Mumbai Water Distribution Improvement Programme

Revision 2026-08-26-claim-mapping · effective 2026-07-26

Current revision. This is the snapshot used by the live entity page.

unreviewed

Added a five-claim evidence mapping and a sourced lesson; the impact now carries the wind-up terms and the state of the network afterwards alongside the audit's 18.60 per cent.

sha256:dc9a8a4447430271b01eacbe831bc4747deb28fcf342a707b2575da6d23143f0

Change set

  • replace /snapshot/projectFingerprint — Updated projectFingerprint to the current sourced project record.
  • replace /snapshot/claims — Updated claims to the current sourced project record.
  • replace /snapshot/sources — Updated sources to the current sourced project record.
5
of 5 claims mapped
4
source dossiers
4
publication dates recorded
1
archives linked
0
exact locators
0
content captures hashed

Claims, one by one

The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.

Claim 1 clm-36b7787fe144b77f quantitative
In 2014 the BMC hired Suez Environnement India under a 275 crore rupee contract to GIS-map Mumbai's poorly documented water network, zone it into district metered areas, meter connections, detect leaks and move two wards to continuous pressurised supply
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The audit report as reported names the 2014 award to Suez Environment India at about 276 crore rupees and the two pilot wards; the 2021 report lists the ten contracted services including GIS mapping and leakage detection.
Caveat
The reported contract value is about 276 crore rupees; the entry's 275 is a rounding of the same award.

Sources carrying this claim

  1. Mumbai Live — CAG questions BMC on 24x7 water supply project
  2. Construction World — BMC to wind up 24-hr water supply project (9 March 2021)
Claim 2 clm-dc7e8358d63c211e quantitative
The five-year deadline passed in July 2019 with roughly a fifth of the work done; the contractor filed for arbitration and the BMC wound the programme up in March 2021 after paying about 47 crore rupees
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The March 2021 report states that the contractor filed for arbitration after the five-year deadline expired in July 2019, that about 20 per cent of the work was complete and that about 47 crore rupees had been paid.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Construction World — BMC to wind up 24-hr water supply project (9 March 2021)
  2. Mumbai Live — CAG questions BMC on 24x7 water supply project
Claim 3 clm-a5ee5976d633f0df quantitative
The national auditor found that at the July 2019 deadline only 18.60% of the contract had been executed by monetary value
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The report quotes the audit directly: in terms of overall monetary value it was only 18.60 per cent.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Mumbai Live — CAG questions BMC on 24x7 water supply project
Claim 4 clm-ca9f7cf912f9c8e8 quantitative
Mumbai still supplies 3,950 million litres a day against demand of 4,200, and an independent estimate puts non-revenue water at 38% including all unmetered consumption, against a national norm of 15%
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The think-tank analysis gives supply of 3,950 MLD against demand of 4,200 MLD and estimated non-revenue water of 38 per cent including unmetered consumption, against a national norm of 15 per cent.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Observer Research Foundation — Tackling water stress in Mumbai (6 June 2023)
Claim 5 clm-ed3e39efe0d806e3 descriptive
The instruments Mumbai runs today, SCADA and metered-district pilots, are not attributed by any source to this programme
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The 2026 trade survey of what the corporation operates lists SCADA, district-metered-area pilots, automated meter reading and smart-meter pilots without attributing any of it to this contract.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Indian Infrastructure — Modernising Systems: ULB initiatives to strengthen water networks (4 June 2026)

Source dossiers and revision state

This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.

unreviewed Revision 2026-08-26-claim-mapping effective 2026-07-26 · created 2026-08-26

Awaiting operator and domain-expert review; publication of this revision implies neither.

Erratum on this revision's envelope. The snapshot, its hash and its permanent link are untouched.

  • createdAt previously read 2026-08-26T23:21:00Z. The batching script that produced this revision advanced createdAt into the future to satisfy the strictly-increasing order the validator requires per entity. The value never recorded a real event; the corrected value is the moment the revision provably existed in the repository. Corrected to 2026-08-26T23:13:33Z on 2026-08-27; evidence: first appears in commit 5e17071a63, committed 2026-08-26T23:13:33Z.
sha256:dc9a8a4447430271b01eacbe831bc4747deb28fcf342a707b2575da6d23143f0
5
of 5 claims mapped
4
source dossiers
4
publication dates recorded
1
archives linked
0
exact locators
0
content captures hashed

Governance facts carried by the record

Operator
Brihanmumbai Municipal Corporation, Hydraulic Engineer's Department; contractor Suez Environnement India
Actor types
city-government, private
Funding model
public
Funding description
Not recorded
Cost
Not recorded
Ownership
Not recorded
Decision rights
Not recorded
Exit conditions
Not recorded

4 source dossiers

Mumbai Live — CAG questions BMC on 24x7 water supply project mumbailive.com · 3 linked claims

Open original source ↗

Stable source ID
src-f2e68171662bd995
Publisher
Name not classified · mumbailive.com
Type / language
web-page · language not classified
Published
2020-01-31
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-26
Retrieved copy
No local capture recorded
Archive
Open archived copy ↗ · 2025-07-23
Content hash
No captured content hash
Locator
Open the recorded source note

Reports the national audit finding: 2014 award to Suez Environnement India at 276 crore rupees, only 18 per cent of work (18.60 per cent by monetary value) complete at the July 2019 deadline, pilot wards T (Mulund) and H West (Bandra).

Descriptive only — not page/paragraph exact
Construction World — BMC to wind up 24-hr water supply project (9 March 2021) constructionworld.in · 2 linked claims

Open original source ↗

Stable source ID
src-116ac777187214ac
Publisher
Name not classified · constructionworld.in
Type / language
web-page · language not classified
Published
2021-03-09
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-26
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Confirms the March 2021 discontinuation: the contractor filed for arbitration after the deadline expired; about 20 per cent of work complete; about 47 crore rupees paid; lists the ten contracted services including GIS mapping and leakage detection.

Descriptive only — not page/paragraph exact
Observer Research Foundation — Tackling water stress in Mumbai (6 June 2023) orfonline.org · 1 linked claim

Open original source ↗

Stable source ID
src-a66fe7bd8ba2f4d3
Publisher
Name not classified · orfonline.org
Type / language
web-page · language not classified
Published
2023-06-06
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-26
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Independent think-tank analysis: supply of 3,950 MLD against 4,200 MLD demand; estimated non-revenue water of 38 per cent including unmetered consumption as of 2016, against a national norm of 15 per cent; slums receive 45 lpcd against 135 lpcd in residential buildings.

Descriptive only — not page/paragraph exact
Indian Infrastructure — Modernising Systems: ULB initiatives to strengthen water networks (4 June 2026) indianinfrastructure.com · 1 linked claim

Open original source ↗

Stable source ID
src-aaaf93db2a966a82
Publisher
Name not classified · indianinfrastructure.com
Type / language
web-page · language not classified
Published
2026-06-04
Updated
2026-06-16
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-26
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Current-state check on what BMC operates after the programme: SCADA plus district-metered-area pilots, automated meter reading, smart-meter pilots. None of it is attributed by the source to this programme, so none is claimed here.

Descriptive only — not page/paragraph exact
Known limits of this passport
  • Publisher names and source languages have not yet been classified; domains are recorded without guessing.
  • Existing source notes are descriptive locators, not page- or paragraph-exact citations.
  • A missing archive, publication date or content hash is shown as null rather than inferred.
  • The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim.