EFCOS: Metro Manila's Flood Telemetry and Floodway Gates
This overview was generated with AI from the public sources listed below and checked against them before publication. It has not had a complete human fact-check — treat it as a starting point and follow the sources.
10 sourced claims on this page, none individually verified yet — turn on “Sources in the text” to see each one.
How this atlas is made · What “last verified” means · What “source-checked” means · The full record behind this page
✎ Corrected 13 Oct 2026 4 sources added. · 2 revisions in all What changed →
Metro Manila publishes its river levels minute by minute, and says its gauges give 90 minutes of warning. The flood defences they warn about became one of the country's biggest corruption scandals — 421 projects flagged as ghosts.
what does this mean?
The strongest source is the operator's or the city's own reporting — an official report, dataset or press release. It grades who did the looking — not how well the project went. All four grades →Part of 1001 Smart Cities — 1,216 documented projects · 🏙️ 9 more in Manila · 🌊 Flood resilience guide · 🌱 Environment projects
The MMDA's Effective Flood Control Operation System, built with Japanese aid in 1993 and rehabilitated by JICA in 2014-2016, telemeters rainfall and river levels across the Pasig-Marikina basin from a control room at Rosario Pumping Station. Readings publish live on PAGASA's basin site with alert, alarm and critical thresholds. Crews decide how many Manggahan Floodway gates to open, keyed to the Sto. Niño gauge upstream. The defences those gauges warn about are another matter: a 2025 government validation flagged 421 flood-control projects nationwide as ghosts, and in May 2026 the Ombudsman charged a senator, a former public works secretary and two Metro Manila district engineers with plunder.
📊 Impact
The MMDA says mountain rain gauges give roughly 90 minutes of warning before water levels rise in the Marikina and Pasig rivers. An operator statement, not independently measured. In January 2026 the acting justice secretary told the Senate that only 14 of the 421 flagged projects had been confirmed non-existent. In September 2026 the anti-graft court dropped the former public works secretary as a co-accused so that he could testify as a state witness; the senator and the three other accused remained in detention.
🎓 Lesson
Sensing and concrete are procured, funded and audited separately. Metro Manila measures its floods in public, minute by minute, while the works those measurements warn about became one of the country's biggest corruption scandals.
Sources
Show 8 more sourcesShow fewer
📅 How old is the evidence?
Two clocks, kept apart: when this entry’s sources were published, and what has happened to its record in the atlas. Documented span: since 1993. 12 of 13 sources carry a publication date, from 27 September 2010 to 2 September 2026.
When the sources were published
- Official Gazette of the Republic of the Philippines · national governmentOfficial Gazette — MMDA flood reduction measures in Metro Manila
- Inquirer · pressInquirer — Metro gets a tweaked early flood warning system (2016)
- The Philippine Star · pressPhilstar — JICA hands over rehabilitated flood control project to MMDA (14 Mar 2016) · updated 16 May 2016
- De La Salle University · researchDe La Salle University — thesis on the Manggahan and Napindan control structures
- Rappler · pressRappler — at least 421 ghost flood control projects uncovered nationwide (9 Oct 2025)
- The Philippine Star · pressPhilstar — 421 flood control projects found to be ghosts (9 Oct 2025)
- SunStar · pressSunStar — timeline of the flood control scandal
- GMA News · pressGMA News — 14 of 421 ghost flood control projects confirmed non-existent (19 Jan 2026)
Show 4 more dated sourcesShow fewer
- GMA News · pressGMA News — Ombudsman files plunder and graft cases over flood control projects (28 May 2026)
- Manila Bulletin · pressManila Bulletin — anti-graft court orders arrests in the plunder case (1 Jun 2026)
- The Philippine Star · pressPhilstar — Jinggoy Estrada ordered arrested for plunder (1 Jun 2026)
- SunStar · pressSunStar — Sandiganbayan discharges Bonoan as co-accused (2 Sep 2026)
What happened to this record
Show your work What this page rests on and what it can’t tell you · all 10 claims with their sources · the forensic record
Evidence file · public beta 10 addressable claims, 13 source dossiers, one permanent baseline. The file is unreviewed — an AI-assisted structural migration, not a human or expert endorsement. Every revision keeps a permanent copy under revision history.
Inspect the claims, one by one — verbatim text, sources and caveats for all 10
The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-6774b626101cc5a0
quantitative
The MMDA's Effective Flood Control Operation System, built with Japanese aid in 1993 and rehabilitated by JICA in 2014-2016, telemeters rainfall and river levels across the Pasig-Marikina basin from a control room at Rosario Pumping Station
Sources carrying this claim
clm-d40fc3d2d354c605
descriptive
Readings publish live on PAGASA's basin site with alert, alarm and critical thresholds
Sources carrying this claim
clm-7e0f7ddea8046dfe
descriptive
Crews decide how many Manggahan Floodway gates to open, keyed to the Sto. Niño gauge upstream
Sources carrying this claim
clm-9b9c3109a847735c
quantitative
a 2025 government validation flagged 421 flood-control projects nationwide as ghosts
Sources carrying this claim
clm-0b9055a22797d476
quantitative
in May 2026 the Ombudsman charged a senator, a former public works secretary and two Metro Manila district engineers with plunder
Sources carrying this claim
clm-93faf163c46875dc
quantitative
The MMDA says mountain rain gauges give roughly 90 minutes of warning before water levels rise in the Marikina and Pasig rivers
Sources carrying this claim
clm-07fbb6d8e6219089
quantitative
In January 2026 the acting justice secretary told the Senate that only 14 of the 421 flagged projects had been confirmed non-existent.
