clm-12edc8f4416f8a4d
descriptive
Abu Dhabi's Integrated Transport Centre announced smart ramp signals at seven on-ramps feeding Sheikh Zayed bin Sultan Street
Permanent project revision
Revision 2026-08-22-evidence-baseline · effective 2026-08-08
Current revision. This is the snapshot used by the live entity page.
Created the first structured Evidence Passport with 8 claims and 4 source dossiers.
sha256:e4e7d1a8230148aa68de37fd0faae06c5551b0b2d44880b0bbb6f1d72401ba01
add /evidencePassport — Added claim-level evidence mapping and source dossiers.add /revisionHistory — Established a permanent, hash-addressed baseline revision.The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-12edc8f4416f8a4d
descriptive
Abu Dhabi's Integrated Transport Centre announced smart ramp signals at seven on-ramps feeding Sheikh Zayed bin Sultan Street
clm-3404f2f9db895707
quantitative
in August 2025
clm-c5fae2236f437db9
descriptive
using radar, video and AI-flagged cameras
clm-bb1d456c0311c301
descriptive
to throttle merging traffic before backups form
clm-1e7af41f8a1793fd
descriptive
A build by Umovity, Econolite and Tatweer
clm-bbfb0d8e9eacd2da
descriptive
billed as the Middle East's first fully adaptive ramp-metering system
clm-e50da1ca77a15a7a
descriptive
links it to the emirate's traffic-modelling platform
clm-2b984467227beb8c
quantitative
The vendors project — but have not measured — up to $2.6M a year in avoided delay costs.
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:e4e7d1a8230148aa68de37fd0faae06c5551b0b2d44880b0bbb6f1d72401ba01
src-24c83a92b94b2be3Seven entry points, sensors/AI cameras, dynamic signal timing, platform integration.
src-40b4ccc0295bc337Confirms same seven locations and Sept 1, 2025 activation reporting.
src-c61f6b5b1be2a9c0Technology stack, six-month delivery, $1.7-2.6M projected annual savings (explicitly a projection, not a measured result).
src-5bffe8c2f7e7dba3May 2026 commissioning, vendor list, executive quotes.