Harare scrapped its South African BIQ enterprise-resource-planning system in May 2019 — at 92% implementation, after its audit committee found it 'could not generate a reliable trial balance' — then ran the capital's billing largely manually for five years; by 2024 the mayor conceded the city did not know how many households it was billing. After the procurement regulator blocked a US$57M foreign ERP and a US$2.8M billing system, the council re-engaged the original vendor in April 2024 for US$2.6M on the Auditor-General's recommendation. The reinstated BIQ is rolling out in phases, and the 2026 budget calls full deployment a 'non-negotiable commitment' — separate from the billing layer bundled into the city's prepaid-water PPP.

Live 📅 since 2024
Scale🏙️ City-wide
CostUS$2.6M re-implementation contract (staged payments)
FundingMunicipal budget; US$12.95M ICT/ERP line in the 2026 city budget

📊 Impact

Council officials told the Cheda Commission of Inquiry the city was losing about US$70M a year in uncollected revenue without a working ERP — roughly US$350M over five years — with collections at 40-50% of a US$500M+ budget (council testimony).

🎓 Lesson

Switching a billing data layer off is also a decision: Harare dropped BIQ at 92% implementation, ran on manual processes for five years while the procurement regulator blocked two replacements, and ended up re-hiring the original vendor.

Sources

↗ Pindula News (press)May 2019 scrapping: BIQ at 92% implementation; audit committee found it 'could not generate a reliable trial balance'; high running costs.
↗ NewZimbabwe.com (press)Council resolution of 30 April 2024 re-engaging Quill Associates to restore BIQ for US$2.6M in staged payments, on the Auditor-General's recommendation; progress on 7 of 10 modules by July 2024.
↗ Bulawayo24 (press)Suspended town clerk Chisango's testimony to the Cheda Commission (Nov 2024): ≈US$70M/yr uncollected, ≈US$350M over five years, collections at 40-50%; PRAZ blocked a US$57M foreign ERP and a US$2.8M billing system; a US$350,000 local HIT system was rejected.
↗ The Standard (press)June 2024: Mayor Mafume — 'we don't know how many households we are billing'; Local Government ministry rejected the 2024 budget citing the lack of a functional ERP.
↗ City of Harare 2026 Budget Statement (authority)Names BIQ as the city's ERP; US$12.95M for ICT modernisation and ERP roll-out in 2026; calls comprehensive ERP implementation 'a central, non-negotiable commitment'; projects 19% revenue growth partly from ERP billing efficiency.
📎 Cite this project

1001 Smart Cities (2026). “Council ERP Scrapped and Reinstated (BIQ)” — Harare, Zimbabwe. The Smart City Atlas. https://1001smartcities.org/projects/harare-biq-erp-reinstatement/ (last verified 2026-08-07). Data: CC BY 4.0.

The underlying data is free to reuse with attribution — see the open data page.

✉️ Get the next verified smart-city project in your inbox

One short email a week: the Landmark, one Insight, the new cities. No spam, one-click unsubscribe. About the newsletter · RSS