the 22@ plan rezoned roughly 200 hectares of industrial Poblenou into an innovation district
Permanent project revision
Revision 2026-08-27-p1-quality-uplift · effective 2026-07-25
Current revision. This is the snapshot used by the live entity page.
Full claim mapping over snippet, impact and lesson; sourced impact and lesson added; source dates and attributions corrected from the same reading.
sha256:b85c85033d2e3ae0a33f14b2518cf9df693cc6c4ed18bb61663e435abcf7ff05
replace /snapshot/projectFingerprint — Updated projectFingerprint to the current sourced project record.replace /snapshot/claims — Updated claims to the current sourced project record.replace /snapshot/sources — Updated sources to the current sourced project record.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-8b32f5edc2466d55
quantitative
the 22@ plan rezoned roughly 200 hectares of industrial Poblenou into an innovation district
clm-5d3d2d1280ce55c4
quantitative
a special infrastructure plan covered about 37 km of streets and laid fibre-optic telecommunications, waste-collection and electricity networks
clm-af3bc8987a5870be
descriptive
the Districlima district heating-and-cooling system
clm-f1ac3d8e8b1d4ff4
quantitative
Backed by more than €180 million in public funding
clm-8ed68a85bb5223a1
descriptive
the district became Barcelona's Urban Lab: delimited areas where companies could test technologies later replicated elsewhere in the city
clm-c576db5103ee384b
quantitative
of the 4,600 social housing units expected, 1,520 had been built by 2010 and 1,600 by December 2014 — eighty more units in four years
clm-a9c110dac6ac6715
quantitative
the share of land approved for transformation moved from 68.92% in December 2010 to 70.5% in December 2014
clm-baa0330f1ede8a78
quantitative
A sectoral real-estate study put 50.6% of the district's land as still pending complete transformation
clm-62dc823d0bdc62d8
quantitative
400 companies moved into the district between 2007 and 2008, and only 61 between 2008 and 2009
clm-fc72612cbbfe22a5
quantitative
The housing and land figures come from the city's own 2016 report '10 Anys de 22@'
clm-1b5dc1b7d82b7ad7
quantitative
22@ put fibre, waste collection and district heating and cooling under 200 hectares of Poblenou, and that buried layer is what made the Urban Lab
clm-0b7081a0a80439e7
quantitative
moved eighty social housing units in four years against a promise of 4,600
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
Erratum on this revision's envelope. The snapshot, its hash and its permanent link are untouched.
sha256:b85c85033d2e3ae0a33f14b2518cf9df693cc6c4ed18bb61663e435abcf7ff05
src-0028767c0c7fc154Peer-reviewed, published 11 April 2020: the district equipped with fibre optics, a connection to pneumatic waste and spaces for climate-control systems as the precondition for Urban Lab projects; the social-housing, land-transformation and company-arrival figures; and the attribution of the stall to the financial crisis.
src-4588b161c39d01fbSpecial Infrastructure Plan covering 37 km of streets and constituting fibre-optic telecommunications, waste-collection and electricity networks; over €180m of public funding; two hundred hectares of former industrial land, ongoing since 2000.
src-93886b2d7359cceaDistriclima district heating and cooling serving 22@ and Poblenou, with a further plant announced for 2024-2025.
src-3b462b8fbc901fb8Case study of the rezoning: 200 hectares of privately owned land, about 250 city blocks; by 2010 the district had 114,000 m² of new green space and 7,000 companies, businesses and shops. The page carries no publication date; the June 2011 dates in its text are the author's own access dates for cited works.