Sources carrying this claim
clm-10e947e9ed7aaec8
quantitative
In September 2026 the anti-graft court dropped the former public works secretary as a co-accused so that he could testify as a state witness
Sources carrying this claim
clm-bdcd1bdd34711912
descriptive
the senator and the three other accused remained in detention
Sources carrying this claim
clm-b28fe7030bc64a76
descriptive
Metro Manila measures its floods in public, minute by minute, while the works those measurements warn about became one of the country's biggest corruption scandals
Sources carrying this claim
Forensic record — source dossiers, gaps, hashes and the exact revision this page renders
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:c0311af2b81ac11af62a9aca9fe32bd0194d55f142a297822193d16e06c1564c
- 10
- of 10 claims mapped
- 13
- source dossiers
- 10
- publication dates recorded
- 0
- archives linked
- 0
- exact locators
- 0
- content captures hashed
Governance facts carried by the record
- Operator
- Metropolitan Manila Development Authority (EFCOS unit), with PAGASA publishing the readings
- Actor types
- regional-government, national-government
- Funding model
- mixed
- Funding description
- Japanese development aid for the telemetry and its 2014-2016 restoration; MMDA operating budget
- Cost
- Not recorded
- Ownership
- Not recorded
- Decision rights
- Not recorded
- Exit conditions
- Not recorded
13 source dossiers
PAGASA — Pasig-Marikina-Tullahan flood forecasting and warning system (water level)
- Stable source ID
src-84ac08de89a28c6b- Publisher
- Name not classified · pasig-marikina-tullahanffws.pagasa.dost.gov.ph
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-10-11
- Dossier created
- 2026-10-13
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Live dashboard of the Pasig-Marikina-Tullahan flood forecasting and warning system: real-time river levels for the Marikina, Pasig and Tullahan with alert, alarm and critical elevation columns and a legend distinguishing PAGASA stations from MMDA stations. A continuously updated page, so it carries no publication date.
- Claims linked
Official Gazette — MMDA flood reduction measures in Metro Manila
- Stable source ID
src-cafa7999c0b865ca- Publisher
- Name not classified · officialgazette.gov.ph
- Type / language
- web-page · language not classified
- Published
- 2010-09-27
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-10-11
- Dossier created
- 2026-10-13
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Government briefing establishing that EFCOS is designed for operating the Manggahan Floodway and the Napindan Hydraulic Control Structure, fed by telemetered observation stations with units at the public works central office, PAGASA, Napindan and Rosario, plus warning posts along the floodway.
- Claims linked
Inquirer — Metro gets a tweaked early flood warning system (2016)
- Stable source ID
src-e61a10c60e4b1bce- Publisher
- Name not classified · newsinfo.inquirer.net
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-10-11
- Dossier created
- 2026-10-13
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Reports the JICA-funded rehabilitation and the March 2016 turnover to the MMDA, the control base at Rosario Pumping Station in Pasig, and the MMDA's statement that the system warns at least an hour and a half before water levels rise.
- Claims linked
Philstar — JICA hands over rehabilitated flood control project to MMDA (14 Mar 2016)
- Stable source ID
src-e27817efb111b251- Publisher
- Name not classified · philstar.com
- Type / language
- web-page · language not classified
- Published
- 2016-03-14
- Updated
- 2016-05-16
- Source last checked
- No source-level check date
- Record last verified
- 2026-10-11
- Dossier created
- 2026-10-13
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
JICA handed the rehabilitated EFCOS to the MMDA at Rosario Pumping Station after 15 months of repair under an October 2014 memorandum covering the telemetry and radio systems; Phase 1 was completed in 1993 for real-time rainfall and water-level collection across the Pasig-Marikina-Laguna Lake complex; the MMDA has 18 observation stations and nine warning posts along the Manggahan Floodway.
- Claims linked
De La Salle University — thesis on the Manggahan and Napindan control structures
- Stable source ID
src-e57337c04525ea93- Publisher
- Name not classified · animorepository.dlsu.edu.ph
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-10-11
- Dossier created
- 2026-10-13
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Undergraduate thesis modelling the Manggahan and Napindan structures during Typhoon Ulysses; states that in real practice MMDA-EFCOS bases the gate controls of these structures on the Sto. Niño water level gauge station upstream of the Rosario weir.
