Hanoi Metro: Two Lines, a Driver in Every Cab

Revision 2026-08-20-source-dates-r2 · effective 2026-08-15

Current revision. This is the snapshot used by the live entity page.

unreviewed

Record the publication date of each source that states one; sources that publish no date are marked null.

sha256:bf6f1f086013b176aa0c6ded09fb0688b2dbb253741e281363dbde82a9be0b4d

Change set

  • replace /snapshot/projectFingerprint — Updated projectFingerprint to the current sourced project record.
  • replace /snapshot/sources — Updated sources to the current sourced project record.
14
of 14 claims mapped
7
source dossiers
4
publication dates recorded
0
archives linked
0
exact locators
0
content captures hashed

Claims, one by one

The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.

Claim 1 clm-24e50dca09a29890 quantitative
The Chinese-built Cat Linh–Ha Dong line opened in November 2021, ten years after construction began
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
VietnamPlus records commercial operation from November 6, 2021, construction start in October 2011 and China Railway Sixth Group as the builder.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. VietnamPlus — Cat Linh-Ha Dong metro put into commercial operation
Claim 2 clm-bc7ffc95fe6bcd09 quantitative
its cost rising from $553 million to about $868 million, with 77% covered by Chinese ODA loans
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The same report gives the original estimate of roughly $553 million, a final cost of approximately $868 million and a 77% share of Chinese official development assistance loans.
Caveat
Reported final figures vary between $868 million and $886 million across outlets; the entry uses the figure in the opening-day report.

Sources carrying this claim

  1. VietnamPlus — Cat Linh-Ha Dong metro put into commercial operation
Claim 3 clm-5e3fe0eae9b6de40 quantitative
The Alstom-fitted elevated section of the Nhon–Hanoi Station line followed in August 2024
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
Alstom's release announces revenue service of the elevated section in August 2024; the operator's two-year review dates commercial operation from August 8, 2024.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Alstom — Line 3 passenger service press release
  2. Nhon line two-year results (via vietnam.vn)
Claim 4 clm-08a411e0956cadbd quantitative
8.5 of the planned 12.5 kilometres, with the four underground stations still unfinished
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
Alstom describes the first phase as 8.5 km with eight elevated stations, and the full 12.5 km line as including four underground stations that are not yet in service.
Caveat
No source used here states a completion date for the underground section.

Sources carrying this claim

  1. Alstom — Line 3 passenger service press release
Claim 5 clm-ee9ba27d33addd87 quantitative
Alstom's Urbalis 400 CBTC on the Nhon line
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The vendor names its Urbalis 400 communications-based train control system as part of the integrated Line 3 package.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Alstom — Line 3 passenger service press release
Claim 6 clm-accb714888930b47 quantitative
a system VnExpress described as 'level 2.5' automation on Cat Linh–Ha Dong
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
VnExpress's technical explainer places the line's automatic control system at 'level 2.5' on a five-level automation scale, with a driver mode built in.
Caveat
A description in press reporting before opening, not an official grade-of-automation certification.

Sources carrying this claim

  1. VnExpress — Cat Linh-Ha Dong control technology
Claim 7 clm-47c61b8df88fdcb3 descriptive
trains run automatically in normal weather and switch to manual driving when rain makes the rails slippery
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
After a mid-route stop in May 2022, Hanoi Metro general director Vu Hong Truong explained that trains operate in automatic mode in normal weather and are switched to manual when rain makes the rails slippery.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. VOV — sudden stop in rain, automatic to manual
Claim 8 clm-55550c28d3591c90 descriptive
the Nhon line recruited hundreds of operations staff, train drivers included, before opening
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
VOV reported the recruitment of nearly 450 staff to run the Nhon–Hanoi Station line ahead of opening, train drivers among them.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. VOV — Nhon line recruits nearly 450 operations staff
Claim 9 clm-f9cb2b984b054754 descriptive
No source reviewed here names a date for the day nobody is on board
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
Negative finding: both lines' own reporting consistently describes drivers aboard — manual fallback procedures on Line 2A, driver recruitment for Line 3 — and no reviewed source announces unattended operation or a date for it.
Caveat
An absence-of-evidence statement based on the sources reviewed for this entry, not an official commitment either way.

Sources carrying this claim

  1. VOV — sudden stop in rain, automatic to manual
  2. VOV — Nhon line recruits nearly 450 operations staff
Claim 10 clm-a6944e33ed7c92f4 quantitative
11.8 million passenger trips on Cat Linh–Ha Dong in 2024
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The operator's year-end report, relayed by the state information portal, states over 11.8 million passengers on Line 2A in 2024.
Caveat
Operator self-reported; no independent audit of ridership exists.

Sources carrying this claim

  1. Hanoi Metro 2024 results (via vietnam.vn)
Claim 11 clm-6f43b719b2f30e2a quantitative
about 32,900 a day, roughly 10% more than in 2023
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The same report gives an average of over 32,900 passengers per day and puts 2024 at 109.7% of 2023.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Hanoi Metro 2024 results (via vietnam.vn)
Claim 12 clm-c665455e42cf1422 quantitative
nearly 14.2 million on the Nhon line's elevated section in its first two years
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
The operator's two-year review counts nearly 14.2 million passengers and 157,955 train trips between August 8, 2024 and August 8, 2026.
Caveat
Operator self-reported; no independent audit.

