After the 1978 drought, which forced water-supply restrictions for 287 days
Permanent project revision
Revision 2026-11-16-baseline · effective 2026-11-16
Current revision. This is the snapshot used by the live entity page.
Created the first structured Evidence Passport with 16 claims and 6 source dossiers.
sha256:014ce940944568ec18d724a566dc4b3e681eacc9bf36869e87c677ee15100d4c
add /evidencePassport — Added claim-level evidence mapping and source dossiers.add /revisionHistory — Established a permanent, hash-addressed baseline revision.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-83968ad12cdf1dae
quantitative
After the 1978 drought, which forced water-supply restrictions for 287 days
clm-2896b48f0917c860
quantitative
began running a distribution control system in 1981 that manages flow and pressure in the city's mains around the clock from a Water Management Center
clm-e0f9ce5ea15bd2c2
quantitative
Readings from about 300 telemeters reach the centre
clm-ae3182b05c630c44
descriptive
operators remotely work motorised valves to shift water between purification plants, throttle pressure when demand falls, and cut off leaking mains
clm-2e6cb3856b4e0b98
quantitative
The World Bank describes a network divided into 21 blocks, run by three operators who actuate about 2,000 valves a day.
clm-530b7cc297810937
quantitative
In 2024 the bureau added a second layer: satellite radar screening flagged likely leak areas, and AI-equipped acoustic sensors, 50 of them by October, now listen on pipes there and alert the bureau automatically.
clm-a3ca9569e0d1f752
quantitative
The World Bank, working from the city's own figures, reports that the leakage rate fell from 14 percent in 1979 to 2 percent
clm-99b21e4b340181b7
quantitative
its own economic evaluation puts the internal rate of return of the control centre and the leakage programme combined at 15 percent
clm-60e0afb52d1d4745
quantitative
Nikkan Kogyo Shimbun reported a leakage rate of 1.8 percent for fiscal 2022.
clm-2af4515ae1e95f41
quantitative
The bureau's own calculation credits pressure control alone with avoiding about 4,000 to 5,000 cubic metres of leakage a day, about 1 percent of daily distribution.
clm-eabca70ad5a61dd3
quantitative
In the 1994 drought, water was restricted for 295 days, longer than in 1978, but the valve work took 14,157 person-days instead of 32,434, and no water trucks were sent out, against 13,433 in 1978.
clm-1d3f8b8b7ea003ca
descriptive
the same decades brought pipe renewal, ductile-iron mains in polyethylene sleeves and leak inspections
clm-459f773dcbd983a0
quantitative
the bureau credits pressure control itself with about 1 percent of daily distribution
clm-d22068f002e8ed39
descriptive
Its clearest separate effect is on rationing, which it made far cheaper to run rather than shorter.
clm-4995d9607879d23c
quantitative
In the 2026 drought, as the Chikugo River dams that supply about a third of the city's water fell, the bureau twice announced stronger pressure reduction through the system.
clm-f465bc081c0460a0
descriptive
Seawater desalination for the metropolitan area is a separate plant run by a regional water agency, not by the city.
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:014ce940944568ec18d724a566dc4b3e681eacc9bf36869e87c677ee15100d4c
src-6125e5900728b379Waterworks Bureau page on the Water Management Center: 1981 start after the 1978 drought, five functions, pressure-control leakage estimate, 1978 vs 1994 drought figures, and links to the 2026 reduced-pressure notices.
src-9ae212358d411507Bureau explainer stating that the centre adjusts flow using information from about 300 telemeters across the city and motorised valves.
src-3d14976aa3a4617fWorld Bank / Tokyo Development Learning Center case study: 21 blocks, three operators, about 2,000 valve operations a day, leakage 14 percent (1979) to 2 percent, cost table and the authors' own economic evaluation (IRR 15 percent). Data drawn from Fukuoka City.
src-f3a6accd64f5c8a6Web edition of a Nikkan Kogyo Shimbun article printed 24 Dec 2024: 1.8 percent leakage in fiscal 2022, 287-day restriction in 1978, 24-hour pressure adjustment, satellite screening (May 2024) and 50 AI acoustic sensors (October 2024).
src-eb7792a343ea901bPress release setting up the city's drought-response council: Chikugo dams falling, about a third of city water from the Chikugo River, distribution control among the council's tasks.
src-724e3c6344265e9bPress release of the regional water agency calling its Umi no Nakamichi Nata desalination centre Japan's largest and stating it supplies the Fukuoka metropolitan area.