Montreal awarded a consortium of Dessau and Simard-Beaudry a roughly CA$356M, 25-year contract in late 2007 to meter non-residential buildings and optimise the water network
Permanent project revision
Revision 2026-08-21-source-dates · effective 2026-07-26
Current revision. This is the snapshot used by the live entity page.
Record the publication date of each source that states one; a source that publishes no date is marked null, and one that shows only a revision carries `updated` instead.
sha256:3c5ec1bff8e6ede4b5d658400d3fda7972dae52fe05556b3bddfdf957d6141c2
replace /snapshot/projectFingerprint — Updated projectFingerprint to the current sourced project record.replace /snapshot/sources — Updated sources to the current sourced project record.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-00d87f3658f66f62
quantitative
Montreal awarded a consortium of Dessau and Simard-Beaudry a roughly CA$356M, 25-year contract in late 2007 to meter non-residential buildings and optimise the water network
clm-7fc3ddda68f409ab
quantitative
Auditor General Jacques Bergeron judged the tender 'trop vite, trop gros et trop cher' (too fast, too big, too expensive) and the city cancelled it in September 2009
clm-2875eaa5ddfd2911
quantitative
arbitration then cost Montreal more than CA$13M, which it sued to recover in 2018
clm-dcce984a75103bb2
quantitative
The city restarted in 2012 with three smaller contracts worth about CA$55M
clm-380dfbc16fd959b5
quantitative
by 2023 had fitted roughly 19,500 industrial, commercial and institutional buildings with remote-read meters
clm-f9fff3d0b528aba0
quantitative
Volumetric billing for those buildings began on 1 January 2023
clm-5fd5cade9f29d7e3
quantitative
the city's own data put overconsumption and losses at 30%, the same as in 2015, and its 2021 water-use report rated infrastructure leakage high for the Pierrefonds network and very high for Lachine and Atwater-Charles-J.-Des Baillets
clm-e2f848592299973a
quantitative
Montreal cancelled a CA$356M, 25-year deal and then bought roughly the same meters for about CA$55M over the following decade — proof the original price was the scandal, not the meters
clm-68e8ed1966c37528
descriptive
the readings are withheld from the open data as commercially confidential
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:3c5ec1bff8e6ede4b5d658400d3fda7972dae52fe05556b3bddfdf957d6141c2
src-f1479707bacc5958Operator page, the obligation and the data layer: 'Tout batiment destine en partie ou en totalite a un usage non residentiel, qu'il soit existant ou a construire, doit etre muni d'un compteur d'eau.' and 'Ils sont munis d'un systeme de lecture a distance et sont conformes au standard NSF61.' (Every wholly or partly non-residential building, existing or to be built, must have a water meter; the meters have a remote-reading system and meet NSF61.) Also states the Quebec drinking-water strategy target of a 20% cut in production by 2025.
src-8fb1d58f080f2400Operator page dating the billing layer: 'Depuis le 1er janvier 2023, les immeubles qui sont en partie ou en totalite destines a un usage non residentiel paient une tarification selon le volume d'eau consomme.' (Since 1 January 2023 non-residential buildings pay by volume consumed.) 2026 rates run from 0 $/m3 below 1,000 m3 to 0,690 $/m3 above 100,000 m3; bills follow the year after the meters are read.
src-9d62083b565dc46eThe open register, updated monthly: 'Cette liste contient les compteurs d'eau exploites par le Service de l'eau de la Ville de Montreal.' Fields include meter number, diameter, mechanical or electronic type, operating status, address, borough and obfuscated coordinates. The limit is stated on the same page: 'les consommations liees a ces compteurs ne seront pas publiees' (consumption for these meters will not be published), for reasons of industrial confidentiality.
src-a752f1d56cd1fb7bNames the instrument still in force: 'Reglement sur la mesure de la consommation de l'eau dans les ICI — Codification administrative (RCG 07-031)'. The metering by-law outlived the contract meant to implement it.
src-110b0ff2cb7762b7The replacement programme and the auditor general's verdict in one piece: three separate contracts for '2900 compteurs d'eau pour les industries, commerces et institutions', 16,200 meters planned by 2018, and 'L'ensemble du projet s'eleve a 55 millions $, assume par les etablissements concernes' (the whole project comes to $55M, borne by the establishments concerned). Context given: the 2009 cancellation of the $356M GENIeau contract, which the auditor general had judged 'trop vite, trop gros et trop cher'.
src-07ed4af423e9206bThe bill and the civil claim: the 2007 award of a $356M contract to the GENIeau consortium, its 2009 termination after the auditor general's report, the 2012 arbitration ordering the city to pay, and a claim of '10,2 M$ en compensation et une penalite de 3,1 M$, plus les frais d'arbitrage et d'experts, pour un total d'un peu plus de 14 M$'. Defendants named: Frank Zampino, Tony Accurso, Paolo Catania, Simard-Beaudry and Groupe SM. The collusion described is an allegation in the city's pleading.
src-a055090865455c52Carries the two current numbers, both attributed to the City's bilan de l'usage de l'eau potable: 'Il aura fallu une dizaine d'annees pour que la Ville de Montreal dote l'ensemble des ICI de compteurs d'eau, pour un total de 19 500 compteurs installes' and 'Les donnees de la Ville de Montreal montrent que le taux de surconsommation et de pertes, qui s'eleve actuellement a 30%, est le meme qu'en 2015.' Also, from the 2021 bilan: 'un IFI eleve pour le reseau de Pierrefonds et tres eleve pour ceux de Lachine et Atwater-Charles-J.-Des Baillets.'
src-ddb590c9952759b2The cancellation itself, September 2009: Mayor Gerald Tremblay cancelled the contract after auditor general Jacques Bergeron's report, and dismissed city manager Claude Leger and corporate affairs director Robert Cassius de Linval. Fetch returned 403; outlet, headline and content confirmed through search results, and the year and the causal link are corroborated by the two Journal Metro articles above. La Presse ran the same story on 22 September 2009 ('Tremblay annule le contrat des compteurs d'eau', also 403).