Gothenburg's Cloudburst Map: A Modelled 100-Year Rain and a Rule for New Buildings

🤖 AI-generated summary · ◆ 22 sourced claims · 🔎 Last verified

This overview was generated with AI from the public sources listed below and checked against them before publication. It has not had a complete human fact-check — treat it as a starting point and follow the sources.

22 sourced claims on this page, none individually verified yet — turn on “Sources in the text” to see each one.

How this atlas is made · What “last verified” means · What “source-checked” means · The full record behind this page

Gothenburg's map shows where a 100-year rain would leave more than a metre of water. The pipes are built for a ten-year rain, owners must protect their own buildings, and only a third of residents know how.

Evidence📊 Independent
what does this mean?The strongest source is an independent non-academic evaluation: an audit office, a government or EU review, or an NGO. It grades who did the looking — not how well the project went. All four grades →
Scale🏙️ City-wide

Part of 1001 Smart Cities — 1,277 documented projects · 🏙️ 11 more in Gothenburg · 🌊 Flood resilience guide · 🌱 Environment projects

Kretslopp och vatten, an administration of the City of Gothenburg, publishes a cloudburst map showing the maximum water depth a so-called 100-year rain could leave across the city: 100 mm in six hours, half of it within half an hour, with the effect of climate change up to 2100 taken into account. According to the map, some areas could flood with more than a metre of water. It is a model result, not a live reading: in the department's cloudburst analyses a surface-flow model is coupled to its hydraulic model of the sewer network, and the city warns that the map does not show exactly how a single house is affected and that more rain can fall than the calculation shows. Under the flood-risk supplement to the comprehensive plan, adopted by the city council on 25 April 2019, new buildings must not be damaged by a climate-adapted 100-year rain, and the department proposes cloudburst measures in plans for new development when needed.

