindan control structures
- Stable source ID
src-e57337c04525ea93- Publisher
- Name not classified · animorepository.dlsu.edu.ph
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-22
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Academic source for the operating practice: the MMDA bases gate control of the Manggahan and Napindan structures on the Sto. Niño water-level gauge upstream of the Rosario weir, supporting the claim that gate operation is a crewed decision on gauge thresholds rather than automatic actuation.
- Claims linked
SunStar — timeline of the flood control scandal
- Stable source ID
src-9422ae45f92d5d79- Publisher
- Name not classified · sunstar.com.ph
- Type / language
- web-page · language not classified
- Published
- 2025-10-29
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-22
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Dated chronology: the president ordered an audit of three years of flood-control projects in his 28 July 2025 address; on 11 August 2025 he named 15 contractors holding over 100 billion pesos in contracts since 2022; an Independent Commission for Infrastructure was created by executive order on 11 September 2025; Senate hearings opened 19 August 2025.
- Claims linked
Rappler — at least 421 ghost flood control projects uncovered nationwide (9 Oct 2025)
- Stable source ID
src-323d75a01dcae344- Publisher
- Name not classified · rappler.com
- Type / language
- web-page · language not classified
- Published
- 2025-10-09
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-22
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Source for the 421 figure: validation of about 8,000 public works projects, carried out with the defence department, armed forces, police and the planning agency, flagged at least 421 as non-existent, with roughly 100,000 projects still to be validated.
- Claims linked
GMA News — 14 of 421 ghost flood control projects confirmed non-existent (19 Jan 2026)
- Stable source ID
src-b1972d487c57e979- Publisher
- Name not classified · gmanetwork.com
- Type / language
- web-page · language not classified
- Published
- 2026-01-19
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-22
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Counterweight and precision check: the acting justice secretary told a Senate hearing that only 14 of the 421 were confirmed non-existent, adding that the department was not yet convinced the others were ghost projects. This justifies the word flagged rather than confirmed in the snippet.
- Claims linked
GMA News — Ombudsman files plunder and graft cases over flood control projects (28 May 2026)
- Stable source ID
src-9067a22c35d4ec2d- Publisher
- Name not classified · gmanetwork.com
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- 2026-05-28
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-22
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
The Metro Manila link that carries the scope: charges cover roughly 573 million pesos in alleged kickbacks from fiscal 2025 public works projects in the National Capital Region, naming a senator, a former public works secretary, two National Capital Region district engineers and an assistant district engineer. Charges only; no conviction.
- Claims linked
Manila Bulletin — anti-graft court orders arrests in the plunder case (1 Jun 2026)
- Stable source ID
src-269df8a693044748- Publisher
- Name not classified · mb.com.ph
- Type / language
- web-page · language not classified
- Published
- 2026-06-01
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-22
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
State of proceedings as of mid-2026: the anti-graft court found probable cause and ordered arrests on 1 June 2026, with no bail recommended on the plunder count. Trial pending.
- Claims linked
Known limits of this passport
- Publisher names and source languages have not yet been classified; domains are recorded without guessing.
- Existing source notes are descriptive locators, not page- or paragraph-exact citations.
- A missing archive, publication date or content hash is shown as null rather than inferred.
- The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim.
Continue exploring
Compare this project
Explore the wider context
📎 Cite this project
1001 Smart Cities (2026). “EFCOS: Metro Manila's Flood Telemetry and Floodway Gates” — Manila, Philippines. The Smart City Atlas. https://1001smartcities.org/projects/manila-flood-monitoring/ (last verified 2026-07-26). Data: CC BY 4.0.
The underlying data is free to reuse with attribution — see the open data page.