clm-24e50dca09a29890
quantitative
The Chinese-built Cat Linh–Ha Dong line opened in November 2021, ten years after construction began
Permanent project revision
Revision 2026-08-15-baseline · effective 2026-08-15
Superseded. A later revision exists: 2026-08-20-source-dates-b2 →
Created the first structured Evidence Passport with 14 claims and 7 source dossiers.
sha256:7abab1c6dae869d9270c91bcc0af27b8679fc755c7bbc1f364447d8cf43ee768
add /evidencePassport — Added claim-level evidence mapping and source dossiers.add /revisionHistory — Established a permanent, hash-addressed baseline revision.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-24e50dca09a29890
quantitative
The Chinese-built Cat Linh–Ha Dong line opened in November 2021, ten years after construction began
clm-bc7ffc95fe6bcd09
quantitative
its cost rising from $553 million to about $868 million, with 77% covered by Chinese ODA loans
clm-5e3fe0eae9b6de40
quantitative
The Alstom-fitted elevated section of the Nhon–Hanoi Station line followed in August 2024
clm-08a411e0956cadbd
quantitative
8.5 of the planned 12.5 kilometres, with the four underground stations still unfinished
clm-ee9ba27d33addd87
quantitative
Alstom's Urbalis 400 CBTC on the Nhon line
clm-accb714888930b47
quantitative
a system VnExpress described as 'level 2.5' automation on Cat Linh–Ha Dong
clm-47c61b8df88fdcb3
descriptive
trains run automatically in normal weather and switch to manual driving when rain makes the rails slippery
clm-55550c28d3591c90
descriptive
the Nhon line recruited hundreds of operations staff, train drivers included, before opening
clm-f9cb2b984b054754
descriptive
No source reviewed here names a date for the day nobody is on board
clm-a6944e33ed7c92f4
quantitative
11.8 million passenger trips on Cat Linh–Ha Dong in 2024
clm-6f43b719b2f30e2a
quantitative
about 32,900 a day, roughly 10% more than in 2023
clm-c665455e42cf1422
quantitative
nearly 14.2 million on the Nhon line's elevated section in its first two years
clm-bb53930c8d093580
quantitative
the 23,900 passengers per hour per direction quoted for the finished Line 3 is the signalling vendor's design capacity
clm-7975e8a48527af88
descriptive
both still roster a driver in every cab with no announced date for their removal
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:7abab1c6dae869d9270c91bcc0af27b8679fc755c7bbc1f364447d8cf43ee768
src-76c8e68f42ce4c9fState news agency record of the November 6, 2021 opening: construction start October 2011, cost rise from ~$553M to ~$868M, 77% Chinese ODA loans, operator Hanoi Railway One-Member Co.
src-8b64cf21483d76aaPre-opening technical explainer: automatic control system rated 'level 2.5' on a five-level automation scale, command centre issues automatic speed orders, driver mode built in.
src-a1af19efc74b679cHanoi Metro's general director explains (May 2022) that trains run in automatic mode in normal weather and are switched to manual driving when rain makes rails slippery.
src-03a166f7b310a5acVendor release (alstom.com bot-walled to direct fetch; text verified via the WebWire mirror of the same release): Urbalis 400 CBTC, ten Metropolis trains, 8.5 of 12.5 km opened August 2024, 23,900 pphpd design capacity, French/AFD/EIB/ADB financing, MRB as owner.
src-3d865493a72951cfRelays the operator's year-end report: 11.8 million trips on Line 2A in 2024 (109.7% of 2023), average over 32,900 passengers/day, 14.8 million across both lines.
src-1803508e8ec1f3d8Operator figures for the elevated section: nearly 14.2 million passengers and 157,955 train trips from August 8, 2024 to August 8, 2026.
src-fb26db6fb9567ce7Recruitment of nearly 450 staff, train drivers included, to operate the Nhon–Hanoi Station line — the line opened with drivers in the cab.