- Claims linked
SunStar — timeline of the flood control scandal
- Stable source ID
src-9422ae45f92d5d79- Publisher
- Name not classified · sunstar.com.ph
- Type / language
- web-page · language not classified
- Published
- 2025-10-29
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-10-11
- Dossier created
- 2026-10-13
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Dated chronology calling the scandal one of the biggest corruption controversies of 2025: the president ordered an audit of three years of flood-control projects on 28 July 2025; on 11 August 2025 he named 15 contractors holding over 100 billion pesos in contracts since 2022; Senate hearings opened 19 August 2025; an Independent Commission for Infrastructure was created by executive order on 11 September 2025.
- Claims linked
Rappler — at least 421 ghost flood control projects uncovered nationwide (9 Oct 2025)
- Stable source ID
src-323d75a01dcae344- Publisher
- Name not classified · rappler.com
- Type / language
- web-page · language not classified
- Published
- 2025-10-09
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-10-11
- Dossier created
- 2026-10-13
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Reports the public works secretary's 9 October 2025 announcement that validation of about 8,000 flood-control projects with security and planning agencies flagged 421 as non-existent, with many more still to be validated.
- Claims linked
Philstar — 421 flood control projects found to be ghosts (9 Oct 2025)
- Stable source ID
src-563c8abfd3aa72e6- Publisher
- Name not classified · philstar.com
- Type / language
- web-page · language not classified
- Published
- 2025-10-09
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-10-11
- Dossier created
- 2026-10-13
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Same announcement: the public works department said it found 421 ghost flood-control projects out of the 8,000 it investigated with the armed forces, the defence department and the planning department, and the secretary stressed these were initial figures, with around 100,000 projects still to be validated.
- Claims linked
GMA News — 14 of 421 ghost flood control projects confirmed non-existent (19 Jan 2026)
- Stable source ID
src-b1972d487c57e979- Publisher
- Name not classified · gmanetwork.com
- Type / language
- web-page · language not classified
- Published
- 2026-01-19
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-10-11
- Dossier created
- 2026-10-13
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
The acting justice secretary told a Senate hearing that only 14 of the 421 projects initially flagged as ghosts had been confirmed non-existent and that the department was not yet convinced about the others; a public works undersecretary said the validation might have to restart after wrong grid coordinates were used.
- Claims linked
GMA News — Ombudsman files plunder and graft cases over flood control projects (28 May 2026)
- Stable source ID
src-9067a22c35d4ec2d- Publisher
- Name not classified · gmanetwork.com
- Type / language
- web-page · language not classified
- Published
- 2026-05-28
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-10-11
- Dossier created
- 2026-10-13
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
The Ombudsman filed one plunder and two graft cases against Senator Jinggoy Estrada over alleged kickbacks of over 573 million pesos tied to budget insertions in the fiscal 2025 public works portfolio; the former public works secretary, two DPWH National Capital Region district engineers and an assistant district engineer are on the charge sheet. Charges only; no conviction.
- Claims linked
Manila Bulletin — anti-graft court orders arrests in the plunder case (1 Jun 2026)
- Stable source ID
src-269df8a693044748- Publisher
- Name not classified · mb.com.ph
- Type / language
- web-page · language not classified
- Published
- 2026-06-01
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-10-11
- Dossier created
- 2026-10-13
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
The anti-graft court found probable cause and ordered arrests in the plunder case on 1 June 2026, with no bail set.
- Claims linked
Philstar — Jinggoy Estrada ordered arrested for plunder (1 Jun 2026)
- Stable source ID
src-675bc300bdb9b386- Publisher
- Name not classified · philstar.com
- Type / language
- web-page · language not classified
- Published
- 2026-06-01
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-10-11
- Dossier created
- 2026-10-13
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
The anti-graft court's Fifth Division issued a plunder arrest warrant on 1 June 2026 against the senator, the former public works secretary and three DPWH engineers, days after he posted bail on a separate graft charge.
- Claims linked
SunStar — Sandiganbayan discharges Bonoan as co-accused (2 Sep 2026)
- Stable source ID
src-2603bd037dd83602- Publisher
- Name not classified · sunstar.com.ph
- Type / language
- web-page · language not classified
- Published
- 2026-09-02
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-10-11
- Dossier created
- 2026-10-13
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
The anti-graft court granted the Ombudsman's request to discharge the former public works secretary as a co-accused so he could serve as a state witness, and recalled his arrest warrant; the senator and the three other accused were detained at the Quezon City Jail.
- Claims linked
Known limits of this file
- Publisher names and source languages have not yet been classified; domains are recorded without guessing.
- Existing source notes are descriptive locators, not page- or paragraph-exact citations.
- A missing archive, publication date or content hash is shown as null rather than inferred.
- The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim.
Continue exploring
Compare this project
Explore the wider context
📎 Cite this project
1001 Smart Cities (2026). “EFCOS: Metro Manila's Flood Telemetry and Floodway Gates” — Manila, Philippines. The Smart City Atlas. https://1001smartcities.org/projects/manila-flood-monitoring/ (last verified 2026-10-11). Data: CC BY 4.0.
The underlying data is free to reuse with attribution — see the open data page.