Buenos Aires Subte: CBTC Resignalling & Control Centre
This overview was generated with AI from the public sources listed below and checked against them before publication. It has not had a complete human fact-check — treat it as a starting point and follow the sources.
14 sourced claims on this page, none individually verified yet — turn on “Sources in the text” to see each one.
How this atlas is made · What “last verified” means · What “source-checked” means · The full record behind this page
✎ Corrected 27 Sep 2026 3 sources added. What changed →
The city bought the signalling to run a train every 2 minutes 15 seconds. It still runs one every 3 minutes, because there are not enough trains to fill the gaps.
what does this mean?
The strongest source is an independent non-academic evaluation: an audit office, a government or EU review, or an NGO. It grades who did the looking — not how well the project went. All four grades →Part of 1001 Smart Cities — 1,216 documented projects · 🏙️ 10 more in Buenos Aires · 🚌 Public transport guide · 🚲 Mobility projects
Argentina handed its 1913 metro to the city in 2012, and the city agency SBASE has since put Siemens Trainguard MT CBTC on three of six lines — H in 2016, C in 2020, D in 2024 — and in August 2026 awarded Line B's resignalling to China's CRRC, again at GoA2. It runs attended automatic train operation at GoA2: the driver stays in the cab and presses to depart, and no Subte line is driverless or certified to be. Two round-the-clock control rooms track train positions alongside traction power, ventilation and pumping, SBASE publishes a static GTFS feed and the city a real-time transit API, but the city's open-data portal now lists every GTFS and API dataset as suspended for review. A city audit found the Line D programme finished one of three planned stages, five months late, reaching a 3-minute headway but not the promised 2:15 — there are not enough trains. Ridership has not recovered either: an estimated 199.1 million trips in 2024.
📊 Impact
Line D reached a 3-minute headway after resignalling, but the promised 2 minutes 15 seconds could not be verified in practice for lack of rolling stock, and one of three planned stages was completed, five months late — findings of an Auditoría General de la Ciudad report on the Line D works, reported April 2026.
Sources
Show 9 more sourcesShow fewer
📅 How old is the evidence?
Two clocks, kept apart: when this entry’s sources were published, and what has happened to its record in the atlas. Documented span: since 2016. 14 of 14 sources carry a publication date, from 28 December 2012 to 25 August 2026.
When the sources were published
- Gobierno de la Ciudad de Buenos Aires — Digesto Jurídico · city governmentLey 4472 (2012) — Digesto Jurídico de la Ciudad (text)
- enelSubte · pressenelSubte — Line C reopens operating with the new CBTC signalling
- Railway Gazette International · pressRailway Gazette / Metro Report — Siemens to resignal Buenos Aires Line D
- Siemens Mobility · vendorSiemens Mobility press release — CBTC signalling for Buenos Aires Line D (17 July 2020)
- Gobierno de la Ciudad de Buenos Aires · city governmentBuenos Aires Data — Subte GTFS (published by SBASE) · updated 1 July 2026
- Gobierno de la Ciudad de Buenos Aires · city governmentBuenos Aires Data — API Transporte Público (real-time feed) · updated 17 June 2026
- Gobierno de la Ciudad de Buenos Aires · city governmentBuenos Aires city government — inside the Subte's monitoring centre
- Gobierno de la Ciudad de Buenos Aires · city governmentBuenos Aires city government — Emova takes over operation and maintenance (30 Nov 2021)
Show 6 more dated sourcesShow fewer
- enelSubte · pressenelSubte — Lack of trains and signalling problems behind Line D's poor service (22 May 2024)
- enelSubte · pressenelSubte — Chinese firm CRRC pre-awarded the new Line B trains
- Observatorio del Derecho a la Ciudad · ngoObservatorio del Derecho a la Ciudad — passengers and fares on the Buenos Aires Subte, 2015–2025 (21 June 2025)
- Nueva Ciudad · pressNueva Ciudad — Line D: cost overruns, delays and failures in key works (15 April 2026)
- Diario CEMBA · pressDiario CEMBA — AGCBA detects irregularities and cost overruns in the Line D works
- enelSubte · pressenelSubte — Line B resignalling awarded to CRRC (25 Aug 2026)
What happened to this record
- Entered the record
- 3 sources added
- Sources last read
Show your work What this page rests on and what it can’t tell you · all 14 claims with their sources · the forensic record
Evidence file · public beta 14 addressable claims, 14 source dossiers, one permanent baseline. The file is unreviewed — an AI-assisted structural migration, not a human or expert endorsement. Every revision keeps a permanent copy under revision history.
Inspect the claims, one by one — verbatim text, sources and caveats for all 14
The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-b63266183af253d9
quantitative
Argentina handed its 1913 metro to the city in 2012
Sources carrying this claim
clm-e5f61a65494e3645
quantitative
the city agency SBASE has since put Siemens Trainguard MT CBTC on three of six lines — H in 2016, C in 2020, D in 2024
Sources carrying this claim
clm-e8743cf5b9dc2b57
quantitative
in August 2026 awarded Line B's resignalling to China's CRRC, again at GoA2
Sources carrying this claim
clm-078334afebcb3aae
quantitative
It runs attended automatic train operation at GoA2: the driver stays in the cab and presses to depart
Sources carrying this claim
clm-41ab108b03eec2db
descriptive
no Subte line is driverless or certified to be
Sources carrying this claim
clm-69c78697374174f4
descriptive
Two round-the-clock control rooms track train positions alongside traction power, ventilation and pumping
Sources carrying this claim
clm-6bb446f3160ca55a
descriptive
SBASE publishes a static GTFS feed and the city a real-time transit API
Sources carrying this claim
clm-2cb9493b90c29304
descriptive
the city's open-data portal now lists every GTFS and API dataset as suspended for review
Sources carrying this claim
clm-f89b0c45f47fd408
quantitative
A city audit found the Line D programme finished one of three planned stages, five months late, reaching a 3-minute headway but not the promised 2:15 — there are not enough trains
Sources carrying this claim
clm-cddfb73cef46fd18
quantitative
Ridership has not recovered either: an estimated 199.1 million trips in 2024
Sources carrying this claim
clm-a19f31b4f9ed3895
quantitative
Line D reached a 3-minute headway after resignalling, but the promised 2 minutes 15 seconds could not be verified in practice for lack of rolling stock, and one of three planned stages was completed, five months late
Sources carrying this claim
clm-f8022cc0652fa23a
quantitative
findings of an Auditoría General de la Ciudad report on the Line D works, reported April 2026
Sources carrying this claim
clm-bbcba6cf91ee2509
descriptive
Signalling sets the floor on headway; the fleet sets the actual service.
Sources carrying this claim
clm-23c98f7d8d417c63
quantitative
Buenos Aires bought the capacity to run a train every 2:15 and still runs one every 3.
Sources carrying this claim
Forensic record — source dossiers, gaps, hashes and the exact revision this page renders
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:015950dba3e30e85aaed4ea9007b9a456a1e19e40927d40489577f7b7460ef06
- 14
- of 14 claims mapped
- 14
- source dossiers
- 14
- publication dates recorded
- 1
- archives linked
- 0
- exact locators
- 0
- content captures hashed
Governance facts carried by the record
- Operator
- Subterráneos de Buenos Aires SE (SBASE), infrastructure and signalling; Emova Movilidad, operation and maintenance under concession
- Actor types
- utility, private
- Funding model
- public
- Funding description
- City of Buenos Aires capital works through SBASE
- Cost
- Not recorded
- Ownership
- Not recorded
- Decision rights
- Not recorded
- Exit conditions
- Not recorded
14 source dossiers
Railway Gazette / Metro Report — Siemens to resignal Buenos Aires Line D
- Stable source ID
src-11e5f5063586b54d- Publisher
- Name not classified · railwaygazette.com
- Type / language
- web-page · language not classified
- Published
- 2020-07-17
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
The load-bearing automation sentence: SBASE selected Siemens Mobility for CBTC on Line D, "with the CBTC supporting attended ATO to Grade of Automation 2". Also dates Trainguard MT on Line H to mid-2016 and its commissioning on Line C to February, and says it replaces an Alstom ATP in use since 2008, coordinated by a newly established operations control centre.
Siemens Mobility press release — CBTC signalling for Buenos Aires Line D (17 July 2020)
- Stable source ID
src-09db5a752fa1950f- Publisher
- Name not classified · press.siemens.com
- Type / language
- web-page · language not classified
- Published
- 2020-07-17
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Supplier confirmation of the contract award date. Fetched and read: it states no contract value and no automation grade, and does not mention lines H or C — so it corroborates the award only, not the GoA2 claim.
- Claims linked
- Background source; no baseline claim points here
enelSubte — Line C reopens operating with the new CBTC signalling
- Stable source ID
src-d6b1975dd46f9423- Publisher
- Name not classified · enelsubte.com
- Type / language
- web-page · language not classified
- Published
- 2020-02-03
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Trade press describing what GoA2 means in the cab: the driver presses a button and the train accelerates automatically to the next stop, and "can take control of the formation's operation at any moment". Dates the Line C reopening to 3 February 2020, replacing signalling in service since 1934, and states the 2:15 headway target depends on buying more trains — the line then had 13.
- Claims linked
enelSubte — Lack of trains and signalling problems behind Line D's poor service (22 May 2024)
- Stable source ID
src-3ee120497a6cb72b- Publisher
- Name not classified · enelsubte.com
- Type / language
- web-page · language not classified
- Published
- 2024-05-22
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Three months after the Line D cutover: Siemens was still updating software for line-specific behaviour, causing speed restrictions at platforms and station approaches; the Alstom 100 units — about a third of the fleet — could not run until calibration finished; journey times up 25%. "La línea funciona con menos trenes que antes."
- Claims linked
- Background source; no baseline claim points here
Nueva Ciudad — Line D: cost overruns, delays and failures in key works (15 April 2026)
- Stable source ID
src-1d37db47cf878087- Publisher
- Name not classified · nueva-ciudad.com.ar
- Type / language
- web-page · language not classified
- Published
- 2026-04-15
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- Open archived copy ↗ · 2026-05-21
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Carries the impact figures from an Auditoría General de la Ciudad report: the signalling project "contemplaba tres etapas, pero solo una se completó (con cinco meses de atraso)"; the completed phase enabled a 3-minute frequency while the promised 2:15 cannot be verified because "falta material rodante suficiente"; works advanced "sin un plan de trabajo aprobado para su etapa final". FETCH FAILURE, flagged: the AGCBA report PDF itself returned unreadable binary to automated fetching, so these audit findings are verified at press level, not against the primary document. The 48.11% cost increase and nine-month extension in the same audit belong to the Palermo and Scalabrini Ortiz station works, not to the signalling, and are deliberately excluded here.
Diario CEMBA — AGCBA detects irregularities and cost overruns in the Line D works
- Stable source ID
src-2b0548d490e8414f- Publisher
- Name not classified · cemba.com.ar
- Type / language
- web-page · language not classified
- Published
- 2026-04-28
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Second outlet independently confirming that the Auditoría General de la Ciudad report on the Line D works exists and its supervision findings — SBASE assigned a single works director without a full technical team or inspection plan.
- Claims linked
Buenos Aires city government — inside the Subte's monitoring centre
- Stable source ID
src-29ed425464af202a- Publisher
- Name not classified · buenosaires.gob.ar
- Type / language
- web-page · language not classified
- Published
- 2021-10-05
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Operator/authority description of the Puesto Central de Operaciones: two centres, one for lines A–E and one for line H, 26 staff, running "las 24 horas, los 365 días del año", monitoring train positions and signalling plus power, ventilation and pumping systems. No performance data is published from it — the entry claims none.
- Claims linked
Buenos Aires Data — Subte GTFS (published by SBASE)
- Stable source ID
src-bbddec0b269cde5b- Publisher
- Name not classified · data.buenosaires.gob.ar
- Type / language
- web-page · language not classified
- Published
- 2021-05-10
- Updated
- 2026-07-01
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Static GTFS for the Subte, publisher Subterráneos de Buenos Aires (SBASE), licence CC-BY-2.5-AR. Checked 26 July 2026: the page carried the notice "Se informa a los usuarios de BA DATA que todos los datasets con Formato API y GTFS, están suspendidos. Se encuentran en revisión y corrección", with no date given.
- Claims linked
Buenos Aires Data — API Transporte Público (real-time feed)
- Stable source ID
src-45839c2963435014- Publisher
- Name not classified · data.buenosaires.gob.ar
- Type / language
- web-page · language not classified
- Published
- 2021-05-10
- Updated
- 2026-06-17
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
The real-time layer: for subte it provides static GTFS, forecastGTFS (trips currently running) and service alerts, licence CC-BY-2.5-AR, published by the Secretaría de Transporte y Obras Públicas; the portal states the API is used by Google and Moovit and is open to any developer on registration. Carries the same suspension notice as the GTFS dataset.
- Claims linked
Observatorio del Derecho a la Ciudad — passengers and fares on the Buenos Aires Subte, 2015–2025 (21 June 2025)
- Stable source ID
src-f4f7798b7d29be36- Publisher
- Name not classified · observatoriociudad.org
- Type / language
- web-page · language not classified
- Published
- 2025-06-21
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Independent NGO report, drawing on the Centro de Estudios Metropolitanos and official statistics: 199,116,074 passengers in 2024, and March 2025 at "apenas el 54% de los pasajeros de marzo de 2019". Two different 2019 annual totals circulate (about 325 and about 341 million) and neither is used here. FETCH FAILURE, flagged: the official Instituto de Estadística y Censos series at estadisticaciudad.gob.ar looped on a host redirect and could not be read to settle the 2019 figure.
- Claims linked
enelSubte — Chinese firm CRRC pre-awarded the new Line B trains
- Stable source ID
src-79ba5d51049b8c54- Publisher
- Name not classified · enelsubte.com
- Type / language
- web-page · language not classified
- Published
- 2025-06-10
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Establishes the limit of the rollout: CBTC operates on lines C, D and H only, no installation has been announced for Line B, and the new Line B trains must suit the existing ATP while being "prepared for a possible conversion to CBTC with ATO in GoA2" — the city itself specifies GoA2 as the ceiling.
- Claims linked
enelSubte — Line B resignalling awarded to CRRC (25 Aug 2026)
- Stable source ID
src-5fb5e0bf0ebfd8f7- Publisher
- Name not classified · enelsubte.com
- Type / language
- web-page · language not classified
- Published
- 2026-08-25
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
SBASE awarded Zhuzhou CRRC Times Electric, the CRRC unit building Line B's 29 new trains, a contract to replace Line B's ATP with CBTC at GoA2; CBTC to enter service 20 months after works start with 17 trains, full conversion at 34 months. Also dates CBTC on H (July 2016), C (February 2020) and D (March 2024), all Siemens Trainguard MT.
Ley 4472 (2012) — Digesto Jurídico de la Ciudad (text)
- Stable source ID
src-b5243fe702839ba4- Publisher
- Name not classified · digesto.buenosaires.gob.ar
- Type / language
- web-page · language not classified
- Published
- 2012-12-28
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Official digest entry for Ley 4472: sanctioned 19 December 2012, published in the Boletín Oficial 28 December 2012. The law has the City assume the Subte public service and designates SBASE as the authority for infrastructure, maintenance and the operating control systems. Replaces the dead cedom.gov.ar URL. (Full text PDF: digesto.buenosaires.gob.ar/documento/download/Ley%20Ciudad-4472__958d201cd37ba4daaed819996f963099cc2ad0e6.pdf)
- Claims linked
Buenos Aires city government — Emova takes over operation and maintenance (30 Nov 2021)
- Stable source ID
src-74f5dbc91f4bdb43- Publisher
- Name not classified · buenosaires.gob.ar
- Type / language
- web-page · language not classified
- Published
- 2021-11-30
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-09-27
- Dossier created
- 2026-09-27
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
The city announces that Emova Movilidad S.A., of the Benito Roggio Transporte group, takes over Subte and Premetro operation and maintenance on 1 December 2021 for 12 years, extendable by three, replacing a 20-year concession. Readable replacement for the Página/12 source.
- Claims linked
- Background source; no baseline claim points here
Known limits of this file
- Publisher names and source languages have not yet been classified; domains are recorded without guessing.
- Existing source notes are descriptive locators, not page- or paragraph-exact citations.
- A missing archive, publication date or content hash is shown as null rather than inferred.
- The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim.
Continue exploring
Compare this project
Explore the wider context
📎 Cite this project
1001 Smart Cities (2026). “Buenos Aires Subte: CBTC Resignalling & Control Centre” — Buenos Aires, Argentina. The Smart City Atlas. https://1001smartcities.org/projects/buenos-aires-subte-signalling/ (last verified 2026-09-27). Data: CC BY 4.0.
The underlying data is free to reuse with attribution — see the open data page.