Rio's 28 km tram network opened in June 2016 across the Porto Maravilha port regeneration and the Olympic works
Permanent project revision
Revision 2026-08-22-evidence-baseline · effective 2026-07-26
Current revision. This is the snapshot used by the live entity page.
Created the first structured Evidence Passport with 13 claims and 7 source dossiers.
sha256:87b1e04adf64f5a4cddd1095b9f9c7b517d64d78248000b6cbbeb10399cdb800
add /evidencePassport — Added claim-level evidence mapping and source dossiers.add /revisionHistory — Established a permanent, hash-addressed baseline revision.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-d1d3ab621fd5fd3e
quantitative
Rio's 28 km tram network opened in June 2016 across the Porto Maravilha port regeneration and the Olympic works
clm-e7e5a3eaa3bd5beb
descriptive
running catenary-free on Alstom's ground-level power supply
clm-783bf7b5c8982be3
descriptive
It takes no cash on board: riders must hold a loaded Jaé card or an app QR code
clm-78ec0dc438382c61
quantitative
mandatory for every VLT passenger since 2 August 2025
clm-1dbee7e7497868bc
descriptive
Station machines sell and top up cards
clm-1db7df43ffeda186
descriptive
no coins, and they give no change
clm-599618ad43153ea0
quantitative
A R$170 fine was for years applied to people who simply boarded without a card
clm-015070f69b28ed2f
quantitative
until a 2021 court ruling held that boarding without a validated ticket is not in itself grounds for one
clm-cfb744b3cddb444f
quantitative
25.2 million boardings in 2025, up 11.2% on 2024 (operator figures)
clm-6182e37a6d7c290c
quantitative
Rio's concession authority puts network capacity at 300,000 passengers/day — a design figure, not a demand forecast
clm-0c1a2ee4e8cfc344
descriptive
A cashless fare regime quietly converts 'could not pay' into 'broke the rules'
clm-4311752713123c58
descriptive
It took prosecutors and a court to establish that boarding without a valid ticket is not in itself unlawful conduct
clm-713971798d443975
descriptive
the penalty, not the card, was doing the excluding
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:87b1e04adf64f5a4cddd1095b9f9c7b517d64d78248000b6cbbeb10399cdb800
src-5895cd007aa54121Operator FAQ, fetched OK. Carries the load-bearing fare claims: cash is not accepted on board ('Não. Você deve ter o cartão carregado'); Jaé card or app QR code; station self-service machines accept 'cartões de crédito, débito ou cédulas' but 'não aceitam moedas' and 'os terminais não dão troco'; machines at every station except Praia Formosa; fare R$5.00; BUC integration 2h30 with municipal buses, 3h intermunicipal. Does NOT list contactless bank cards for VLT validators — see note on the metro source below.
src-0f3fde86b571f78aOperator, 8 July 2025, fetched OK. Sentence-level source for: Jaé exclusive for gratuities from 5 July 2025 and mandatory for all passengers from 2 August 2025; fines R$170 rising to R$255 on repeat under municipal law; exit-gate validation introduced at Terminal Gentileza from 9 July 2025 to curb fare evasion; fare R$4.70 at that date (since raised to R$5.00).
src-bc9a2a04def36a2f13 November 2021, fetched OK. The counterweight the entry is built on: acting on a suit by the MPRJ's 1st consumer-protection prosecutor's office, the court held that travelling without a valid ticket is not in itself unlawful, so a fine cannot be imposed for merely lacking a card or sufficient balance; fines are limited to passengers who refuse to disembark, and the concessionaire was ordered to enable payment by mobile device. The concessionaire replied that it had not been notified and that fines are the Municipal Guard's responsibility.
src-07d4a933088d0f614 July 2019, fetched OK. Financial counterweight: the consortium sought rescission citing ≈R$150m of unpaid municipal investment obligations and the city's refusal to authorise Line 3; states Lines 1 and 2 were carrying 80,000 passengers a day and that the concession 'only survived due to extra shareholder contributions'. The consortium projected 150,000/day if Line 3 opened and downtown bus routes were reorganised. Article does not report the outcome.
src-4901b76d098079abOfficial concession authority, fetched OK. Source for cost R$1.157bn split R$532M federal PAC / R$625M PPP; 28 km network; 32 trams of 420 passengers; APS ground-level power supply. Critically, it words the 300,000 figure as what the system 'can transport' — a CAPACITY, not a demand forecast. Note pt.wikipedia gives a slightly different cost split (R$525M/R$632M); the official figures are used here.
src-22d925990508bc86Operator, February 2026, fetched OK. Sentence-level source for the impact figure: 25.2 million boardings in 2025, +11.2% on 2024, the largest percentage growth among the group's rail assets; 2 million boardings in December 2025 (+4.5%). No daily average is stated by the operator — the '84,000/day' and '95,000/day' figures circulating in the press are not used here because their basis (calendar day vs. weekday) is undefined and they conflict.
src-888a7cc75224cfccSupplier source, June 2026. FETCH FAILED (HTTP 403); content known only from search-result summaries, so nothing from it is used as a standalone load-bearing number. Basis for the traction description — APS ground-level supply on ~80% of the network with onboard supercapacitor storage (SRS) on the remainder — which is independently corroborated by English Wikipedia. Alstom also claims Rio was the second city in the world with a 100% catenary-free network, after Dubai; that superlative is a supplier claim and is deliberately kept out of the snippet. The release's 10-year passenger totals are irreconcilable with other outlets (126m vs 145m vs 180m) and are not used.