Permanent project revision

Porto Alegre Flood Protection System and Pumping-Station Telemetry

Revision 2026-11-15-baseline · effective 2026-11-15

Current revision. This is the snapshot used by the live entity page.

unreviewed

Created the first structured Evidence Passport with 16 claims and 10 source dossiers.

sha256:1559e5801667cb75ceb1aa43258f71289a0bcc635a7f3d1e350eca9af62afa6c

Change set

  • add /evidencePassport — Added claim-level evidence mapping and source dossiers.
  • add /revisionHistory — Established a permanent, hash-addressed baseline revision.
16
of 16 claims mapped
10
source dossiers
9
publication dates recorded
0
archives linked
0
exact locators
0
content captures hashed

Claims, one by one

The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.

Claim 2 clm-0021bbc7392312f6 quantitative
23 stormwater pumping stations, all run by the municipal water department Dmae
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The city magazine says 23 Ebaps are in operation; the October 2026 release describes the stations as operated by Dmae.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Prefeitura de Porto Alegre — Revista Mais POA, ed. 8 (Aug 2026)
  2. Prefeitura de Porto Alegre — Obras de resiliência climática avançam nas casas de bombas (28 Oct 2026)
Claim 3 clm-ab6fa681145c0348 quantitative
In May 2024 the Guaíba reached 5.37 metres at Cais Mauá, 2.37 metres above the flood level
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The city magazine gives the May 2024 peak and its height above the flood level.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Prefeitura de Porto Alegre — Revista Mais POA, ed. 8 (Aug 2026)
Claim 5 clm-6c44658a6aea9ff8 quantitative
state auditors found the system had started failing before the river reached its 1941 record
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The report on the TCE-RS audit quotes its finding that the system began to fail before levels reached the 1941 flood.
Caveat
The audit report itself was not available to us; this is the press account of it.

Sources carrying this claim

  1. Brasil de Fato — TCE responsabiliza Melo e Marchezan por falhas no sistema de proteção contra cheias (8 Dec 2025)
Claim 6 clm-8dfa0416771ee701 quantitative
since April 2025 telemetry sensors in all 23 pumping stations report the level of each suction well, in real time, to Dmae's control centre
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
Jornal do Comércio dates the telemetry installation to April and says it covers the 23 units; the Dmae release says the sensors show well levels in real time to the Centro de Controle Operacional.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Jornal do Comércio — Dmae investe R$ 300 milhões, mas combate aos alagamentos ainda é desafio (28 Apr 2025)
  2. Prefeitura de Porto Alegre — Sensores reforçam capacidade operacional das casas de bombas (17 Apr 2025)
Claim 7 clm-233ad1be998c7ce0 quantitative
Of the 14 floodgates, eight have been replaced by permanent concrete
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The July 2026 release says eight of the 14 gates were replaced by permanent reinforced-concrete structures.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Prefeitura de Porto Alegre — Dmae conclui modernização das comportas (8 Jul 2026)
Claim 8 clm-78766d4ebf4f45f7 quantitative
the remaining six are closed by Dmae under a protocol keyed to the Cais Mauá gauge, starting at 2.84 metres when forecasts show the river will pass the 3-metre flood level
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
Dmae's protocol: closing starts at 2.84 m on the Cais Mauá gauge only when forecasts show the 3 m flood level will be exceeded; six remaining gates.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Prefeitura de Porto Alegre — Saiba como o Dmae define o fechamento das comportas (30 Jul 2026)
Claim 9 clm-cf8d2f298985e62e quantitative
concluded that the 2024 flood did not reach the reference level the system was designed for in 1970
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The report quotes the audit's justification that the Guaíba did not reach the reference level projected in 1970.
Caveat
The audit report itself was not available to us; this is the press account of it.

Sources carrying this claim

  1. Brasil de Fato — TCE responsabiliza Melo e Marchezan por falhas no sistema de proteção contra cheias (8 Dec 2025)
Claim 10 clm-cd5379c701d0f50b quantitative
examined design, maintenance and municipal management, suggested that 33 people be summoned
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The report lists the three aspects analysed and says the audit suggests 33 people be summoned.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Brasil de Fato — TCE responsabiliza Melo e Marchezan por falhas no sistema de proteção contra cheias (8 Dec 2025)
Claim 11 clm-3df4062d3f156a7c descriptive
found ample indications of gross negligence by mayors Sebastião Melo and Marchezan
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The report says the court found ample indications of gross negligence or gross error by Melo and Marchezan.
Caveat
These are audit findings in an ongoing process, not a final judgment.

