Cablebus: Cable Cars as Ordinary Public Transit
This overview was generated with AI from the public sources listed below and checked against them before publication. It has not had a complete human fact-check — treat it as a starting point and follow the sources.
1 sourced claim on this page, none individually verified yet — turn on “Sources in the text” to see each one.
How this atlas is made · What “last verified” means · What “source-checked” means · The full record behind this page
The lines climbing into hillside neighbourhoods carry riders in Metro-scale numbers. The flat park line drew about 15,000 passengers a day in 2025 against a design capacity of 34,000.
what does this mean?
The strongest source is an independent non-academic evaluation: an audit office, a government or EU review, or an NGO. It grades who did the looking — not how well the project went. All four grades →Part of 1001 Smart Cities — 1,167 documented projects · 🏙️ 7 more in Mexico City · 🚌 Public transport guide · 🚲 Mobility projects
Mexico City runs three aerial cable car lines as regular public transport: Line 1 (9.2 km, Gustavo A. Madero, Doppelmayr) opened in July 2021, Line 2 (10.55 km, Iztapalapa, Leitner, awarded by direct contract) in August 2021, and Line 3 (5.42 km, across the four sections of Chapultepec park) in September 2024. They carried 47.7 million passengers in 2025, cost 7 pesos a ride and are paid for with the citywide Movilidad Integrada card, which also covers the Metro, Metrobus, Trolebus and Ecobici. Guinness certified Line 2 in 2021 as the world's longest urban cable car line. The hillside lines carry the riders: the Chapultepec line drew about 15,000 passengers a day in 2025 against a design capacity of 34,000.
📊 Impact
A 2024 review by ITDP Mexico and the Inter-American Development Bank found Cablebus cut users' travel times by almost 45% and doubled, in some cases tripled, the jobs, health services, schools, shops and leisure destinations reachable within an hour's trip. The same study put operating cost at 8.73 pesos per passenger, below Metrobus (11.5), the Metro (15.3) and RTP buses (17.7).
🎓 Lesson
A cable car earns its place by geography, not by technology: the two lines climbing into hillside neighbourhoods carry riders in Metro-scale numbers, while the flat park line runs at under half its designed capacity.
Sources
Show 3 more sourcesShow fewer
📅 How old is the evidence?
Two clocks, kept apart: when this entry’s sources were published, and what has happened to its record in the atlas. Documented span: since 2021. 6 of 8 sources carry a publication date, from 5 August 2021 to 14 July 2026.
When the sources were published
- Expansión · pressExpansion Obras, 5 Aug 2021: who built Line 2 and what it cost (press) · updated 8 August 2021
- Corriente Alterna (UNAM) · pressCorriente Alterna, UNAM: failures and queues on Line 2 (independent journalism)
- Institute for Transportation and Development Policy (ITDP) Mexico · ngoITDP Mexico / Inter-American Development Bank, 'Lecciones aprendidas en la implementacion del Cablebus' (research)
- Expansión · pressExpansion Obras, 27 Sept 2024: cost per passenger (press, reporting the ITDP/IDB study)
- El Universal · pressEl Universal, 2025 ridership by line (press, citing STE)
- Infobae · pressInfobae, 14 July 2026: annual two-week inspection shutdown (press)
Show your work What this page rests on and what it can’t tell you · all 1 claims with their sources · the forensic record
Evidence Passport · public beta 1 addressable claim, 8 source dossiers, one permanent baseline. The passport is unreviewed — an AI-assisted structural migration, not a human or expert endorsement. Every revision keeps a permanent copy under revision history.
