clm-010e5dcd764a66a9
quantitative
was structurally complete by late 2023 but could not carry anyone until August 2025, because the trains were missing
Permanent project revision
Revision 2026-08-27-correction-run · effective 2026-07-26
Current revision. This is the snapshot used by the live entity page.
Read the ridership report and the Railway Gazette report in full; corrected the ridership source's date to the publisher's local day and removed a headway figure its note attributed to it.
sha256:6ac1c0b69291c4497d6e876b27163250fb7944bdd399e7061a63fed935a9a347
replace /snapshot/projectFingerprint — Updated projectFingerprint to the current sourced project record.replace /snapshot/sources — Updated sources to the current sourced project record.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-010e5dcd764a66a9
quantitative
was structurally complete by late 2023 but could not carry anyone until August 2025, because the trains were missing
clm-e068fbc97293e7a5
quantitative
The 2019 coach order went to China's CRRC as the lowest bidder
clm-1338d5b83b3253c1
quantitative
after the 2020 Galwan clash new procurement rules required bidders from land-border countries to obtain security clearances, CRRC's Indian factory plan stalled and its personnel were denied visas
clm-23b877badff63d3d
quantitative
Siemens supplied CBTC rated GoA 4, the highest grade of automation, but service opened in semi-automatic mode with a driver in the cab
clm-83d71286ce32ceca
quantitative
three trainsets out of fifteen, on a 25-minute headway
clm-d854a488fb6a7419
quantitative
The Takshashila Institution estimates the delay added 32 per cent to the cost, about 1,866 crore rupees, against the 410 crore saved by taking the cheapest bid
clm-aa1d7605c5004fb9
quantitative
By June 2026 ten trains were running at a seven-minute peak headway, with the last two of the fifteen still in manufacture
clm-09419ade01aae837
quantitative
the civil works were finished in 2023 and the signalling was rated for the highest grade of automation
clm-d3e334c52c7c4a39
descriptive
after Galwan, new rules required bidders from land-border countries to obtain security clearances, the supplier's Indian factory plan stalled and its personnel were refused visas
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:6ac1c0b69291c4497d6e876b27163250fb7944bdd399e7061a63fed935a9a347
src-b3f70831c70dc965Independent think-tank analysis and the load-bearing source for the delay chain: the December 2019 coach contract as the cheapest bid, the local-content rule, the 2020 border clash and the new security-clearance requirement, the 2022 pivot to an Indian joint venture, visas cleared only in December 2023, structures complete by late 2023, opening 11 August 2025 with 3 of 15 trainsets. Carries the impact figure.
src-70e277425e6e4d49Supplier primary source: CBTC with automatic train protection and supervision. States it will be the first such project in India rated for unattended operation — a capability claim by the vendor, not evidence of how the line actually runs.
src-b7643355ea901d7dRead in full 2026-08-27 through a text-extraction proxy; published 12 August 2025. Decisive on the automation question: the trains are capable of unattended operation but opened in semi-automatic mode with a driver in the cab, to be upgraded after systems assurance.
src-43e405e543c283fcTrade press for the launch facts: inaugurated 10 August 2025, 19.14 km, 16 stations, interchange with the Green Line, network to 76 km. Cites a project cost higher than the Takshashila figure.
src-344b0ebd5f1eacf6Most recent operational status: 13th six-coach set handed over 15 June 2026; 10 trains in service at a 7-minute peak headway; all 15 expected by August 2026.
src-a2fadffb7122292aCounterweight: a roughly 40-minute evening disruption acknowledged by the operator. Also confirms the headway sequence: three trains every 25 minutes at opening, a fourth cutting the wait to about 19 minutes.
src-fb67eea454bc5e0aRead in full 2026-08-27 through a text-extraction proxy (deccanherald.com returns HTTP 403 to direct clients). 'Since the inauguration of Namma Metro Yellow Line on August 10, the stretch running between RV Road and Bommasandra has been garnering an average daily ridership of 60,000, a well-placed Bangalore Metro Rail Corporation Limited (BMRCL) confirmed to DH.' The publisher's timestamp is 2025-09-01 03:07 IST; the date recorded here follows the publisher's local day. The article does not carry a headway figure — that is the Asianet report.