the works were designed to prevent flooding in the city's Maldonado basin in a 10-year storm, with about 342,968 direct beneficiaries in the basin's critical zone
Permanent project revision
Revision 2026-08-20-source-dates · effective 2026-07-26
Current revision. This is the snapshot used by the live entity page.
Created the first structured Evidence Passport with 1 claim and 10 source dossiers.
sha256:5730834229c4001dbfa806675e9f5a73399f7ed35f01979a4bb6fd20212c765b
add /evidencePassport — Added claim-level evidence mapping and source dossiers.add /revisionHistory — Established a permanent, hash-addressed baseline revision.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-7db4e414c477082a
quantitative
the works were designed to prevent flooding in the city's Maldonado basin in a 10-year storm, with about 342,968 direct beneficiaries in the basin's critical zone
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:5730834229c4001dbfa806675e9f5a73399f7ed35f01979a4bb6fd20212c765b
src-612738650401aac4Independent review. Gives the Moderately Unsatisfactory outcome rating, appraisal cost US$189M against actual US$193.01M, an IBRD loan of US$134.01M (originally EUR 98M), board approval 5 April 2005 and closing 31 August 2012 after extension from 31 December 2010; states the secondary drainage works were 'underway in 2 of the 6 proposed areas, with the remainder expected to be completed with City funds', and draws the lesson that combining structural and non-structural components in one project is challenging. The PDF at the same document ID returned unparseable binary to our fetcher; this identical .txt rendition was read instead.
src-3d60bcaca9a45ccaSource for the tunnel dimensions (9.8 km and 4.6 km, 6 m inner diameter, both in operation from mid-2012), the design standard ('designed to avoid flooding in the area of the City within the Maldonado Basin during rain events of 10 year intervals'), the figure of roughly 342,968 direct beneficiaries, and the statement that 'shortage of funding meant that the Project could not achieve the development of a complete hydrological monitoring network for the City'. PDF unparseable; .txt rendition read.
src-89defab6e6a67f4cOperator page. Dates the system to October 2016, describes a network of 34 automatic meteorological stations 'of which 10 are already transmitting data', a dual-polarisation Doppler radar then still being installed at Merlo, and data converging at the Centro Único de Coordinación y Control, 'currently operated by the Ministry of Justice and Security'. The page reads as an undated snapshot close to launch — we did not find a current count of stations actually transmitting, so the entry claims none. Nothing on the page describes automatic actuation of pumps or gates.
src-63a6bc265f8902a2Confirms the sensing layer: 'Los sensores monitorean en forma constante la lluvia, la temperatura, el viento, el caudal y el nivel del agua', feeding 'un tablero de control donde se visualizan en mapas y gráficos con la finalidad de detectar variaciones en los caudales y anticipar posibles inconvenientes'. No sensor count, no public data feed and no automatic response described — the basis for this entry's placement as warning-only.
src-f22896dd44b4e26aDescribes maintenance rather than control: constant inspection because 'en esos conductos pluviales una obstrucción puede generar un problema muy grande', robots in the smaller pipes, cleaning of some 900 km of conduits and 30,000 sumideros by Espacio Público e Higiene Urbana, and a 6 m conduit that routes inflow from the Province to the Riachuelo via the Cildañez. Also cites rainfall up about 11% over two decades. No sensor-driven control is mentioned anywhere in the piece.
src-5b02ef8a3518cd64Counterweight: flooded streets and businesses and three subway lines out of service, a decade after the tunnels opened. Surfaced via search with headline and date; the article page itself was not fetched.
src-d12d2fd7ea930f0cSecond dated counterweight: close to 118 mm across the AMBA, with 155 mm in Villa Devoto and 114 mm in Villa Santa Rita, flooded neighbourhoods and cut streets. Surfaced via search; page not fetched.
src-a492e52722648571The follow-on loan (P145686), which moved to the Vega basin — the basin where the city's 2013 deaths occurred and which the Maldonado tunnels do not serve. Cited only for the existence and date of the successor project, not for any Maldonado figure.
src-c774c32420f14191Contemporaneous reporting put the toll inside the Autonomous City at six to eight, in Saavedra, Colegiales, Villa Luro, Villa Ortúzar and Villa Urquiza — neighbourhoods largely in the Vega basin, not the Maldonado. Surfaced via search; page not fetched, and the exact final city figure varies between outlets, so the entry gives no number.
src-701ecded1a2c21ffCited only to keep the tolls apart: the 89 judicially confirmed deaths of 2-3 April 2013 belong to La Plata, a different city roughly 60 km away, and are routinely merged with Buenos Aires figures in coverage. They are not attributed to this entry.