Pune's Smart Water Metering, DMA & SCADA Network

Pune Municipal Corporation began its 24x7 metered water supply project in 2017, part-funded by a ₹200 crore, 10-year municipal bond (the first Indian civic bond issue in 14 years) toward a roughly ₹2,300 crore programme of reservoirs, bulk/smart metering and distribution works. The city was divided into 327 District Metered Areas so inflow and outflow can be tracked to curb leakage and theft, with bulk meters feeding a SCADA/IoT system and a staff-facing portal (flow, pressure and level sensors, DMA and automatic-meter-reading data). As of September 2025, trade press put the metered-supply scheme at roughly 75% physical progress; PMC's parallel Equal Water Supply tank-and-pipeline component was reported 85% complete in February 2026, with completion still slipping past its original target years.

In build 📅 since 2017

🤖 AI-generated summary of the sources below — how this works · 🔎 Last verified

📊 Impact

Trade press reported the 24x7 metered-supply scheme at about 75% physical progress as of September 2025; PMC separately reported its linked tank-and-pipeline component at 85% complete in February 2026.

🎓 Lesson

A revenue-bond-funded smart-metering rollout is still a construction project first — Pune's DMA/SCADA network has taken the better part of a decade to approach completion, well past its original schedule.

Evidence🏛️ Official
Scale🏙️ City-wide
Cost≈₹2,300 crore programme, part-financed by a ₹200 crore municipal bond
Funding₹200 crore, 10-year municipal bond (BSE-listed, 7.59% coupon) plus PMC capital budget

📖 Terms in this entry: Non-revenue water (NRW) · Adaptive traffic signals · Digital twin

Sources

↗ Business Standard — Pune's first municipal bond in 14 years2017 bond issuance: ₹200cr, 10-year tenor, 6x oversubscribed, funding a ₹2,300cr 24x7 water project (reservoirs/metering/distribution).
↗ Indian Infrastructure — water sector coverage updateSeptember 2025 currency check: reports the Pune 24x7 metered water supply scheme (775 MLD) at roughly 75% progress.
↗ The Bridge Chronicle — Equal Water Supply Scheme nearing completionFebruary 2026: reports the linked tank-and-pipeline component at 85% complete, expected May 2026, delayed by land-acquisition issues.

This overview was generated with AI from the public sources listed above and checked against them before publication. It has not had a complete human fact-check — treat it as a starting point and follow the sources.

📎 Cite this project

1001 Smart Cities (2026). “Pune's Smart Water Metering, DMA & SCADA Network” — Pune, India. The Smart City Atlas. https://1001smartcities.org/projects/pune-water-metering-scada/ (last verified 2026-08-02). Data: CC BY 4.0.

The underlying data is free to reuse with attribution — see the open data page.

✉️ Get the next verified smart-city project in your inbox

One short email a week: the Landmark, one Insight, the new cities. No spam, one-click unsubscribe. About the newsletter · RSS