Sources carrying this claim

  1. Nhon line two-year results (via vietnam.vn)
Claim 13 clm-bb53930c8d093580 quantitative
the 23,900 passengers per hour per direction quoted for the finished Line 3 is the signalling vendor's design capacity
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
Alstom's own release states the integrated system 'can transport 23,900 passengers per hour per direction at full capacity' — a vendor design figure, quoted here precisely so it is not mistaken for ridership.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Alstom — Line 3 passenger service press release
Claim 14 clm-7975e8a48527af88 descriptive
both still roster a driver in every cab with no announced date for their removal
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
Line 2A's operating procedures assume a driver who takes over in bad weather; Line 3 recruited and trained its own drivers before opening. No reviewed source announces their removal.
Caveat
Negative finding based on the sources reviewed for this entry.

Sources carrying this claim

  1. VOV — sudden stop in rain, automatic to manual
  2. VOV — Nhon line recruits nearly 450 operations staff

Source dossiers and revision state

This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.

unreviewed Revision 2026-08-20-source-dates-r2 effective 2026-08-15 · created 2026-08-21

Awaiting operator and domain-expert review; publication of this revision implies neither.

sha256:bf6f1f086013b176aa0c6ded09fb0688b2dbb253741e281363dbde82a9be0b4d
14
of 14 claims mapped
7
source dossiers
4
publication dates recorded
0
archives linked
0
exact locators
0
content captures hashed

Governance facts carried by the record

Operator
Hanoi Metro Company (Hanoi Railway One-Member Co., Ltd), owned by the Hanoi People's Committee
Actor types
city-government, national-government
Funding model
public
Funding description
Chinese ODA loans (~77% of Line 2A); French government, AFD, EIB and ADB (Line 3)
Cost
≈$868M (Line 2A alone, up from $553M)
Ownership
Not recorded
Decision rights
Not recorded
Exit conditions
Not recorded

7 source dossiers

VietnamPlus — Cat Linh-Ha Dong metro put into commercial operation en.vietnamplus.vn · 2 linked claims

Open original source ↗

Stable source ID
src-76c8e68f42ce4c9f
Publisher
Name not classified · en.vietnamplus.vn
Type / language
web-page · language not classified
Published
Not recorded
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-08-15
Dossier created
2026-08-21
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

State news agency record of the November 6, 2021 opening: construction start October 2011, cost rise from ~$553M to ~$868M, 77% Chinese ODA loans, operator Hanoi Railway One-Member Co.

Descriptive only — not page/paragraph exact
VnExpress — Cat Linh-Ha Dong control technology vnexpress.net · 1 linked claim

Open original source ↗

Stable source ID
src-8b64cf21483d76aa
Publisher
Name not classified · vnexpress.net
Type / language
web-page · language not classified
Published
2018-09-21
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-08-15
Dossier created
2026-08-21
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Pre-opening technical explainer: automatic control system rated 'level 2.5' on a five-level automation scale, command centre issues automatic speed orders, driver mode built in.

Descriptive only — not page/paragraph exact
VOV — sudden stop in rain, automatic to manual vov.vn · 3 linked claims

Open original source ↗

Stable source ID
src-a1af19efc74b679c
Publisher
Name not classified · vov.vn
Type / language
web-page · language not classified
Published
Not recorded
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-08-15
Dossier created
2026-08-21
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Hanoi Metro's general director explains (May 2022) that trains run in automatic mode in normal weather and are switched to manual driving when rain makes rails slippery.

Descriptive only — not page/paragraph exact
Alstom — Line 3 passenger service press release alstom.com · 4 linked claims

Open original source ↗

Stable source ID
src-03a166f7b310a5ac
Publisher
Name not classified · alstom.com
Type / language
web-page · language not classified
Published
2024-08-08
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-08-15
Dossier created
2026-08-21
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Vendor release (alstom.com bot-walled to direct fetch; text verified via the WebWire mirror of the same release): Urbalis 400 CBTC, ten Metropolis trains, 8.5 of 12.5 km opened August 2024, 23,900 pphpd design capacity, French/AFD/EIB/ADB financing, MRB as owner.

Descriptive only — not page/paragraph exact
Hanoi Metro 2024 results (via vietnam.vn) vietnam.vn · 2 linked claims

Open original source ↗

Stable source ID
src-3d865493a72951cf
Publisher
Name not classified · vietnam.vn
Type / language
web-page · language not classified
Published
2025-01-23
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-08-15
Dossier created
2026-08-21
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Relays the operator's year-end report: 11.8 million trips on Line 2A in 2024 (109.7% of 2023), average over 32,900 passengers/day, 14.8 million across both lines.

Descriptive only — not page/paragraph exact
Nhon line two-year results (via vietnam.vn) vietnam.vn · 2 linked claims

Open original source ↗

Stable source ID
src-1803508e8ec1f3d8
Publisher
Name not classified · vietnam.vn
Type / language
web-page · language not classified
Published
2026-08-08
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-08-15
Dossier created
2026-08-21
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Operator figures for the elevated section: nearly 14.2 million passengers and 157,955 train trips from August 8, 2024 to August 8, 2026.

Descriptive only — not page/paragraph exact
VOV — Nhon line recruits nearly 450 operations staff vov.gov.vn · 3 linked claims

Open original source ↗

Stable source ID
src-fb26db6fb9567ce7
Publisher
Name not classified · vov.gov.vn
Type / language
web-page · language not classified
Published
Not recorded
Updated
2022-11-15
Source last checked
No source-level check date
Record last verified
2026-08-15
Dossier created
2026-08-21
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Recruitment of nearly 450 staff, train drivers included, to operate the Nhon–Hanoi Station line — the line opened with drivers in the cab.

Descriptive only — not page/paragraph exact
Known limits of this passport
  • Publisher names and source languages have not yet been classified; domains are recorded without guessing.
  • Existing source notes are descriptive locators, not page- or paragraph-exact citations.