Harare scrapped its South African BIQ enterprise-resource-planning system in May 2019
Permanent project revision
Revision 2026-11-04-evidence-baseline · effective 2026-11-03
Current revision. This is the snapshot used by the live entity page.
Created the first structured Evidence Passport with 17 claims and 7 source dossiers.
sha256:47c207b23b78ec28f9f4587da181e6e37b9a2aa10cc39537a6ad8cb4ea14aac6
add /evidencePassport — Added claim-level evidence mapping and source dossiers.add /revisionHistory — Established a permanent, hash-addressed baseline revision.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-5ad004c28390858c
quantitative
Harare scrapped its South African BIQ enterprise-resource-planning system in May 2019
clm-9900284327c279f0
quantitative
at 92% implementation
clm-bac6d28d73bdaaf8
descriptive
after its audit committee found it 'could not generate a reliable trial balance'
clm-775e279f51d4db46
descriptive
then ran the capital's billing largely manually for five years
clm-5b0325135efe503e
quantitative
by 2024 the mayor conceded the city did not know how many households it was billing
clm-9a9e69d7fd266a84
quantitative
The procurement regulator blocked a US$57M foreign ERP and a US$2.8M billing system
clm-9120af0b4ac5f770
quantitative
on the Auditor-General's recommendation the council resolved in April 2024 to re-engage the original vendor for US$2.6M
clm-71389aed7f355968
quantitative
but its first procurement request reached the regulator only in June 2025
clm-f26aa4c166ab6ff7
quantitative
On 20 April 2026 the city began switching its 43 collection centres to BIQ
clm-54923df4a9bfc784
quantitative
the 2026 budget calls full deployment a 'non-negotiable commitment'
clm-f3d793d9ef7f9c4a
descriptive
separate from the billing layer bundled into the city's prepaid-water PPP
clm-0c3e866c4a381061
quantitative
Harare's suspended town clerk told the Cheda Commission of Inquiry the city could be losing over US$70M a year in uncollected revenue without a working ERP
clm-1cf096aa432e218a
quantitative
an estimated US$350M over five years
clm-78a132ba208a184b
quantitative
with collections at 40-50% of potential revenue against a budget above US$500M
clm-a5a761d196d22c89
quantitative
Harare dropped BIQ at 92% implementation
clm-c3dab7c84965c191
descriptive
ran on manual processes for five years while the procurement regulator blocked two replacements
clm-ea12bf75ee76ca69
descriptive
ended up re-hiring the original vendor
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:47c207b23b78ec28f9f4587da181e6e37b9a2aa10cc39537a6ad8cb4ea14aac6
src-20bbd8063a40aa50May 2019 scrapping: BIQ at 92% implementation; audit committee found it 'could not generate a reliable trial balance'; high running costs.
src-5835342958815910Council resolution of 30 April 2024 re-engaging Quill Associates to restore BIQ for US$2.6M in staged payments, on the Auditor-General's recommendation; progress on 7 of 10 modules by July 2024.
src-f3dd158b569da943Suspended town clerk Chisango's testimony to the Cheda Commission (Nov 2024): ≈US$70M/yr uncollected, ≈US$350M over five years, collections at 40-50%; PRAZ blocked a US$57M foreign ERP and a US$2.8M billing system; a US$350,000 local HIT system was rejected.
src-882ba1c3d924a174Names BIQ as the city's ERP; US$12.95M for ICT modernisation and ERP roll-out in 2026; calls comprehensive ERP implementation 'a central, non-negotiable commitment'; projects 19% revenue growth partly from ERP billing efficiency.
src-91a2549e70054184Residents' reaction to Mayor Jacob Mafume telling a full council meeting that the council had no information on the number of households it bills.
src-dcc92f9bdb74810dPRAZ granted direct-procurement approval in October 2024, on recommendations from Parliament and Auditor-General Mildred Chiri, to re-hire Quill Associates to reactivate BIQ; the city submitted its first procurement request only in June 2025, at US$1.7 million for full implementation of all BIQ modules.
src-c7160dce9c925f45The city's head of revenue collection announces the BIQ ERP rollout from 20 April 2026, installing the platform across all 43 collection centres and deactivating the old system.