clm-54e543e746b202d9
quantitative
Evening-peak congestion on served corridors fell 33.6% six months and 34.9% one year after opening, measured against control corridors by difference-in-differences on Google Maps travel times
Permanent project revision
Revision 2026-08-20-source-dates-2 · effective 2026-07-26
Current revision. This is the snapshot used by the live entity page.
Record publication (and where stated, revision) dates for this entry's sources.
sha256:87e7551dc8e2ff92db0d4050e7e2a29e5f9597007f3ff42e6321df3b06d77a6c
replace /snapshot/projectFingerprint — Updated projectFingerprint to the current sourced project record.replace /snapshot/sources — Updated sources to the current sourced project record.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-54e543e746b202d9
quantitative
Evening-peak congestion on served corridors fell 33.6% six months and 34.9% one year after opening, measured against control corridors by difference-in-differences on Google Maps travel times
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:87e7551dc8e2ff92db0d4050e7e2a29e5f9597007f3ff42e6321df3b06d77a6c
src-18c8a895ae898c50Operator on the record: grade of automation 2, meaning trains run automatically but a driver stays in the cab and is responsible for the run. Load-bearing source for the automation grade, deliberately press rather than the signalling supplier.
src-0588aed1c3e9fc09Supplier claim, used only for the signalling scope: CBTC with automatic train protection, automatic train supervision and computer-based interlocking on the 15.7 km line. Its 173,000 passengers/day figure is design capacity, not a ridership forecast, and is widely miscited as one.
src-46126810760c78fbOperator page confirming platform screen doors at every station: full height underground, half height on the elevated section.
src-cb1ccdf0158a7e52The ticketing layer: JakLingko card with cross-mode fare integration, bank e-money, MyMRTJ app QR linked to e-wallets, and NFC QRIS Tap.
src-5e71bdfa65687b57Operator announcement of the NFC QRIS Tap contactless payment option and its bank and wallet partners.
src-51a0f9ddac84cfdbThe loan split: JICA lends to the national government, which on-grants 49 percent and on-lends 51 percent to Jakarta province; Rp14.51tn total, about Rp7.1tn from the national budget and Rp7.4tn from the provincial one.
src-d2993ce2e5efb8f7Project cost about US$1.15bn; the original patronage target of 65,000/day against 89,645/day actual in 2019; land acquisition delays in the southern section and the constraint of tied Japanese procurement.
src-8d4093380cbdbcdfThe COVID collapse: 24.41m riders and 86,270/day in 2019, 9.92m and 27,122/day in 2020, 7.18m and 19,659/day in 2021.
src-8be6a38419fa64a2Recovery past pre-pandemic levels: 130,533 passengers/day in September 2025, above the operator's 119,000 target.
src-6778b6724cf1c33dSource of the impact figures, verified sentence-level: evening-peak congestion on treated corridors down 33.6% at six months and 34.9% at one year, difference-in-differences against control corridors using Google Maps travel times.
src-ff11c8accb8d0268The peer-reviewed original: the authors themselves describe the congestion reduction as considerably modest and largely localised to the central business district corridor.
src-2ad240d1f607340aThe behavioural counterweight: a two-wave panel survey of 74 residents near stations against 84 farther away found statistically insignificant effects on vehicle use and no substantial difference in self-assessed travel habits.
src-d52087f3b4b205b7Current Phase 2A schedule: Bundaran HI to Monas targeted for late 2027 and the extension to Kota for 2029, against an original March 2025 target.
src-03261d5ad7017c7bConstruction harm, February 2026: a father and infant injured by a deep trench in the carriageway inside the Phase 2A works zone; the city roads agency said the section falls in the project area and is the contractor's responsibility.
src-211aa49ef7c50597Official budget line: Rp592.9bn allocated for the MRT Jakarta fare subsidy in the 2024 provincial budget.