Sources carrying this claim

  1. Brasil de Fato — TCE responsabiliza Melo e Marchezan por falhas no sistema de proteção contra cheias (8 Dec 2025)
Claim 12 clm-a70657c81d975c5a quantitative
The audit followed a 2024 request by the public accounts prosecutor that also asked whether the failure of pumping station 16 flooded parts of Cidade Baixa and Menino Deus.
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
Brasil de Fato reports the Ministério Público de Contas representation, which asks about the non-operation of EBAP 16 and the flooding of Cidade Baixa and Menino Deus.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Brasil de Fato — Gestores do DMAE e da prefeitura serão auditados (15 Jul 2024)
Claim 13 clm-ce0f31998d4d6fc6 descriptive
the sensors indicate when the motors should run
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The magazine's glossary says the control centre indicates automatically when station motors should be switched on, based on monitored levels.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Prefeitura de Porto Alegre — Revista Mais POA, ed. 8 (Aug 2026)
Claim 15 clm-2ba57919f793b409 quantitative
A UFRGS hydraulics researcher says the original design was sound, but that in 2024 several pumping stations were not operational and their check valves were missing or broken
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
Fernando Meirelles (IPH/UFRGS) defends the original design and says pumping stations were not operational and check valves did not exist or were broken.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Jornal do Comércio — Desastre anunciado: o que causou a enchente histórica de 2024 no RS (28 Apr 2025)
Claim 16 clm-ae0dc6e9ddf43349 descriptive
former Dmae directors said the dikes and walls did not leak, the floodgates did
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The manifesto by former Dmae and DEP directors says the dikes and walls do not leak and that the leaks are in the floodgates.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. Instituto Humanitas Unisinos (IHU) — Ex-diretores do Dmae e DEP apontam falta de manutenção (15 May 2024)

Source dossiers and revision state

This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.

unreviewed Revision 2026-11-15-baseline effective 2026-11-15 · created 2026-11-15

Awaiting operator and domain-expert review; publication of this revision implies neither.

sha256:1559e5801667cb75ceb1aa43258f71289a0bcc635a7f3d1e350eca9af62afa6c
16
of 16 claims mapped
10
source dossiers
9
publication dates recorded
0
archives linked
0
exact locators
0
content captures hashed

Governance facts carried by the record

Operator
Departamento Municipal de Água e Esgotos (Dmae), Prefeitura de Porto Alegre
Actor types
city-government, utility, regional-government
Funding model
public
Funding description
Dmae budget plus the state Fundo do Plano Rio Grande (Funrigs) for the 2026–2027 pumping-station works
Cost
R$ 1 million for the pumping-station telemetry (Dmae, April 2025)
Ownership
Not recorded
Decision rights
Not recorded
Exit conditions
Not recorded

10 source dossiers

Prefeitura de Porto Alegre — Sensores reforçam capacidade operacional das casas de bombas (17 Apr 2025) prefeitura.poa.br · 2 linked claims

Open original source ↗

Stable source ID
src-633c820acfff286e
Publisher
Name not classified · prefeitura.poa.br
Type / language
web-page · language not classified
Published
2025-04-17
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-15
Dossier created
2026-11-15
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Dmae release: telemetry sensors in the stormwater pumping stations (Ebaps) report well levels in real time to the Centro de Controle Operacional; R$ 1 million; motor automation named as the next step; 17 stations with generators.

Descriptive only — not page/paragraph exact
Jornal do Comércio — Dmae investe R$ 300 milhões, mas combate aos alagamentos ainda é desafio (28 Apr 2025) jornaldocomercio.com · 2 linked claims

Open original source ↗

Stable source ID
src-5a9d787de9d59c8d
Publisher
Name not classified · jornaldocomercio.com
Type / language
web-page · language not classified
Published
2025-04-28
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-15
Dossier created
2026-11-15
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Report on Dmae's first year after the flood: R$ 300 million spent, telemetry installed in April 2025 in all 23 pumping stations, floodgate system installed in 1970, three gates closed permanently.

Descriptive only — not page/paragraph exact
Prefeitura de Porto Alegre — Revista Mais POA, ed. 8 (Aug 2026) prefeitura.poa.br · 3 linked claims

Open original source ↗

Stable source ID
src-b5b857674c3e9655
Publisher
Name not classified · prefeitura.poa.br
Type / language
pdf · language not classified
Published
Not recorded
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-15
Dossier created
2026-11-15
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

City magazine on the flood-protection plan: Guaíba peak of 5.37 m at Cais Mauá in May 2024, 23 Ebaps in operation, control-centre glossary (sensors indicate when motors should run), Civil Defence monitoring.

Descriptive only — not page/paragraph exact
Prefeitura de Porto Alegre — Dmae conclui modernização das comportas (8 Jul 2026) prefeitura.poa.br · 2 linked claims

Open original source ↗

Stable source ID
src-d1d74e71de56208b
Publisher
Name not classified · prefeitura.poa.br
Type / language
web-page · language not classified
Published
2026-07-08
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-15
Dossier created
2026-11-15
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

City release on completing the floodgate works: eight of 14 gates replaced by permanent concrete, gates 11 and 12 replaced, mayor's statement that the barrier did not hold in 2024.

Descriptive only — not page/paragraph exact
Prefeitura de Porto Alegre — Saiba como o Dmae define o fechamento das comportas (30 Jul 2026) prefeitura.poa.br · 1 linked claim

Open original source ↗

Stable source ID
src-256bccd5a5cfdb6f
Publisher
Name not classified · prefeitura.poa.br
Type / language
web-page · language not classified
Published
2026-07-30
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-15
Dossier created
2026-11-15
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Dmae's floodgate-closing protocol: Cais Mauá gauge alert level 2.5 m, flood level 3 m; mobilisation at 2.74 m; closing from 2.84 m only when forecasts show the flood level will be passed; six remaining gates.

Descriptive only — not page/paragraph exact
Brasil de Fato — TCE responsabiliza Melo e Marchezan por falhas no sistema de proteção contra cheias (8 Dec 2025) brasildefato.com.br · 4 linked claims

Open original source ↗

Stable source ID
src-083ae50abffb9ddf
Publisher
Name not classified · brasildefato.com.br
Type / language
web-page · language not classified
Published
2025-12-08
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-15
Dossier created
2026-11-15
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Report (citing Matinal Jornalismo) on the TCE-RS audit of the 2024 failures of the flood-protection system: system began failing before the 1941 level, three aspects analysed, 33 people to be summoned, indications of gross negligence by Melo and Marchezan.

Descriptive only — not page/paragraph exact
Brasil de Fato — Gestores do DMAE e da prefeitura serão auditados (15 Jul 2024) brasildefato.com.br · 1 linked claim

Open original source ↗

Stable source ID
src-ece6c0ffbfe4349a
Publisher
Name not classified · brasildefato.com.br
Type / language
web-page · language not classified
Published
2024-07-15
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-15
Dossier created
2026-11-15
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Report on the Ministério Público de Contas representation that opened a special accounts process on Dmae's maintenance of the flood-protection system 2018–2024, including whether pumping station 16 failed.

Descriptive only — not page/paragraph exact
Jornal do Comércio — Desastre anunciado: o que causou a enchente histórica de 2024 no RS (28 Apr 2025) jornaldocomercio.com · 1 linked claim

Open original source ↗

Stable source ID
src-bfea00287c8c1d1f
Publisher
Name not classified · jornaldocomercio.com
Type / language
web-page · language not classified
Published
2025-04-28
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-15
Dossier created
2026-11-15
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Report on the causes of the 2024 flood quoting UFRGS IPH researcher Fernando Meirelles on non-operational pumping stations, missing or broken check valves and the ordinary gate on Avenida Castelo Branco.

Descriptive only — not page/paragraph exact
Instituto Humanitas Unisinos (IHU) — Ex-diretores do Dmae e DEP apontam falta de manutenção (15 May 2024) ihu.unisinos.br · 1 linked claim

Open original source ↗

Stable source ID
src-9530e20da0b2dbde
Publisher
Name not classified · ihu.unisinos.br
Type / language
web-page · language not classified
Published
2024-05-15
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-15
Dossier created
2026-11-15
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Manifesto by former Dmae and DEP directors and specialists (May 2024): the system is robust but poorly maintained; leaks were in the floodgates, not the dikes and walls.

Descriptive only — not page/paragraph exact
Prefeitura de Porto Alegre — Obras de resiliência climática avançam nas casas de bombas (28 Oct 2026) prefeitura.poa.br · 1 linked claim

Open original source ↗

Stable source ID
src-af8f55c1d4bfd390
Publisher
Name not classified · prefeitura.poa.br
Type / language
web-page · language not classified
Published
2026-10-28
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-11-15
Dossier created
2026-11-15
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Dmae release on the R$ 202 million resilience works at 18 pumping stations (raised electrical panels, permanent generators), funded by the state Funrigs fund and Dmae, due through 2027.

Descriptive only — not page/paragraph exact
Known limits of this file
  • Publisher names and source languages have not yet been classified; domains are recorded without guessing.
  • Existing source notes are descriptive locators, not page- or paragraph-exact citations.
  • A missing archive, publication date or content hash is shown as null rather than inferred.
  • The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim.