a catastrophic July 2011 cloudburst
Permanent project revision
Revision 2026-10-05-p4-quality-run · effective 2026-10-05
Current revision. This is the snapshot used by the live entity page.
Quality run to P4: claim array, source dates, present-tense audit. Still under construction; the most recent dated account (Yale e360, 28 July 2025, already in the entry) has the plan less than halfway done with two of four HOFOR tunnels finished. No newer dated source found; the entry's present-tense statements hold.
sha256:27de7573d27d9b6475bcc9775f661caac4552a5156b06553387009c1b590e31b
replace /snapshot/projectFingerprint — Updated projectFingerprint to the current sourced project record.replace /snapshot/asOf — Updated asOf to the current sourced project record.replace /snapshot/claims — Updated claims to the current sourced project record.replace /snapshot/sources — Updated sources to the current sourced project record.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-b75371dbe7b29653
quantitative
a catastrophic July 2011 cloudburst
clm-8743b8bfb9fcd9a6
quantitative
Copenhagen and utility HOFOR adopted a DKK 20 billion, 20-year Cloudburst Management Plan
clm-8358c3fe97dae2ea
quantitative
The programme spans 300+ projects
clm-ad4f49590f816343
descriptive
retention parks
clm-a122a6783cddc61c
descriptive
cloudburst streets
clm-2d49bd682c63a3ef
descriptive
underground tunnels
clm-bdc517d9310441fb
descriptive
including Sankt Kjelds Kvarter
clm-57cc792a8614d3cd
quantitative
where about 30% of local rainfall no longer reaches the sewers
clm-db7700a7a6e1a8fa
descriptive
In Sankt Kjelds Kvarter
clm-11a45b0547d74c55
quantitative
about 30% of local rainfall no longer reaches the sewers
clm-eb84c6a2022a164f
quantitative
Yale Environment 360 reported in July 2025 that the programme, originally slated for completion in 2032, was less than halfway to its goal, with two of four tunnels finished
clm-24eb2e496f160403
quantitative
Copenhagen's plan was drawn up to work mostly above ground, but by 2025 more of it was being built underground than its designers envisioned
clm-c08d1b6aaa820862
descriptive
the cloudburst streets meant to carry water to the parks stalled on the water mains and cables beneath them
clm-628078e7a654d5b8
quantitative
thirteen years in, experts quoted by Yale Environment 360 said the city still could not handle a storm like the one in 2011
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:27de7573d27d9b6475bcc9775f661caac4552a5156b06553387009c1b590e31b
src-34b478c60610858aOperator page: DKK 20bn budget, 20-year timeframe, 300+ projects, four tunnels.
src-01a941254fcec0adGovernment portal: ~30% of local stormwater managed, opened Dec 2014.
src-c21227d40e886412Project designer's case study, neighbourhood-wide figures.
src-c366c47f6f140a622025 currency check: Kalvebod Brygge cloudburst tunnel nearly complete.
src-b2de373d4556fbb1Plan originally slated for completion in 2032 is less than halfway done; of four HOFOR storm-water tunnels, two completed, one in progress, one to start the following year.