Live 📅 since 2019

Sources

↗ Kretslopp och vatten, City of Gothenburg — Karta över hur skyfall kan påverka områden i GöteborgThe cloudburst map itself, made by Kretslopp och vatten. It shows the maximum water depths to be expected in a so-called 100-year rain, defined as 100 mm in six hours with half of it falling in half an hour, with the effect of climate change up to 2100 taken into account. The page warns that the map does not show exactly how a specific house is affected and that more rain can fall than the calculation shows.
↗ City of Gothenburg — Ansvar för hanteringen av dagvatten och skyfallThe city's page on responsibilities: the municipal water and sewer network must cope with normal rain, defined as rain with a ten-year return period, while property owners must protect their own property against flooding from heavier rain, including cloudbursts.
↗ City of Gothenburg — Så arbetar Göteborgs Stad med dagvatten och skyfallHow the city works on stormwater and cloudbursts: Kretslopp och vatten proposes cloudburst measures in plans for new development when needed, seven city administrations signed a cloudburst agreement in 2021, and because plans take years to be realised, only isolated cloudburst facilities have been built so far.
↗ DHI for Kretslopp och vatten — Skyfallssäkring Volvo Lundby (11 Oct 2018)A cloudburst analysis prepared by the consultancy DHI for Kretslopp och vatten for a detailed plan in Lundby. It describes the method: an existing MIKE 21 surface model is coupled to the hydraulic sewer network model (MIKE URBAN) built by Kretslopp och vatten, and loaded with a climate-adjusted 100-year rain of six hours.
↗ Kretslopp och vatten, City of Gothenburg — PM DP Kämpegatan: Skyfallsanalys (11 Apr 2024)Kretslopp och vatten's cloudburst analysis for the detailed plan at Kämpegatan, north of the Central Station. It quotes the flood-risk supplement's requirement that new buildings must not be damaged by a climate-adapted 100-year rain, uses the department's 2023 cloudburst model to set a volume of about 850 m³ for Bergslagsparken, and recommends a plan rule on the lowest finished floor level.
Show 8 more sourcesShow fewer
↗ Socialförvaltningen Centrum, City of Gothenburg — Bilaga 1: Föreslagen ändring av översiktsplanenAn annex to a city committee's consultation response, summarising the proposed amendment of the comprehensive plan. It states that the new climate-adaptation chapter builds mainly on the thematic supplement on flood risks, adopted by the city council on 25 April 2019; the annex itself carries no date.
↗ City of Gothenburg — Skyfallssäsong ska förbereda göteborgare på allt fler kraftiga regn (20 May 2024)Kretslopp och vatten's press release launching the city's 'cloudburst season'. An engineer working on the department's cloudburst strategy says that in the worst case no cloudburst warning comes in advance, and the release states that Gothenburg had not yet been hit by a real cloudburst.
↗ City of Gothenburg — Göteborgarna inte redo för kraftiga skyfall trots stor skaderisk (26 May 2025)Kretslopp och vatten's campaign release. According to the cloudburst map some areas could flood with more than a metre of water; the city's citizen survey, carried out by Statistics Sweden, found that only a third of residents knew how to prepare for a cloudburst, the same result as in 2022; and protecting the city from cloudburst damage would require storage equal to 15 Karlatornet towers, hard to build underground.
↗ City of Gothenburg — Skyfallsanläggning i Stabbeparken färdig (18 Jun 2025)Release on the cloudburst facility in Stabbeparken, south of Östra Hospital: a gabion embankment built from November 2024 to the end of May 2025 that can hold up to 3,000 m³ and is calculated to reduce water depth around important hospital operations by up to a metre in a heavy cloudburst.
↗ Stadsrevisionen, City of Gothenburg — Skyfallshanteringen i Göteborgs Stad behöver bli bättre (22 Feb 2023)The city audit office's release on its review of cloudburst management: knowledge of where and how the city will flood in a cloudburst is extensive, but only a few cloudburst facilities have been built and few are planned; responsibilities and goals need to be clearer, and there has been no overall follow-up.
↗ Stadsrevisionen, City of Gothenburg — Revisionsredogörelse 2022 för kretslopp- och vattennämnden (21 Mar 2023)The audit office's account of its 2022 review of the Kretslopp och vatten committee. It summarises the cloudburst review decided on 21 February 2023: not enough city-wide decisions on what the city is to achieve and at what pace, unclear responsibilities and insufficient follow-up, and it notes that binding law covers new detailed plans but not existing buildings.
↗ Stadsrevisionen, City of Gothenburg — Stadsrevisionens årsredogörelse 2025, Handling 2026 nr 79 (13 Apr 2026)The audit office's annual report for 2025, sent to the city council. Its review of the city's climate adaptation plan 2024–2026 found that Gryaab, the Port of Gothenburg and the Kretslopp och vatten committee work on climate adaptation appropriately and that the work is organised, steered and followed up.
↗ City of Gothenburg — Ändring av översiktsplan för Göteborg, granskningshandling (May 2026)Published May 2026The review version of the comprehensive-plan amendment, which works the flood-risk supplement into the plan and updates it. Its cloudburst section says facilities for diverting and retaining surplus water are sized so that a climate-adapted 100-year rain does not damage buildings and infrastructure.

📅 How old is the evidence?

Two clocks, kept apart: when this entry’s sources were published, and what has happened to its record in the atlas. Documented span: since 2019. 9 of 13 sources carry a publication date, from 11 October 2018 to May 2026.

When the sources were published

  1. DHI Group · vendorDHI for Kretslopp och vatten — Skyfallssäkring Volvo Lundby (11 Oct 2018)
  2. Stadsrevisionen, Göteborgs Stad · oversight bodyStadsrevisionen, City of Gothenburg — Skyfallshanteringen i Göteborgs Stad behöver bli bättre (22 Feb 2023)
  3. Stadsrevisionen, Göteborgs Stad · oversight bodyStadsrevisionen, City of Gothenburg — Revisionsredogörelse 2022 för kretslopp- och vattennämnden (21 Mar 2023)
  4. City of Gothenburg (Göteborgs Stad) · city governmentKretslopp och vatten, City of Gothenburg — PM DP Kämpegatan: Skyfallsanalys (11 Apr 2024)
  5. City of Gothenburg (Göteborgs Stad) · city governmentCity of Gothenburg — Skyfallssäsong ska förbereda göteborgare på allt fler kraftiga regn (20 May 2024)
  6. City of Gothenburg (Göteborgs Stad) · city governmentCity of Gothenburg — Göteborgarna inte redo för kraftiga skyfall trots stor skaderisk (26 May 2025)
  7. City of Gothenburg (Göteborgs Stad) · city governmentCity of Gothenburg — Skyfallsanläggning i Stabbeparken färdig (18 Jun 2025)
  8. Stadsrevisionen, Göteborgs Stad · oversight bodyStadsrevisionen, City of Gothenburg — Stadsrevisionens årsredogörelse 2025, Handling 2026 nr 79 (13 Apr 2026)
Show 1 more dated sourcesShow fewer
  1. City of Gothenburg (Göteborgs Stad) · city governmentCity of Gothenburg — Ändring av översiktsplan för Göteborg, granskningshandling (May 2026)