Inspect the claims, one by one — verbatim text, sources and caveats for all 1
The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-4d44818d548cb240
quantitative
A 2024 review by ITDP Mexico and the Inter-American Development Bank found Cablebus cut users' travel times by almost 45% and doubled, in some cases tripled, the jobs, health services, schools, shops and leisure destinations reachable within an hour's trip
Sources carrying this claim
Forensic record — source dossiers, gaps, hashes and the exact revision this page renders
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:123845e75bcdc30aac078932fff2b07a3535a7562c4d2583a6c6dd2ccea4d32c
- 1
- of 1 claims mapped
- 8
- source dossiers
- 7
- publication dates recorded
- 1
- archives linked
- 0
- exact locators
- 0
- content captures hashed
Governance facts carried by the record
- Operator
- Servicio de Transportes Electricos de la Ciudad de Mexico (STE)
- Actor types
- utility
- Funding model
- public
- Funding description
- Mexico City government budget; federal funds announced for Line 4
- Cost
- Line 2 approx. MXN 3.17bn, Line 3 approx. MXN 2.6bn (Line 1 not confirmed)
- Ownership
- Not recorded
- Decision rights
- Not recorded
- Exit conditions
- Not recorded
8 source dossiers
ITDP Mexico / Inter-American Development Bank, 'Lecciones aprendidas en la implementacion del Cablebus' (research)
- Stable source ID
src-0014b1107438c74d- Publisher
- Name not classified · mexico.itdp.org
- Type / language
- web-page · language not classified
- Published
- 2024-07-23
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- Open archived copy ↗ · 2026-05-12
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Carries the impact figures at sentence level: 'El Cablebus logro disminuir los tiempos de traslado de las personas usuarias casi en un 45%' ('Cablebus cut users' travel times by almost 45%'), and 'Se duplicaron las oportunidades de empleo, salud, educacion, abastecimiento y esparcimiento' reachable in under an hour, tripled in some cases. Also estimates 18,569 t CO2e avoided from 2021 to December 2023. Method: literature review of 21 papers, 4 interviews in La Paz-El Alto, Bogota and Medellin, 9 interviews with Cablebus actors, with the city mobility ministry SEMOVI taking part. No control group, and the implementing agency was a participant, so this is a lessons-learned study rather than an arm's-length audit.
- Claims linked
Expansion Obras, 27 Sept 2024: cost per passenger (press, reporting the ITDP/IDB study)
- Stable source ID
src-9c01369d31d84327- Publisher
- Name not classified · obras.expansion.mx
- Type / language
- web-page · language not classified
- Published
- 2024-09-27
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
'el costo operativo del Cablebus (el promedio de las lineas 1 y 2) es de 8.73 pesos por pasajero' ('the operating cost of Cablebus, averaging lines 1 and 2, is 8.73 pesos per passenger'), against 11.5 for Metrobus, 15.3 for the Metro and 17.7 for RTP. Also: 'Las lineas 1 y 2 del Cablebus ... transportaron a mas de 40 millones de pasajeros en 2022.'
- Claims linked
- Background source; no baseline claim points here
El Universal, 2025 ridership by line (press, citing STE)
- Stable source ID
src-d5f6e33ed5773d63- Publisher
- Name not classified · eluniversal.com.mx
- Type / language
- web-page · language not classified
- Published
- 2025-12-29
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
STE figures for calendar 2025: Line 2 'movilizo a 22.9 millones de personas', Line 1 'traslado a 19.3 millones de pasajeros', Line 3 'fue utilizada por un total de 5.5 millones de personas' (22.9M / 19.3M / 5.5M, 47.7M combined). Strongest recent confirmation that all three lines are running.
- Claims linked
- Background source; no baseline claim points here
Expansion Obras, 5 Aug 2021: who built Line 2 and what it cost (press)
- Stable source ID
src-7ea671bdf4bec4ca- Publisher
- Name not classified · obras.expansion.mx
- Type / language
- web-page · language not classified
- Published
- 2021-08-05
- Updated
- 2021-08-08
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
'La empresa encargada de construir la segunda linea del medio de transporte es Leitner Spa' ('the company charged with building the second line is Leitner Spa'), contracted directly rather than by tender, with Alfa Proveedores and Leitner Ropeways Mexico; 'La Linea 2 tuvo una inversion de 3,168 millones de pesos'. The city government's own inauguration release gives 3,183 million pesos; the discrepancy is left standing rather than averaged.
- Claims linked
- Background source; no baseline claim points here
Corriente Alterna, UNAM: failures and queues on Line 2 (independent journalism)
- Stable source ID
src-676bb56fc634a5d6- Publisher
- Name not classified · corrientealterna.unam.mx
- Type / language
- web-page · language not classified
- Published
- 2021-08-08
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Counterweight to the operator account: 'la espera puede demorar hasta sesenta minutos en las horas pico' at Xalpa station ('the wait can take up to sixty minutes at peak hours'), nicknamed 'el Pantitlan del Cablebus'; the works ministry documented seven cabin stoppages between 8 August and 21 November 2021, mostly power supply and motor control faults; passengers were stranded aloft during the 7.1 earthquake of 7 September 2021. Leitner is contracted to spend 159.7 million pesos a year on maintenance in the first year of operation.
- Claims linked
- Background source; no baseline claim points here
Wikipedia (ES), Linea 1 and Linea 3 del Cablebus (encyclopedia, used for line geometry only)
- Stable source ID
src-7d5f78c42f9dd9c6- Publisher
- Name not classified · es.wikipedia.org
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Line 1: 'El 11 de julio de 2021, fue inaugurado el troncal Indios Verdes — Cuautepec', 9.2 km, 6 stations, 377 cabins, 33 min 20 s end to end, fare MXN 7.00; first section opened 4 March 2021. The companion article on Line 3 gives 24 September 2024, 5.42 km, 6 stations, 180 cabins, Miguel Hidalgo and Alvaro Obregon, connecting the four sections of Chapultepec, with a five-station extension into the upper Alvaro Obregon neighbourhoods only proposed. Used as corroboration because the operator site ste.cdmx.gob.mx returns 503 to automated requests.
- Claims linked
- Background source; no baseline claim points here
La Jornada, 27 Aug 2021: Guinness record for Line 2 (press)
- Stable source ID
src-d763499565b507e5- Publisher
- Name not classified · jornada.com.mx
- Type / language
- web-page · language not classified
- Published
- 2021-08-27
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Guinness World Records certified Line 2 (10.55 km) as the world's longest urban cable car line, August 2021; also reported by Forbes Mexico. Attributed to Guinness rather than asserted by the atlas, and the record is a moving target: the planned 15.2 km Line 5 is promoted as its successor.
- Claims linked
- Background source; no baseline claim points here
Infobae, 14 July 2026: annual two-week inspection shutdown (press)
- Stable source ID
src-23ef0c5b5f0af33c- Publisher
- Name not classified · infobae.com
- Type / language
- web-page · language not classified
- Published
- 2026-07-14
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Each of the three lines closes for roughly two weeks a year for its annual inspection, staggered from 13 July, with free RTP replacement buses; El Universal reported riders saying they were not told in advance and paid more to travel. Line 3 also lost power in February 2026 and ran on a provisional service for four hours after an electrical fault on 28 May 2026 (La Jornada).
- Claims linked
- Background source; no baseline claim points here
Known limits of this passport
- Publisher names and source languages have not yet been classified; domains are recorded without guessing.
- Existing source notes are descriptive locators, not page- or paragraph-exact citations.
- A missing archive, publication date or content hash is shown as null rather than inferred.
- The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim.
Continue exploring
Compare this project
Explore the wider context
📎 Cite this project
1001 Smart Cities (2026). “Cablebus: Cable Cars as Ordinary Public Transit” — Mexico City, Mexico. The Smart City Atlas. https://1001smartcities.org/projects/mexico-city-cablebus/ (last verified 2026-07-26). Data: CC BY 4.0.
The underlying data is free to reuse with attribution — see the open data page.