Since 2019 Belgrade has been retrofitting its junctions
Permanent project revision
Revision 2026-08-21-evidence-baseline · effective 2026-07-19
Superseded. A later revision exists: 2026-08-21-unsourced-text-correction →
Created the first structured Evidence Passport with 11 claims and 3 source dossiers.
sha256:e9c77e13d7360ba95af50c41bebaba63929bdfb6223dab7070a589d73906a174
add /evidencePassport — Added claim-level evidence mapping and source dossiers.add /revisionHistory — Established a permanent, hash-addressed baseline revision.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-44a51e72719bcd42
quantitative
Since 2019 Belgrade has been retrofitting its junctions
clm-ef66081fd8bf4a23
descriptive
with Siemens Mobility's Sitraffic Scala adaptive control
clm-f488f51d67250151
descriptive
retimes signals in real time from live traffic data
clm-ba32ab0cf0888c20
descriptive
gives trams priority
clm-744fc7e5725c13c0
quantitative
280 of the city's roughly 650 signalised intersections were connected by late 2022
clm-a6ad140c2698e8ad
descriptive
with the rollout continuing under Yunex Traffic
clm-1250e621d5b50744
quantitative
City analysis reported morning travel time on Bulevar kralja Aleksandra cut about 26%
clm-c66949cc15c9ed26
quantitative
tram journey times on prioritised routes shortened by up to 40%
clm-19e631368d2f316d
quantitative
The 322-junction rollout
clm-7d133b95f88e6146
quantitative
first promised for 2021
clm-d71a852700271db4
descriptive
slipped by several years
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:e9c77e13d7360ba95af50c41bebaba63929bdfb6223dab7070a589d73906a174
src-0eed19fae50a8e48Sitraffic Scala, 300+ intersections, tram prioritisation; delivered by the Siemens Mobility spin-off Yunex Traffic
src-b2fb2c3522545e8930 Sep 2019 agreement: RSD 2.8bn, 322 of 650 intersections, 3-year project; projected 10–15% congestion/travel-time cut
src-9b53068bf63ffc9725 Oct 2022: 280 of 322 connected; city analysis −26% on Bul. kralja Aleksandra, trams up to −40%