Johannesburg Broadband Network (BWired/MTC): City Fibre Bought Back for R1.3 Billion

Revision 2026-10-11-baseline · effective 2026-10-11

Current revision. This is the snapshot used by the live entity page.

unreviewed

Created the first structured Evidence Passport with 22 claims and 10 source dossiers.

sha256:3136cde0539bc1b95a7b0fb026dcc7942ebeebd2470b3b2ac89416a67e6332dc

Change set

  • add /evidencePassport — Added claim-level evidence mapping and source dossiers.
  • add /revisionHistory — Established a permanent, hash-addressed baseline revision.
22
of 22 claims mapped
10
source dossiers
9
publication dates recorded
0
archives linked
0
exact locators
0
content captures hashed

Claims, one by one

The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.

Claim 1 clm-b27685db3c29ab1d quantitative
began in June 2010 as a 15-year build-operate-transfer contract with Ericsson SA
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
MTC's own history, reproduced by TechFinancials, says Ericsson South Africa was commissioned in June 2010 to build and operate a city-wide network over 15 years, three to build and twelve to operate; ITWeb reported in 2015 that Ericsson won the deal in 2010 to run the project for 15 years.
Caveat
The city's 2017 statement dates the tender award to 19 December 2008; the award and the signed contract are two years apart.

Sources carrying this claim

  1. TechFinancials — City of Jo'burg identifies a potential buyer for its broadband network (23 Feb 2021)
  2. ITWeb — BWired appointed to run R3.4bn Joburg network (18 Feb 2015)
Claim 2 clm-ece27ff03dcb7762 descriptive
ceded to CitiConnect Communications and BWired
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
ITWeb reports that Ericsson SA 'later ceded it to CitiConnect Communications', which manages BWired, an entity the city established with Ericsson SA; TechFinancials carries MTC's account that BWired was set up by the city and Ericsson to operate and commercialise the network.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. ITWeb — BWired appointed to run R3.4bn Joburg network (18 Feb 2015)
  2. TechFinancials — City of Jo'burg identifies a potential buyer for its broadband network (23 Feb 2021)
Claim 3 clm-60a7d0761a7ffd8f quantitative
About 900 km was laid by mid-2013
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
MTC's history says that by the middle of 2013 CCC had built approximately 900 kilometres; ITWeb's 2015 report speaks of '900km of fibre-optic cables that have been rolled out'.
Caveat
The length varies by source and date: MTC's 2015/16 report says 1150 km rolled out, the 2019 sale notice 1 000 km, the 2026/27 business plan 1,200 km.

Sources carrying this claim

  1. TechFinancials — City of Jo'burg identifies a potential buyer for its broadband network (23 Feb 2021)
  2. ITWeb — BWired appointed to run R3.4bn Joburg network (18 Feb 2015)
Claim 4 clm-a57d7cc6bf98ab80 quantitative
the 1 July 2013 go-live was missed
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
ITWeb states the network 'was initially envisaged to become operational on 1 July 2013, but the termination of the original contract scuppered that deadline'; in January 2015 TimesLIVE described a network that 'remains unused 18 months after it was expected to deliver fast internet'.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. ITWeb — Future of Joburg's broadband network remains unclear (21 Jan 2019)
  2. TimesLIVE — R1.2bn bill looms for fibre optic farce (5 Jan 2015)
Claim 5 clm-b50f5edb1bbc5dc9 quantitative
on 31 July 2014 the city cancelled the contract for breaches
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The city's statement says 'On 31 July 2014, the City terminated the agreement so as to operate the network itself through the MTC'; MTC's integrated report says CCC/BWired 'had committed numerous acts of repudiation of its obligation under the BOT' and that the city cancelled it on that date.
Caveat
The substance of the breaches comes from the city's side only: ITWeb (2015) reports intermediary companies selling spare capacity and fibre for a second network laid in the city's trenches. CitiConnect's position is not in these sources.

Sources carrying this claim

  1. City of Johannesburg — Investigation into City's R1.3 billion acquisition of Broadband Network (10 Mar 2017)
  2. Metropolitan Trading Company — Integrated Report 2015/16
Claim 6 clm-6e8194fb611aae3e quantitative
paid R1.3 billion to buy the network out
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The mayor's statement: 'the City chose to buy out the agreement at a cost of R1.3 billion'; MTC's report values the asset transferred as part of the JBN business at R1,3 billion.
Caveat
Earlier figures differ: ITWeb reported in February 2015 that the city would pay R1.2 billion, and MTC's own history gives the September 2015 transfer at approximately R1.25 billion. The entry uses the city's and MTC's R1.3 billion.

Sources carrying this claim

  1. City of Johannesburg — Investigation into City's R1.3 billion acquisition of Broadband Network (10 Mar 2017)
  2. Metropolitan Trading Company — Integrated Report 2015/16
Claim 7 clm-e5e7223863f1ade6 quantitative
from September 2015 ran it through its own Metropolitan Trading Company (now Metropolitan Tech Company, MTC)
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
MTC's report gives 3 September 2015 as the effective date of transfer of the business and network to MTC, a municipal entity 100% owned by the municipality; the city's 2017 statement says MTC commenced operations on 30 September 2015; the Sunday Times describes the company as 'formerly the Metropolitan Trading Company'.
Caveat
Two city documents give two September dates (3 and 30 September 2015); the entry says only the month.

Sources carrying this claim

  1. Metropolitan Trading Company — Integrated Report 2015/16
  2. City of Johannesburg — Investigation into City's R1.3 billion acquisition of Broadband Network (10 Mar 2017)
  3. Sunday Times / Our City News — Joburg's Wi-Fi plan falters amid litany of woes (20 Sep 2026)
Claim 8 clm-cdb8e318dd467738 quantitative
A forensic investigation ordered in 2017 put the deal's costs at R1.7 billion
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The city announced the independent forensic investigation on 10 March 2017; in December 2017 the mayor reported that 'the investigation has since revealed that costs relating to the deal currently amount to R1.7-billion' and were likely to rise.
Caveat
The figure is the mayor's summary of a progress report; the Nexus Forensic Services report itself has not been published. The same statement said a minister and deputy minister benefited by 'almost R200-million'; ITWeb's 2019 retelling gives R279 million.

Sources carrying this claim

  1. TimesLIVE — Minister implicated in dodgy R1.7bn Joburg broadband tender (13 Dec 2017)
  2. City of Johannesburg — Investigation into City's R1.3 billion acquisition of Broadband Network (10 Mar 2017)
Claim 9 clm-7922c22eb279752b descriptive
The fibre now links municipal buildings and carries free public Wi-Fi
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The city's August 2026 article on MTC's rehabilitation programme says 'the fibre network underpins municipal buildings, public Wi-Fi, digital communication systems and other smart city services', with work under way in Randburg, Sandton, Alexandra and other areas.
Caveat
The city's own description; no independent account of what the network carries was found.

Sources carrying this claim

  1. City of Johannesburg — Metropolitan Tech Company is strengthening Johannesburg's digital backbone (6 Aug 2026)
Claim 10 clm-23020b95adf706d4 quantitative
26 network staff maintaining about 1,200 km
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
Reporting MTC's 2026/27 business plan, the Sunday Times says the company is 'relying on just 26 network employees to maintain 1,200km of fibre' and that the plan calls MTC 'currently under-capacitated'.
Caveat
Figures from the business plan as reported by the newspaper; MTC did not answer its questions, and the plan itself was not read.

Sources carrying this claim

  1. Sunday Times / Our City News — Joburg's Wi-Fi plan falters amid litany of woes (20 Sep 2026)
Claim 11 clm-0267c29f2b7f50b8 quantitative
a Wi-Fi target of 200,000 connections, against 1,574,979 recorded in 2024/25
Published field
snippet · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The article reports MTC 'recording 1,574,979 connections to the city's free Wi-Fi network in 2024/25 but setting a target of just 200,000 connections for 2026/27', and that 'the business plan does not explain the sharp difference between the two figures'.
Caveat
What counts as a 'connection' is not defined in the reporting.

Sources carrying this claim

  1. Sunday Times / Our City News — Joburg's Wi-Fi plan falters amid litany of woes (20 Sep 2026)
Claim 12 clm-7858fe72e576e2eb quantitative
the operator reported that the fibre reached about 30 clinics and 15 libraries by 2016
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
MTC's 2015/16 report says the network 'was extended to connect about thirty (30) clinics' for the e-health platform and that connectivity to fifteen (15) libraries benefited the e-learning programme.
Caveat
Operator self-report; a count of sites connected, not a measured service effect.

Sources carrying this claim

  1. Metropolitan Trading Company — Integrated Report 2015/16
Claim 13 clm-b493900eca1a174d quantitative
the free Wi-Fi logged 1,574,979 connections in 2024/25
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The Sunday Times reports the figure from MTC's 2026/27 business plan.
Caveat
A usage count reported by the operator, not an outcome; the unit is not defined.

Sources carrying this claim

  1. Sunday Times / Our City News — Joburg's Wi-Fi plan falters amid litany of woes (20 Sep 2026)
Claim 14 clm-c4def1063711581e quantitative
in March 2017 the mayor said that despite the cost 'few of these benefits have been realised'
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The statement lists the project's aims — service delivery, ICT cost savings, affordable internet for communities and businesses — and continues: 'Despite the astronomical cost, few of these benefits have been realised'.
Caveat
A political assessment by an incoming administration of its predecessor's decision, not an evaluation.

Sources carrying this claim

  1. City of Johannesburg — Investigation into City's R1.3 billion acquisition of Broadband Network (10 Mar 2017)
Claim 15 clm-c9f64513ca6619b8 quantitative
MTC's 2026/27 business plan says ageing equipment, power outages and vandalism have kept it from meeting its network-availability targets
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The article says 'ageing and dilapidated equipment, power outages and vandalism are among the reasons it has struggled to meet its network availability targets', and that insufficient capital budget has affected maintenance and expansion.
Caveat
The targets and the availability actually achieved are not given in the reporting.

Sources carrying this claim

  1. Sunday Times / Our City News — Joburg's Wi-Fi plan falters amid litany of woes (20 Sep 2026)
Claim 16 clm-b2ccef94c02689d1 quantitative
The city projected in 2015 that ending the contract would save it 20% a year
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The city's head of broadband told ITWeb that termination released the city from R279 million a year over 12 years, 'allowing it to realise a 20% annual saving'.
Caveat
A projection by the city at the time of the buy-back, not a measured saving; no later source reports whether it materialised.

Sources carrying this claim

  1. ITWeb — BWired appointed to run R3.4bn Joburg network (18 Feb 2015)
Claim 17 clm-1fe1ef3685e1e5b1 quantitative
Johannesburg's original deal would have cost it an annual fee and handed it the fibre after 15 years
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The city's statement: 'Under the initial agreement, the City would have paid an annual fee for the building and operation of the network. After 15 years we would have taken over ownership of the network.'
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. City of Johannesburg — Investigation into City's R1.3 billion acquisition of Broadband Network (10 Mar 2017)
Claim 18 clm-e0e5b0b04487540f quantitative
the city bought the asset for R1.3 billion and took on the operation it had contracted out
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The statement says the city terminated the agreement 'so as to operate the network itself through the MTC' and bought out the agreement for R1.3 billion; MTC's report records the transfer of the network and its business to the municipal entity in September 2015.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. City of Johannesburg — Investigation into City's R1.3 billion acquisition of Broadband Network (10 Mar 2017)
  2. Metropolitan Trading Company — Integrated Report 2015/16
Claim 19 clm-b18aaa7507b77870 descriptive
an entity the mayor later said had neither a viable business plan nor the capacity to run it
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The statement describes MTC as an entity 'which possessed no viable business plan nor had requisite capacity to run a broadband operation of this size'.
Caveat
No claim-specific caveat recorded

Sources carrying this claim

  1. City of Johannesburg — Investigation into City's R1.3 billion acquisition of Broadband Network (10 Mar 2017)
Claim 20 clm-8ee10a3820d1b951 quantitative
That entity lost R54 million in its first financial year
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The statement: 'On commencing operations on 30 September 2015, the MTC ended the 2015/16 financial year with a net loss of R54 million.'
Caveat
The mayor's figure; MTC's audited statements for 2015/16 could not be read, and the integrated report's Auditor-General section is blank in the published file.

Sources carrying this claim

  1. City of Johannesburg — Investigation into City's R1.3 billion acquisition of Broadband Network (10 Mar 2017)
Claim 21 clm-315091ad675fc4c5 quantitative
the city tried to sell the network again from 2019
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
Engineering News reports the 2019 open tender to sell the network for an expected R853-million to just over R1-billion under a 12-year build-operate-transfer arrangement; TechFinancials reports MTC's February 2021 update that a compliant bidder had 'entered into an agreement of sale'.
Caveat
No source after February 2021 records a completed transfer or names the buyer; the 2026/27 business plan still has MTC maintaining the fibre, which suggests the sale did not close, but that is not stated anywhere.

Sources carrying this claim

  1. Engineering News — Joburg to sell its 1 000 km fibre network (30 Aug 2019)
  2. TechFinancials — City of Jo'burg identifies a potential buyer for its broadband network (23 Feb 2021)
Claim 22 clm-1d91cb272955e6a0 quantitative
in 2026 MTC maintains 1,200 km with 26 network staff while more than 60% of its city subsidy goes to servicing its shareholder loan
Published field
lesson · verbatim
Mapping
mapped · no interpretation or interpolation added by this file
What the mapping says
The Sunday Times: MTC relies on 26 network employees to maintain 1,200km of fibre and 'says more than 60% of the subsidy it receives from the city is used to service its shareholder loan balance, after recording R169m in subsidy revenue'. MTC's own history says the 2015 transfer was 'financed by means of a shareholder loan account'.
Caveat
Whether the 2026 loan balance is the same instrument that financed the 2015 transfer is MTC's description across two documents five years apart; the business plan was not read.

Sources carrying this claim

  1. Sunday Times / Our City News — Joburg's Wi-Fi plan falters amid litany of woes (20 Sep 2026)
  2. TechFinancials — City of Jo'burg identifies a potential buyer for its broadband network (23 Feb 2021)

Source dossiers and revision state

This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.

unreviewed Revision 2026-10-11-baseline effective 2026-10-11 · created 2026-10-11

Awaiting operator and domain-expert review; publication of this revision implies neither.

sha256:3136cde0539bc1b95a7b0fb026dcc7942ebeebd2470b3b2ac89416a67e6332dc
22
of 22 claims mapped
10
source dossiers
9
publication dates recorded
0
archives linked
0
exact locators
0
content captures hashed

Governance facts carried by the record

Operator
Metropolitan Tech Company (MTC, formerly Metropolitan Trading Company), a municipal-owned entity 100% owned by the City of Johannesburg; built 2010–2013 by CitiConnect Communications under the BOT contract ceded by Ericsson SA, with BWired as the operating venture until the 2014 termination
Actor types
city-government, private
Funding model
public
Funding description
Originally a 15-year build-operate-transfer contract with Ericsson SA (annual fee, ownership after 15 years); since September 2015 city-owned — transferred to MTC for about R1.25 billion financed by a shareholder loan, with an annual city subsidy (R169m subsidy revenue in the 2026/27 business plan)
Cost
R1.3 bn buy-out of the BOT contract (2015, city figure); the city's forensic investigation put deal-related costs at R1.7 bn (Dec 2017)
Ownership
Not recorded
Decision rights
Not recorded
Exit conditions
Not recorded

10 source dossiers

City of Johannesburg — Investigation into City's R1.3 billion acquisition of Broadband Network (10 Mar 2017) joburg.org.za · 9 linked claims

Open original source ↗

Stable source ID
src-1d0fd9233458c5c6
Publisher
Name not classified · joburg.org.za
Type / language
web-page · language not classified
Published
2017-03-10
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-10-11
Dossier created
2026-10-11
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Executive mayor Herman Mashaba's statement announcing the forensic investigation. States the sequence the entry relies on: tender awarded 19 December 2008; agreement terminated on 31 July 2014 'so as to operate the network itself through the MTC'; buy-out 'at a cost of R1.3 billion, without any viable business plans'; under the original agreement an annual fee and ownership after 15 years; MTC 'commencing operations on 30 September 2015' and ending 2015/16 with a net loss of R54 million; 'few of these benefits have been realised'; and that the Auditor-General 'raised a number of serious concerns' about MTC's financial performance.

Descriptive only — not page/paragraph exact
Metropolitan Trading Company — Integrated Report 2015/16 joburg.org.za · 5 linked claims

Open original source ↗

Stable source ID
src-6849926c9695e7dc
Publisher
Name not classified · joburg.org.za
Type / language
pdf · language not classified
Published
Not recorded
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-10-11
Dossier created
2026-10-11
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

The operator's own integrated report for its first year (41 pages; the Audit and Risk Committee report inside is dated 30 November 2016, the cover carries only the financial year). States that CCC/BWired 'had committed numerous acts of repudiation' under the BOT and that the city 'cancelled the BOT on 31 July 2014'; settlement concluded 28 May 2015 and implemented 3 September 2015, the effective transfer date; MTC is 100% owned by the municipality; the transferred asset cost 'R1,3 billion'; the MMC's foreword says the city 'has rolled out 1150km' of fibre; the network reached about 30 clinics and 15 libraries; 340 Wi-Fi hotspots were planned for 2016/17; 15 employees migrated from BWired. The Auditor-General's report section (page 40) is blank in the file.

Descriptive only — not page/paragraph exact
ITWeb — BWired appointed to run R3.4bn Joburg network (18 Feb 2015) itweb.co.za · 4 linked claims

Open original source ↗

Stable source ID
src-f9a8d88cf3b14e9d
Publisher
Name not classified · itweb.co.za
Type / language
web-page · language not classified
Published
2015-02-18
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-10-11
Dossier created
2026-10-11
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Reports the council decision to create a municipal entity and pay R1.2 billion to buy back the network assets; Ericsson SA won the deal in 2010 for 15 years and ceded it to CitiConnect Communications, which manages BWired; the dispute concerned intermediary companies selling spare capacity and fibre for a second network laid in the city's trenches; '900km of fibre-optic cables that have been rolled out'; the city's head of broadband says termination released the city from R279 million a year over 12 years, 'a 20% annual saving'. The R3.4bn in the headline is not itemised in the text.

Descriptive only — not page/paragraph exact
TimesLIVE — R1.2bn bill looms for fibre optic farce (5 Jan 2015) timeslive.co.za · 1 linked claim

Open original source ↗

Stable source ID
src-7fe733f627a794af
Publisher
Name not classified · timeslive.co.za
Type / language
web-page · language not classified
Published
2015-01-05
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-10-11
Dossier created
2026-10-11
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Reports, before the council vote, that the network 'remains unused 18 months after it was expected to deliver fast internet', that Ericsson SA was appointed 'four years ago' to build a 900km network for R1.1-billion, that launch was expected in July 2013, and that settling would absolve the city from paying R3.348-billion over the 12-year operating period, according to council documents.

Descriptive only — not page/paragraph exact
TimesLIVE — Minister implicated in dodgy R1.7bn Joburg broadband tender (13 Dec 2017) timeslive.co.za · 1 linked claim

Open original source ↗

Stable source ID
src-337058796c938b4b
Publisher
Name not classified · timeslive.co.za
Type / language
web-page · language not classified
Published
2017-12-13
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-10-11
Dossier created
2026-10-11
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Quotes the mayor's progress update on the forensic investigation: 'costs relating to the deal currently amount to R1.7-billion' and 'likely to rise'; the investigators' report implicates a minister and a deputy minister as benefiting 'to the tune of almost R200-million'; an official was suspended and a court order obtained to image devices. The report itself is not public; the figures are the mayor's account of it.

Descriptive only — not page/paragraph exact
ITWeb — Future of Joburg's broadband network remains unclear (21 Jan 2019) itweb.co.za · 1 linked claim

Open original source ↗

Stable source ID
src-c7042f9b81be900d
Publisher
Name not classified · itweb.co.za
Type / language
web-page · language not classified
Published
2019-01-21
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-10-11
Dossier created
2026-10-11
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Retrospective after the Sunday Times reported the final Nexus Forensic Services findings. States the network 'was initially envisaged to become operational on 1 July 2013', that after more than a decade there is 'still no clarity' when it will go live, the 2010 award to Ericsson SA and cession to CCC, the 2014 cancellation and the R1.3 billion buy-out, and names the three ANC members the Sunday Times said were directors of CCC. Gives the ministers' benefit as R279 million, which conflicts with the R200 million in the mayor's own December 2017 statement.

Descriptive only — not page/paragraph exact
Engineering News — Joburg to sell its 1 000 km fibre network (30 Aug 2019) engineeringnews.co.za · 1 linked claim

Open original source ↗

Stable source ID
src-5643bfb71f4d933f
Publisher
Name not classified · engineeringnews.co.za
Type / language
web-page · language not classified
Published
2019-08-30
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-10-11
Dossier created
2026-10-11
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Reports the open tender to sell the '1 000 km fibre network', expected to raise R853-million to just over R1-billion; MTC proposed the build-operate-transfer sale model in May 2018, would procure network services from the buyer and keep a first right of refusal; public meetings in the seven regions. The sale is cited as a plan — the article does not record a buyer or a completed transfer.

Descriptive only — not page/paragraph exact
TechFinancials — City of Jo'burg identifies a potential buyer for its broadband network (23 Feb 2021) techfinancials.co.za · 5 linked claims

Open original source ↗

Stable source ID
src-dbbea76629bce8e8
Publisher
Name not classified · techfinancials.co.za
Type / language
web-page · language not classified
Published
2021-02-23
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-10-11
Dossier created
2026-10-11
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Reports MTC's February 2021 update that a 'compliant service provider has now been identified' under tender A34-2018/2019 and 'entered into an agreement of sale', with virtual public meetings on the service level agreement from 24 to 26 February 2021; the buyer is not named. Reproduces MTC's own history of the network: Ericsson SA commissioned in June 2010 for 15 years (three years to build, twelve to operate), cession to CCC with BWired to operate, 'approximately 900 kilometres' built by mid-2013, and the September 2015 transfer to MTC as a going concern 'for approximately R1.25 billion, financed by means of a shareholder loan account'.

Descriptive only — not page/paragraph exact
City of Johannesburg — Metropolitan Tech Company is strengthening Johannesburg's digital backbone (6 Aug 2026) joburg.org.za · 1 linked claim

Open original source ↗

Stable source ID
src-adc15ec0fc1d10cc
Publisher
Name not classified · joburg.org.za
Type / language
web-page · language not classified
Published
2026-08-06
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-10-11
Dossier created
2026-10-11
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

City newsroom article (dated 06/08/2026 on the page) on MTC's Core Network Rehabilitation Programme: 'the fibre network underpins municipal buildings, public Wi-Fi, digital communication systems and other smart city services'; rehabilitation work under way in Randburg, Hunters Hill, Sandton, Alexandra, Martindale, Roodepoort, Eldorado Park and Lenasia. The entry's present-tense statements about what runs on the fibre rest on this page.

Descriptive only — not page/paragraph exact
Sunday Times / Our City News — Joburg's Wi-Fi plan falters amid litany of woes (20 Sep 2026) timeslive.co.za · 6 linked claims

Open original source ↗

Stable source ID
src-22756966e5a22d3b
Publisher
Name not classified · timeslive.co.za
Type / language
web-page · language not classified
Published
2026-09-20
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-10-11
Dossier created
2026-10-11
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Jan Bornman for Our City News, published by the Sunday Times (page dated September 20, 2026; the URL slug says 19 September). Reports MTC's 2026/27 business plan: 'relying on just 26 network employees to maintain 1,200km of fibre'; the entity is 'currently under-capacitated'; more than 60% of its city subsidy services its shareholder loan after R169m in subsidy revenue; about R570m operating and R20.7m capital expenditure; ageing equipment, power outages and vandalism behind missed network-availability targets; 1,574,979 free Wi-Fi connections in 2024/25 against a 200,000 target for 2026/27, which the plan does not explain; the Slovo Park 'smart Wi-Fi' pilot launched in March 2026 and residents' reports of very poor signal. MTC did not respond to the newspaper's questions.

Descriptive only — not page/paragraph exact
Known limits of this file
  • Publisher names and source languages have not yet been classified; domains are recorded without guessing.
  • Existing source notes are descriptive locators, not page- or paragraph-exact citations.
  • A missing archive, publication date or content hash is shown as null rather than inferred.
  • The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim.