A 2005 federal consent decree with the EPA, the Justice Department and the District — not the utility's own choice — obliges DC Water to end combined sewer overflows
Permanent project revision
Revision 2026-08-21-source-dates · effective 2026-07-26
Current revision. This is the snapshot used by the live entity page.
Record the publication date of each source that states one; a source that publishes no date is marked null, and one that shows only a revision carries `updated` instead.
sha256:b5d1183023e90c042019c18cc80cae1a72670ea22a19879bb4a9a41bb1874d2a
replace /snapshot/projectFingerprint — Updated projectFingerprint to the current sourced project record.replace /snapshot/sources — Updated sources to the current sourced project record.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-b23220304e86eb51
quantitative
A 2005 federal consent decree with the EPA, the Justice Department and the District — not the utility's own choice — obliges DC Water to end combined sewer overflows
clm-baaab8a5b1098943
descriptive
Three deep tunnels are in service
clm-22e9952a1237f49b
descriptive
Twenty-two flow-metering stations and a calibrated sewer model produce the quarterly overflow accounting the decree demands
clm-a4ad12ae2461c056
descriptive
while inflatable dams, dynamically controlled weirs and outfall gates steer the flow
clm-fc8bf4881ef9df05
descriptive
Every District property pays by impervious area
clm-a3b82e9cb3687273
quantitative
DC Water reports the Anacostia River Tunnel kept about 4.5 billion gallons of sewage out of the river in 2018 alone, its first year
clm-9efab099491aa0fa
quantitative
that overflows to the Anacostia are down roughly 90% since it opened in March 2018
clm-df494bf167c99772
quantitative
DC Water expects 98% for the Anacostia and 96% system-wide, and puts the chance of flooding in Northeast in an average rainfall year at 7%, down from 50%
clm-72340765c972c797
descriptive
All figures are the utility's own; the decree's compliance accounting is quarterly, from flow meters plus a model, not a live public measurement
clm-1b953d87e7837116
quantitative
The 2015-16 modification let green infrastructure try to replace concrete in Rock Creek and shrink the Potomac tunnel
clm-21486f455bb5688b
quantitative
DC Water assessed it, then broke ground on the Piney Branch Tunnel in July 2026 as the programme's final major tunnel
clm-c8b0ac763506ce39
descriptive
the tunnels intercept combined sewage, not failing pipes or illicit connections
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:b5d1183023e90c042019c18cc80cae1a72670ea22a19879bb4a9a41bb1874d2a
src-a2c555c8759fa950The decree itself, sentence-level: a 2005 federal consent decree among EPA, the Department of Justice, the District of Columbia and DC Water, requiring storage tunnels in the Anacostia, Potomac and Rock Creek watersheds. Penalty $250,000, plus $1.7m for rain gardens and low-impact development and $300,000 to the Chesapeake Bay Foundation for green roofs. Anacostia work due 2025, Potomac and Rock Creek extended to 2030. Expected outcomes stated as 98% of CSOs eliminated in the Anacostia, 93% Potomac, 90% Rock Creek.
src-fa917666e2605d06The modification, sentence-level: 'Using green infrastructure to retain the first 1.2 inches of rainwater on 365 acres in the Rock Creek area and 133 acres in the Potomac watershed', potentially 'eliminating the Rock Creek storage tunnel and significantly decreasing the size of the Potomac tunnel', in exchange for 'an additional five years to complete implementation in the Potomac and Rock Creek watersheds'. The Anacostia system stayed on schedule: 'Major portions of this tunnel system are scheduled for completed and in operation in 2018.' DOJ announced the proposal in May 2015; DC Water dates the signed modification to 14 January 2016.
src-f89994afefe31af6The reason this is an atlas entry and not only civil engineering, sentence-level: the system includes '22 flow-metering stations' and is regulated by 'inflatable dams, dynamically controlled weirs, outfall gates and other flow regulating devices', alongside '9 wastewater pumping stations', 'approximately 1,800 miles of sanitary and combined sewers' and '75,000 catch basins and manholes'.
src-124450ba0dbb1e87How overflows are counted, sentence-level: 'DC Water uses a combination of flow meters and a computer model of the combined sewer system to measure and/or estimate the actual CSOs that have occurred on a quarterly basis', published as CSO Division Quarterly Operation Reports and Long Term Control Plan Consent Decree Quarterly Reports. The only real-time public signal: 'DC Water has installed a series of CSO Event Indicator Lights to notify river users of CSO events' — red for an active overflow, yellow for 24 hours afterwards. No predictive or real-time control of the tunnel system is described anywhere on DC Water's site, and the entry claims none.
src-8d4c06a323f4cfabProgramme scope and targets, sentence-level: 'over 18 miles of tunnels' more than 100 feet below ground, fed by diversion chambers, approach channels, roughly 100-foot drop shafts and adits, all draining to Blue Plains. Targets stated as 96% system-wide CSO reduction, 98% Anacostia, 93% Potomac, 90% Rock Creek, and chronic flooding risk in Northeast cut 'from 50% to 7%'. The page lists a 2016 amended consent decree and a 2020 joint stipulation of non-material modification. These are targets, not measurements — the entry treats them as such.
src-7da3e77dad5ac178The 90% figure and its owner, sentence-level: 'combined sewer overflows to the Anacostia River have been reduced by 90 percent' since completion in March 2018. Tunnel is 'approximately 12,500 feet', '23-foot diameter', 'approximately 80 to 120 feet deep'. The page mentions diversion facilities and 'ventilation control facilities to regulate air flow' but no gates, pumping or monitoring detail — so the control layer is sourced from the collection-system pages instead.
src-18cc5d172d1d6dd1First-year volume, carried in the release title and matched by independent WJLA coverage under the same figure. Search results also gave 4.57 billion gallons and nearly 900 tons of trash and solids for March to 31 December 2018, but that sentence was not read on a rendered page, so the entry rounds to 'about 4.5 billion gallons' rather than quoting the finer number.
src-8ca2e3ab4569eceeThe lesson's evidence, sentence-level: groundbreaking 9 July 2026 on 'about a half-mile, 22-foot wide tunnel deep underground' holding 'at least 4.2 million gallons', finished 'by the end of 2029', cutting Piney Branch overflow volume by 96% and frequency from about 25 times a year to about once. The 2015-16 modification had contemplated green infrastructure replacing a 9.5-million-gallon Rock Creek storage facility; the tunnel is being built.
src-218e78bd0aa21fa4The financing mechanism, exactly: $24.23 per equivalent residential unit per month effective 1 October 2025 (FY2026). An ERU is 'a statistical median of the amount of impervious surface area in a single-family residential property, measured in square feet'. Six tiers, from 0.6 ERU at $14.54 a month for 100-699 sq ft of impervious cover to 13.5 ERU at $327.11 for 11,100 sq ft and above. The charge is levied on impervious area, not on water consumed.
src-7252e6f2161d35bdCost and the political counterweight: 'a multi-year $3.5 billion infrastructure project kicked off in 2009', construction wrapping up in 2030, 'each ERU now costs homeowners around $24 a month', projected to 'top out at more than $32 per ERU per month' by 2030. Ward 6 Councilmember Charles Allen on the satellite-measured billing: 'a picture from a satellite doesn't capture that very well, which puts the onus back on the homeowner.' Churches and nonprofits called the charge 'a heavy burden', prompting council relief programmes.
src-a5558be96eac7cd7Current construction status: the cutterhead for TBM Mary lowered down a 100-foot shaft at West Potomac Park, tunnelling to start spring 2026 on the 5.5-mile run from the Georgetown waterfront to Blue Plains, with a second machine, Emily, for the 3.1-mile southern segment. Substantial completion expected 2028, full completion February 2030, 'the date set by a consent decree between the federal government, D.C. government and D.C. Water'. Read via search summary rather than a rendered page; the 2030 decree deadline is independently confirmed by the EPA settlement page.
src-8c5df9904b922cd8Deliberately kept out of the snippet and impact, like the Comparitech and IQAir precedents, because it is a single outlet's reading of someone else's data. Llewellyn Jones, 'based on data from D.C.'s Department of Energy and Environment (DOEE)'s water quality reports to the EPA', reports the upper Anacostia out of compliance for E. coli about 92% of the time against under 40% before the tunnel, and attributes the gap to 'failing sewer pipes and illicit discharges' rather than CSOs. The underlying DOEE reports were not reached, and no DC Water response is included. The Anacostia Watershed Society's 2025 report card, by contrast, gave sample year 2024 a passing grade, its second highest since 2014.