Every source, with links ↑

What happened to this record

  1. Sources last read
  2. Entered the record

Every revision, permanent →

Show your work What this page rests on and what it can’t tell you · all 22 claims with their sources · the forensic record

Evidence file · public beta 22 addressable claims, 13 source dossiers, one permanent baseline. The file is unreviewed — an AI-assisted structural migration, not a human or expert endorsement. Every revision keeps a permanent copy under revision history.

Inspect the claims, one by one — verbatim text, sources and caveats for all 22

The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.

Claim 1 clm-22168ee35432d4c4 descriptive
Kretslopp och vatten, an administration of the City of Gothenburg, publishes a cloudburst map
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The map page states that it was made by Kretslopp och vatten, City of Gothenburg.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Kretslopp och vatten, City of Gothenburg — Karta över hur skyfall kan påverka områden i Göteborg
Claim 2 clm-5d5f6f03f60238ce quantitative
showing the maximum water depth a so-called 100-year rain could leave across the city
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The page says the map shows the maximum water depths that can be expected in a so-called 100-year rain.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Kretslopp och vatten, City of Gothenburg — Karta över hur skyfall kan påverka områden i Göteborg
Claim 3 clm-1166bde949c3d74c quantitative
100 mm in six hours, half of it within half an hour, with the effect of climate change up to 2100 taken into account
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The page defines the calculated rain as 100 mm in six hours with half falling within half an hour, and says climate change up to 2100 is taken into account.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Kretslopp och vatten, City of Gothenburg — Karta över hur skyfall kan påverka områden i Göteborg
Claim 4 clm-d5dccf4dd802d5ce descriptive
According to the map, some areas could flood with more than a metre of water.
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The department's 2025 release says that according to the cloudburst map some areas of the city could flood with more than a metre of water.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. City of Gothenburg — Göteborgarna inte redo för kraftiga skyfall trots stor skaderisk (26 May 2025)
Claim 5 clm-a3594b6833cc44b6 descriptive
in the department's cloudburst analyses a surface-flow model is coupled to its hydraulic model of the sewer network
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The analysis DHI prepared for Kretslopp och vatten describes an existing MIKE 21 surface model coupled to the hydraulic sewer-network model (MIKE URBAN) built by Kretslopp och vatten.
Caveat
The method description comes from one analysis for one catchment, Lundby; the city does not publish a model description for the map itself.

Sources carrying this claim

  1. DHI for Kretslopp och vatten — Skyfallssäkring Volvo Lundby (11 Oct 2018)
Claim 6 clm-7cb09098380900b3 descriptive
the map does not show exactly how a single house is affected and that more rain can fall than the calculation shows
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The map page says the map does not show exactly how a specific house is affected and that more rain can fall than the calculation shows.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Kretslopp och vatten, City of Gothenburg — Karta över hur skyfall kan påverka områden i Göteborg
Claim 7 clm-958b46b8517f7d77 quantitative
the flood-risk supplement to the comprehensive plan, adopted by the city council on 25 April 2019
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The annex states that the thematic supplement on flood risks was adopted by the city council on 25 April 2019.
Caveat
A 2024 planning-strategy document gives the supplement's adoption year as 2017; the supplement was still on public exhibition in December 2017, so the 2019 date is used here.

Sources carrying this claim

  1. Socialförvaltningen Centrum, City of Gothenburg — Bilaga 1: Föreslagen ändring av översiktsplanen
Claim 8 clm-b737300aa59ed5fb quantitative
new buildings must not be damaged by a climate-adapted 100-year rain
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The department's 2024 analysis quotes the supplement's requirement that new development must not be damaged in a cloudburst, defined as a climate-adapted 100-year rain; the 2026 review version of the plan amendment keeps the 100-year standard for buildings and infrastructure.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Kretslopp och vatten, City of Gothenburg — PM DP Kämpegatan: Skyfallsanalys (11 Apr 2024)
  2. City of Gothenburg — Ändring av översiktsplan för Göteborg, granskningshandling (May 2026)
Claim 9 clm-0f309b6b3625e834 descriptive
the department proposes cloudburst measures in plans for new development when needed
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The city's page says Kretslopp och vatten proposes cloudburst measures, when needed, in the plans for new development.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. City of Gothenburg — Så arbetar Göteborgs Stad med dagvatten och skyfall
Claim 10 clm-ce408ba1385f5668 quantitative
the department's 2023 model showed that Bergslagsparken needs to handle about 850 m³ of cloudburst water
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The Kämpegatan analysis says the department's cloudburst model shows that Bergslagsparken must be able to handle a cloudburst volume of about 850 m³, citing Kretslopp och vatten, 2023.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Kretslopp och vatten, City of Gothenburg — PM DP Kämpegatan: Skyfallsanalys (11 Apr 2024)
Claim 11 clm-c7dca46605d68273 quantitative
the department recommended a plan rule placing finished floors at least 0.3 metres above the ground at the flow path outside the entrance, and no lower than +2.8
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The analysis states that Kretslopp och vatten recommends a plan regulation for the lowest finished floor level: at least 0.3 metres above ground level at the flow path outside the entrance, and no lower than +2.8.
Caveat
This is the department's recommendation in the planning documents; whether the adopted plan includes the rule is not shown in the source.

Sources carrying this claim

  1. Kretslopp och vatten, City of Gothenburg — PM DP Kämpegatan: Skyfallsanalys (11 Apr 2024)
Claim 12 clm-24555b4c5e4a9905 quantitative
an embankment finished at the end of May 2025 can hold up to 3,000 m³
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The release says construction ran from November 2024 to the end of May 2025 and that the facility can store up to 3,000 cubic metres.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. City of Gothenburg — Skyfallsanläggning i Stabbeparken färdig (18 Jun 2025)
Claim 13 clm-1b83940fe3de89b6 descriptive
is calculated to cut the water depth around important parts of Östra Hospital by up to a metre
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The release says that in a heavy cloudburst the facility is calculated to reduce the water depth around important hospital operations by up to one metre.
Caveat
A calculated effect; no cloudburst has yet tested it.

Sources carrying this claim

  1. City of Gothenburg — Skyfallsanläggning i Stabbeparken färdig (18 Jun 2025)
Claim 14 clm-da169944d2fd8cb8 quantitative
only a third of residents knew how to prepare for a cloudburst, the same result as in 2022
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The release says the city's citizen survey, carried out by Statistics Sweden, found that only a third of residents know how to prepare for a cloudburst, and that the result was the same in the 2022 survey.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. City of Gothenburg — Göteborgarna inte redo för kraftiga skyfall trots stor skaderisk (26 May 2025)
Claim 15 clm-41b39ab7f4da9201 descriptive
knowledge of where and how a cloudburst would flood the city was extensive, but only a few cloudburst facilities had been built and few were planned
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The audit office's release says there is extensive knowledge of where and how the city will be affected by flooding in a cloudburst, that the municipality has built only a few cloudburst facilities, and that planned facilities are few.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Stadsrevisionen, City of Gothenburg — Skyfallshanteringen i Göteborgs Stad behöver bli bättre (22 Feb 2023)
Claim 16 clm-989f4d31f67a9b54 descriptive
not enough city-wide decisions had been taken on what to achieve and at what pace
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The audit office's account of the review says not enough city-wide decisions had been taken on what the city should achieve in the area and at what pace.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Stadsrevisionen, City of Gothenburg — Revisionsredogörelse 2022 för kretslopp- och vattennämnden (21 Mar 2023)
Claim 17 clm-e6c6c3f0d58c2529 descriptive
The rule binds only what is new
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The audit office notes that under the Planning and Building Act municipalities must consider cloudbursts when drawing up new detailed plans, but that binding legislation is lacking for existing buildings.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Stadsrevisionen, City of Gothenburg — Revisionsredogörelse 2022 för kretslopp- och vattennämnden (21 Mar 2023)
Claim 18 clm-4f9321e74419cafd descriptive
the city's pipes are built for normal rain with a ten-year return period, and protecting an existing building from heavier rain is its owner's responsibility
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The city's page says the municipal water and sewer network must cope with normal rain, with a return period of ten years, and that property owners are responsible for protecting their property against flooding from rain with a return period of more than ten years, including cloudbursts.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. City of Gothenburg — Ansvar för hanteringen av dagvatten och skyfall
Claim 19 clm-bb3f14069d56016a quantitative
protecting the city from cloudburst damage would take storage equal to 15 Karlatornet towers, hard to build underground because the ground is already full of pipes and other infrastructure
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The release says protecting Gothenburg from cloudburst damage would require storage equal to 15 Karlatornet towers, and that building this underground would be difficult because the ground is already full of pipes and other infrastructure.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. City of Gothenburg — Göteborgarna inte redo för kraftiga skyfall trots stor skaderisk (26 May 2025)
Claim 20 clm-082d9770e00a4c20 quantitative
in the worst case, the department said in 2024, no cloudburst warning comes in advance at all
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
An engineer working on the department's strategic cloudburst work is quoted saying that in the worst case no cloudburst warning comes in advance at all.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. City of Gothenburg — Skyfallssäsong ska förbereda göteborgare på allt fler kraftiga regn (20 May 2024)
Claim 21 clm-5f81b43c7b778327 descriptive
the department, the wastewater company Gryaab and the Port of Gothenburg work on the city's climate adaptation plan appropriately
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The audit office's 2025 annual report assesses that Gryaab AB, Göteborgs Hamn AB and the Kretslopp och vatten committee work on climate adaptation appropriately, based on the measures in the climate adaptation plan.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Stadsrevisionen, City of Gothenburg — Stadsrevisionens årsredogörelse 2025, Handling 2026 nr 79 (13 Apr 2026)
Claim 22 clm-70b1b3559ea7ffba quantitative
in May 2026 the city put an updated version of the flood-risk rules out for review
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The May 2026 review version of the comprehensive-plan amendment includes working in and updating the thematic supplement on flood risks.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. City of Gothenburg — Ändring av översiktsplan för Göteborg, granskningshandling (May 2026)
Forensic record — source dossiers, gaps, hashes and the exact revision this page renders

This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.

unreviewed Revision 2026-11-12-baseline effective 2026-11-11 · created 2026-11-12

Awaiting operator and domain-expert review; publication of this revision implies neither.

sha256:59d6679dbee1307bd1b829ab3c2f3d38277754d5f906f9804d5a6ff8b9943b03
22
of 22 claims mapped
13
source dossiers
8
publication dates recorded
0
archives linked
0
exact locators
0
content captures hashed

Governance facts carried by the record

Operator
Kretslopp och vatten, the City of Gothenburg's administration for water, sewers and waste
Actor types
city-government
Funding model
Not recorded
Funding description
Not recorded
Cost
Not recorded
Ownership
Not recorded
Decision rights
Not recorded
Exit conditions
Not recorded

13 source dossiers

Kretslopp och vatten, City of Gothenburg — Karta över hur skyfall kan påverka områden i Göteborg vattenigoteborg.se · 4 linked claims

Open original source ↗

Stable source ID
src-364b4ab4b9ce5c28
Publisher
Name not classified · vattenigoteborg.se
Type / language
web-page · language not classified
Published
Not recorded
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-11
Dossier created
2026-11-12
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

The cloudburst map itself, made by Kretslopp och vatten. It shows the maximum water depths to be expected in a so-called 100-year rain, defined as 100 mm in six hours with half of it falling in half an hour, with the effect of climate change up to 2100 taken into account. The page warns that the map does not show exactly how a specific house is affected and that more rain can fall than the calculation shows.

Descriptive only — not page/paragraph exact
City of Gothenburg — Ansvar för hanteringen av dagvatten och skyfall goteborg.se · 1 linked claim

Open original source ↗

Stable source ID
src-9d6b65b1ba8a571f
Publisher
Name not classified · goteborg.se
Type / language
web-page · language not classified
Published
Not recorded
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-11
Dossier created
2026-11-12
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

The city's page on responsibilities: the municipal water and sewer network must cope with normal rain, defined as rain with a ten-year return period, while property owners must protect their own property against flooding from heavier rain, including cloudbursts.

Descriptive only — not page/paragraph exact
City of Gothenburg — Så arbetar Göteborgs Stad med dagvatten och skyfall goteborg.se · 1 linked claim

Open original source ↗

Stable source ID
src-509b10c42c1bc016
Publisher
Name not classified · goteborg.se
Type / language
web-page · language not classified
Published
Not recorded
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-11
Dossier created
2026-11-12
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

How the city works on stormwater and cloudbursts: Kretslopp och vatten proposes cloudburst measures in plans for new development when needed, seven city administrations signed a cloudburst agreement in 2021, and because plans take years to be realised, only isolated cloudburst facilities have been built so far.

Descriptive only — not page/paragraph exact
DHI for Kretslopp och vatten — Skyfallssäkring Volvo Lundby (11 Oct 2018) www5.goteborg.se · 1 linked claim

Open original source ↗

Stable source ID
src-30bf9c951fe27e60
Publisher
Name not classified · www5.goteborg.se
Type / language
pdf · language not classified
Published
2018-10-11
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-11
Dossier created
2026-11-12
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

A cloudburst analysis prepared by the consultancy DHI for Kretslopp och vatten for a detailed plan in Lundby. It describes the method: an existing MIKE 21 surface model is coupled to the hydraulic sewer network model (MIKE URBAN) built by Kretslopp och vatten, and loaded with a climate-adjusted 100-year rain of six hours.

Descriptive only — not page/paragraph exact
Kretslopp och vatten, City of Gothenburg — PM DP Kämpegatan: Skyfallsanalys (11 Apr 2024) www5.goteborg.se · 3 linked claims

Open original source ↗

Stable source ID
src-2e2a825849168413
Publisher
Name not classified · www5.goteborg.se
Type / language
pdf · language not classified
Published
2024-04-11
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-11
Dossier created
2026-11-12
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Kretslopp och vatten's cloudburst analysis for the detailed plan at Kämpegatan, north of the Central Station. It quotes the flood-risk supplement's requirement that new buildings must not be damaged by a climate-adapted 100-year rain, uses the department's 2023 cloudburst model to set a volume of about 850 m³ for Bergslagsparken, and recommends a plan rule on the lowest finished floor level.

Descriptive only — not page/paragraph exact
Socialförvaltningen Centrum, City of Gothenburg — Bilaga 1: Föreslagen ändring av översiktsplanen www4.goteborg.se · 1 linked claim

Open original source ↗

Stable source ID
src-e048455bbc8e4d21
Publisher
Name not classified · www4.goteborg.se
Type / language
pdf · language not classified
Published
Not recorded
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-11
Dossier created
2026-11-12
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

An annex to a city committee's consultation response, summarising the proposed amendment of the comprehensive plan. It states that the new climate-adaptation chapter builds mainly on the thematic supplement on flood risks, adopted by the city council on 25 April 2019; the annex itself carries no date.

Descriptive only — not page/paragraph exact
City of Gothenburg — Skyfallssäsong ska förbereda göteborgare på allt fler kraftiga regn (20 May 2024) mynewsdesk.com · 1 linked claim

Open original source ↗

Stable source ID
src-990e9b1a43785375
Publisher
Name not classified · mynewsdesk.com
Type / language
web-page · language not classified
Published
2024-05-20
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-11
Dossier created
2026-11-12
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Kretslopp och vatten's press release launching the city's 'cloudburst season'. An engineer working on the department's cloudburst strategy says that in the worst case no cloudburst warning comes in advance, and the release states that Gothenburg had not yet been hit by a real cloudburst.

Descriptive only — not page/paragraph exact
City of Gothenburg — Göteborgarna inte redo för kraftiga skyfall trots stor skaderisk (26 May 2025) mynewsdesk.com · 3 linked claims

Open original source ↗

Stable source ID
src-89b4d30f36770498
Publisher
Name not classified · mynewsdesk.com
Type / language
web-page · language not classified
Published
2025-05-26
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-11
Dossier created
2026-11-12
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Kretslopp och vatten's campaign release. According to the cloudburst map some areas could flood with more than a metre of water; the city's citizen survey, carried out by Statistics Sweden, found that only a third of residents knew how to prepare for a cloudburst, the same result as in 2022; and protecting the city from cloudburst damage would require storage equal to 15 Karlatornet towers, hard to build underground.

Descriptive only — not page/paragraph exact
City of Gothenburg — Skyfallsanläggning i Stabbeparken färdig (18 Jun 2025) mynewsdesk.com · 2 linked claims

Open original source ↗

Stable source ID
src-7304528d1460ba82
Publisher
Name not classified · mynewsdesk.com
Type / language
web-page · language not classified
Published
2025-06-18
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-11
Dossier created
2026-11-12
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Release on the cloudburst facility in Stabbeparken, south of Östra Hospital: a gabion embankment built from November 2024 to the end of May 2025 that can hold up to 3,000 m³ and is calculated to reduce water depth around important hospital operations by up to a metre in a heavy cloudburst.

Descriptive only — not page/paragraph exact
Stadsrevisionen, City of Gothenburg — Skyfallshanteringen i Göteborgs Stad behöver bli bättre (22 Feb 2023) mynewsdesk.com · 1 linked claim

Open original source ↗

Stable source ID
src-7b162a6ecd196e34
Publisher
Name not classified · mynewsdesk.com
Type / language
web-page · language not classified
Published
2023-02-22
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-11
Dossier created
2026-11-12
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

The city audit office's release on its review of cloudburst management: knowledge of where and how the city will flood in a cloudburst is extensive, but only a few cloudburst facilities have been built and few are planned; responsibilities and goals need to be clearer, and there has been no overall follow-up.

Descriptive only — not page/paragraph exact
Stadsrevisionen, City of Gothenburg — Revisionsredogörelse 2022 för kretslopp- och vattennämnden (21 Mar 2023) www4.goteborg.se · 2 linked claims

Open original source ↗

Stable source ID
src-c4a02d588ebdec65
Publisher
Name not classified · www4.goteborg.se
Type / language
pdf · language not classified
Published
2023-03-21
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-11
Dossier created
2026-11-12
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

The audit office's account of its 2022 review of the Kretslopp och vatten committee. It summarises the cloudburst review decided on 21 February 2023: not enough city-wide decisions on what the city is to achieve and at what pace, unclear responsibilities and insufficient follow-up, and it notes that binding law covers new detailed plans but not existing buildings.

Descriptive only — not page/paragraph exact
Stadsrevisionen, City of Gothenburg — Stadsrevisionens årsredogörelse 2025, Handling 2026 nr 79 (13 Apr 2026) www4.goteborg.se · 1 linked claim

Open original source ↗

Stable source ID
src-a827b9b05f08fcbe
Publisher
Name not classified · www4.goteborg.se
Type / language
pdf · language not classified
Published
2026-04-13
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-11
Dossier created
2026-11-12
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

The audit office's annual report for 2025, sent to the city council. Its review of the city's climate adaptation plan 2024–2026 found that Gryaab, the Port of Gothenburg and the Kretslopp och vatten committee work on climate adaptation appropriately and that the work is organised, steered and followed up.

Descriptive only — not page/paragraph exact
City of Gothenburg — Ändring av översiktsplan för Göteborg, granskningshandling (May 2026) www5.goteborg.se · 2 linked claims

Open original source ↗

Stable source ID
src-f09a3b2855a57602
Publisher
Name not classified · www5.goteborg.se
Type / language
pdf · language not classified
Published
Not recorded
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-11
Dossier created
2026-11-12
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

The review version of the comprehensive-plan amendment, which works the flood-risk supplement into the plan and updates it. Its cloudburst section says facilities for diverting and retaining surplus water are sized so that a climate-adapted 100-year rain does not damage buildings and infrastructure.

Descriptive only — not page/paragraph exact
Known limits of this file
  • Publisher names and source languages have not yet been classified; domains are recorded without guessing.
  • Existing source notes are descriptive locators, not page- or paragraph-exact citations.
  • A missing archive, publication date or content hash is shown as null rather than inferred.
  • The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim.
📎 Cite this project

1001 Smart Cities (2026). “Gothenburg's Cloudburst Map: A Modelled 100-Year Rain and a Rule for New Buildings” — Gothenburg, Sweden. The Smart City Atlas. https://1001smartcities.org/projects/gothenburg-cloudburst-map/ (last verified 2026-11-11). Data: CC BY 4.0.

The underlying data is free to reuse with attribution — see the open data page.

✉️ One source-checked project a week. No pitches, no vendors.

Inside: the Landmark of the Week, one Insight, the newly documented cities. One-click unsubscribe. About the newsletter · RSS