clm-1ed7dfc9bd92bc3d
quantitative
Chugach Electric integrates the 11-turbine, 17.6MW Fire Island wind farm (running since 2012, about 3% of retail load) into Anchorage's Railbelt grid
Permanent project revision
Revision 2026-08-27-claims-and-sources · effective 2026-08-27
Superseded. A later revision exists: 2026-08-27-source-dating →
Created the first structured Evidence Passport with 4 claims and 3 source dossiers.
sha256:716d15987c216d531f6a3bcf69095b2dee2d7ced7540a489d9cade95c801fb1e
add /evidencePassport — Added claim-level evidence mapping and source dossiers.add /revisionHistory — Established a permanent, hash-addressed baseline revision.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-1ed7dfc9bd92bc3d
quantitative
Chugach Electric integrates the 11-turbine, 17.6MW Fire Island wind farm (running since 2012, about 3% of retail load) into Anchorage's Railbelt grid
clm-337bceed308ebd4d
quantitative
Since October 2024 it also stabilizes that grid with a 40MW/80MWh Tesla Megapack battery system, co-owned with Matanuska Electric ($65M total), that replaces spinning-reserve gas generators as backup
clm-4538c81bc6cc0cfb
quantitative
Chugach projects the battery system will cut Railbelt-area natural gas consumption by about 5% a year by holding spinning reserve instead of idling gas turbines for it
clm-89d244208110658b
quantitative
no measured figure has been published since commissioning in October 2024
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
Erratum on this revision's envelope. The snapshot, its hash and its permanent link are untouched.
sha256:716d15987c216d531f6a3bcf69095b2dee2d7ced7540a489d9cade95c801fb1e
src-e6629c316d878a43Confirms Fire Island Wind's 17.6MW capacity and ~3% of retail load, current page.
src-d479bb44eb94ecc9Official press release: 40MW/2-hour BESS, $65M, 75/25 Chugach/MEA ownership, spinning-reserve replacement, projected 5% annual gas savings.
src-4d4475e5baf8802fIndependent trade coverage of the October 2024 commissioning.