collapsed in the early hours of 11 September 2024
Permanent project revision
Revision 2026-11-06-baseline · effective 2026-11-06
Current revision. This is the snapshot used by the live entity page.
Created the first structured Evidence Passport with 20 claims and 7 source dossiers.
sha256:d315bbc37a5a9576717923844058b17f787c1333273e72413f0b1e45ad6a31a0
add /evidencePassport — Added claim-level evidence mapping and source dossiers.add /revisionHistory — Established a permanent, hash-addressed baseline revision.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-351a2543e179cebb
quantitative
collapsed in the early hours of 11 September 2024
clm-7c44e1c91bf1a52e
descriptive
the bridge was inspected to the standards in force
clm-2f168fa09279c981
descriptive
existing cracks were monitored by crack-movement measurement
clm-bda0f6578eb700a7
descriptive
hydrogen-induced stress corrosion cracking had begun during construction
clm-15b4cbfda6d0a9ad
descriptive
the design meant failure would not announce itself through wide cracks
clm-592e4ffe821fe1cb
descriptive
sensors that pick up the sound of a prestressing wire snapping
clm-a1b4e26d517ac610
descriptive
The expert summary made it the condition for reopening the Elbe to ships under the remaining sections
clm-06f65480e05fce88
descriptive
built with prestressing steel prone to stress corrosion cracking
clm-ea2c4c7c234cad99
quantitative
122 acoustic emission sensors and about 850 metres of fibre-optic sensing listen for wire breaks and cracks
clm-02de066f8ff90d2d
quantitative
the monitoring recorded several wire breaks from 16 February 2025
clm-f0946ec195500582
descriptive
citing acute risk of collapse, the city waived a tender and awarded the demolition directly
clm-66b71969bda4932c
quantitative
ship-by-ship passages were permitted again from 24 February 2025 because no further breaks were recorded
clm-36851c930f77bde5
descriptive
the monitoring flagged suspect areas; opened up, two places showed embrittled prestressing steel
clm-a0f064239c8ab225
quantitative
On 8 May 2026 the city cut traffic to one lane each way and a 7.5-tonne limit
clm-7c814894475d0d8b
descriptive
Six more wires snapped at axis C after the closure
clm-56bea6c7baaf9ba5
descriptive
emergency steel props went in
clm-f22dc786c2235b66
quantitative
After a load test the bridge reopened on 24 August 2026 to buses and vehicles up to 7.5 tonnes, one lane each way and still without heavy traffic
clm-960d80491327c58c
quantitative
a reserve of at most 16 wire breaks within three metres
clm-8f73bd040c97a9b9
descriptive
the city expects the damage to the wires to continue
clm-5b4443b146b87fbd
descriptive
the monitoring buys time to plan a replacement
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:d315bbc37a5a9576717923844058b17f787c1333273e72413f0b1e45ad6a31a0
src-b44ec8652d3ffed5Two-page summary of the interim findings of the expert team led by Prof. Steffen Marx, on the MKP GmbH letterhead, published by the city: hydrogen-induced stress corrosion cracking initiated during construction as the main cause; the pre-collapse inspection regime, including crack-movement measurement of existing cracks; and acoustic emission monitoring with at least four weeks of prior measurement as the condition for reopening the waterway.
src-ececeec460084654City press release: since 16 February 2025 the acoustic emission monitoring on the bridge recorded several wire breaks; citing acute risk of collapse, the city waived a tender and awarded the demolition directly; because no further breaks were recorded, ship-by-ship passages could be permitted again from 24 February 2025.
src-4057cc586c245167City press release: the permanent monitoring of the Budapester Straße bridge had flagged suspect areas; opened up, two places showed embrittled prestressing steel; 122 acoustic emission sensors and about 850 metres of fibre-optic sensing cover the structure, which was built with prestressing steel prone to stress corrosion cracking; the city aims to keep the bridge in service for ten more years.
src-ff101a91e0402d12City press release: since the closure six more wires had snapped at axis C; the experts' critical limit is a reserve of at most 16 wire breaks within a three-metre zone; four heavy-duty steel props were being built as emergency support.
src-e130e8d8fa7f9587Trade-press report ahead of the load test: the 1967 bridge contains prestressing steel from the former Hennigsdorf steelworks, similar to the Carolabrücke's; monitored since autumn 2024; on 8 May the city cut traffic to one lane each way and a 7.5-tonne limit; the load test with up to 326 t costs about €900,000.
src-a8f80b877c56ea1fCity press release: after the load test the bridge reopens on 24 August 2026 to buses and vehicles up to 7.5 tonnes, one lane each way, still without heavy traffic; the city expects the damage to the wires to continue and an overall assessment in November 2026.
src-366e5dd689e0c07cCity notice on lane closures for fitting the monitoring system to the Budapester Straße bridge, continuing installation work from November 2024. It names Marx Krontal Partner (Dresden/Weimar) as the firm commissioned to install and operate the monitoring system.