chills the towers of West Bay and the island development The Pearl-Qatar — both inside the Municipality of Doha
Permanent project revision
Revision 2026-10-04-baseline · effective 2026-10-04
Current revision. This is the snapshot used by the live entity page.
Created the first structured Evidence Passport with 13 claims and 9 source dossiers.
sha256:550502f3f7c05ed0001c9b6721a6538ef567f4399b33e4aca358428e50c35722
add /evidencePassport — Added claim-level evidence mapping and source dossiers.add /revisionHistory — Established a permanent, hash-addressed baseline revision.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-7caaf2a610cfdb91
descriptive
chills the towers of West Bay and the island development The Pearl-Qatar — both inside the Municipality of Doha
clm-7672cd4ebefa51f3
quantitative
Since September 2024 a command control centre at its West Bay plant uses SCADA and programmable logic controllers to monitor and control all its plants in both districts from one place
clm-4d72128812b600dc
descriptive
real-time insight into plant efficiency, building operations and customer consumption
clm-1d7b27d943cd55d8
quantitative
smart metering at The Pearl goes back to a project begun in 2009
clm-f102bf13936c236f
quantitative
in January 2023 Qatar Cool upgraded its Itron meter-data management system and contracted 25,000 more Itron meters
clm-618485fa17a771fe
quantitative
West Bay plants one and two were retrofitted in 2015 to run on 100% treated sewage effluent (TSE)
clm-7e952ee41a08b374
descriptive
the third West Bay plant has an in-house reverse-osmosis unit fed with TSE, and the two Pearl plants make their water from the sea by reverse osmosis
clm-029833582baa032c
quantitative
moving West Bay's two operating plants from potable water to TSE — blended in gradually over 1.5 years — had cut potable water use by 1.7 million cubic metres in 18 months
clm-0f527408c1f0adfa
quantitative
Kahramaa saying district cooling can cut electricity consumption by 30 to 40% compared with conventional air-conditioning and counting around 70 district cooling plants in Qatar
clm-13f372f569db1972
descriptive
the regulator added decisions designating district cooling service areas and governing network access to public land
clm-5c201b0d96ce1363
quantitative
Qatar Cool says its West Bay plants switched to TSE in 2015 as part of a water scarcity resolution issued by Kahramaa
clm-df466f06e222754b
quantitative
Law No. 19 of 2024 now prohibits desalinated water for district cooling and makes a Kahramaa licence mandatory to operate a system
clm-7b710cdeb1e0f640
descriptive
The energy case, by contrast, still rests on sector-wide percentages rather than a plant-level comparison anyone outside the operator can check
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:550502f3f7c05ed0001c9b6721a6538ef567f4399b33e4aca358428e50c35722
src-c7c3e48b9dd96491Qatar Cool's announcement of a Command Control Center at its West Bay plant: PLC and SCADA systems giving real-time insight into plant efficiency, building operations and customer consumption, and control of all district cooling plants in the Pearl Island and West Bay districts from one location, with a duplicate environment for remote operation. Kahramaa officials attended the launch.
src-4fb1501e475c2428The operator's standing sustainability page: West Bay plants one and two retrofitted in 2015 for 100% direct TSE; West Bay plant three with an in-house RO plant using TSE; the two Pearl plants using seawater reverse osmosis; a thermal energy storage tank; and the statement that the West Bay switch to TSE in 2015 was part of a water scarcity resolution issued by Kahramaa.
src-bd50ad986280d236Report of Qatar Cool's migration of its two operational West Bay plants from potable water to 100% TSE, phased in over 1.5 years under close monitoring of make-up and blow-down water quality, saving 1.7 million cubic metres of potable water in 18 months.
src-46d98f2a6a9ea9b8Supplier press release: Qatar Cool upgraded its Itron EMMSYS meter data management system and contracted 25,000 Itron thermal energy meters, deployed with channel partner QIFEM; the partners' work dates back to a 2009 smart-metering project at The Pearl-Qatar. Quotes Qatar Cool's CEO.
src-6d5ed52db558644fReport of Kahramaa's statements on district cooling: electricity savings of 30 to 40% compared with conventional air-conditioning, around 70 operational plants in Qatar with about 1.15 million refrigeration tonnes, and 18.5 million cubic metres of water saved in 2024.
src-2e3943a0324b7fe5Kahramaa-announced 2026 ministerial decisions Nos. 03 to 06: designation of district cooling service areas, licensed providers' access to public land, relocation of network parts, and compensation of property owners.
src-f84ea2cb17659468Summary of Qatar's district cooling regulations under Law No. 19 of 2024: mandatory Kahramaa licence for 15 years, Kahramaa sets service areas and technical standards, and use of desalinated water for district cooling is prohibited.
src-355a6dd51cb83b00Qatar Cool statement that it operates in two districts, West Bay and The Pearl-Qatar, with the two West Bay plants sold out and a third in design.
src-f55d7c169100d56eInfobox places The Pearl-Qatar in the Municipality of Doha, Zone 66.