Since 2019 Belgrade has been retrofitting its junctions
Permanent project revision
Revision 2026-08-21-unsourced-text-correction · effective 2026-07-19
Current revision. This is the snapshot used by the live entity page.
Removed or softened wording that no listed source carries, after reading every source while preparing the claim ledger. The 26% covers travel time and stops together in one direction, and the 40% applies to Ruzveltova, not to prioritised routes generally; no source describes a delay of several years.
sha256:10b2f4dc0614665a6e0849895099a94fa80f8c32a34040f5faae1c37b491aeee
replace /snapshot/projectFingerprint — Updated projectFingerprint to the current sourced project record.replace /snapshot/claims — Updated claims to the current sourced project record.replace /snapshot/sources — Updated sources to the current sourced project record.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-44a51e72719bcd42
quantitative
Since 2019 Belgrade has been retrofitting its junctions
clm-ef66081fd8bf4a23
descriptive
with Siemens Mobility's Sitraffic Scala adaptive control
clm-f488f51d67250151
descriptive
retimes signals in real time from live traffic data
clm-ba32ab0cf0888c20
descriptive
gives trams priority
clm-744fc7e5725c13c0
quantitative
280 of the city's roughly 650 signalised intersections were connected by late 2022
clm-a6ad140c2698e8ad
descriptive
with the rollout continuing under Yunex Traffic
clm-8eb237a6526bafe6
quantitative
City analysis reported travel time and stops together in one direction of Bulevar kralja Aleksandra cut about 26%
clm-4b96554262f421c9
quantitative
tram journey times on Ruzveltova shortened by up to 40%
clm-19e631368d2f316d
quantitative
The 322-junction rollout
clm-7d133b95f88e6146
quantitative
first promised for 2021
clm-26628e3674890920
quantitative
was still well short of that count in late 2022
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:10b2f4dc0614665a6e0849895099a94fa80f8c32a34040f5faae1c37b491aeee
src-0eed19fae50a8e48Sitraffic Scala, 300+ intersections, tram prioritisation; delivered by the Siemens Mobility spin-off Yunex Traffic
src-b2fb2c3522545e8930 Sep 2019 agreement: RSD 2.8bn, 322 of 650 intersections, 3-year project; projected 10–15% congestion/travel-time cut
src-9b53068bf63ffc9725 Oct 2022: 280 of 322 connected; city analysis −26% on Bul. kralja Aleksandra, trams up to −40%