Mexico City Water Network Sectorisation and Telemetry
This overview was generated with AI from the public sources listed below and checked against them before publication. It has not had a complete human fact-check — treat it as a starting point and follow the sources.
1 sourced claim on this page, none individually verified yet — turn on “Sources in the text” to see each one.
How this atlas is made · What “last verified” means · What “source-checked” means · The full record behind this page
The utility has been cutting its network into metered sectors and has finished 484 of them, 58 percent of the plan. It still loses around 40 percent of its water, and the promised public dashboard never appeared.
what does this mean?
The strongest source behind this entry is an independent peer-reviewed or academic study. It grades who did the looking — not how well the project went. All four grades →Part of 1001 Smart Cities — 1,167 documented projects · 🏙️ 7 more in Mexico City · 💧 Water guide · 📡 Data & IoT projects
Mexico City's water utility has been carving its distribution network into roughly 830 metered sectors since 2019, fitting macro-meters, control valves and pressure regulators so leaks can be isolated and pressure managed. It reported 484 sectors finished by August 2022, 58 percent of the plan, and the goal of covering the whole city by 2024 was missed. Telemetry and SCADA stations watch wells, tanks and pumping plants, and residents can look up their neighbourhood's water source and rationing schedule online. What the city does not publish is the measurements themselves: a promised public dashboard of network readings, due at the end of 2022, never appeared.
📊 Impact
484 of 847 planned hydraulic sectors were built by August 2022 — 58 percent of the programme by the count in La Razón's report of the utility's progress; most other sources put the plan total near 830 — for 955.5 million pesos, which the utility credited with recovering 550 litres per second across seven boroughs. Sacmex has repeatedly put losses at around 40 percent of supply. A 2023 PLOS Water study surveying 2,595 residents found 73 percent of households in the five eastern boroughs receive water only intermittently, averaging 87 hours a week, and 61 percent had suffered an outage in the previous three years.
🎓 Lesson
Cutting a network into metered sectors only pays if the sectors are then operated and the readings are published. Mexico City has built more than half of them, still loses roughly 40 percent of its water by its own account, and gives residents a schedule lookup instead of the data.
Sources
Show 5 more sourcesShow fewer
📅 How old is the evidence?
Two clocks, kept apart: when this entry’s sources were published, and what has happened to its record in the atlas. Documented span: since 2019. 8 of 10 sources carry a publication date, from 4 April 2019 to 18 February 2026.
When the sources were published
- Diario Basta · pressDiario Basta — sectorisation programme launched (4 Apr 2019)
- La Razón de México · pressLa Razón — sectorisation at 58 percent (30 Aug 2022)
- PLOS (Public Library of Science) · researchHuberts et al., PLOS Water (2023) — household costs of intermittent supply
- El Financiero · pressEl Financiero — how residents check the tandeo schedule (30 Jan 2024)
- Excélsior · pressExcélsior — telemetry stations rehabilitated and added (30 Apr 2024)
- El Universal · pressEl Universal — Congress approves replacing Sacmex with Segiagua
- El Universal · pressEl Universal — 2026 water budget funds metering, automation and telemetry (15 Dec 2025)
- Almomento · pressAlmomento — 2026 Plan Hídrico, leak repair and buried-pipe survey (18 Feb 2026)
Show your work What this page rests on and what it can’t tell you · all 1 claims with their sources · the forensic record
Evidence Passport · public beta 1 addressable claim, 10 source dossiers, one permanent baseline. The passport is unreviewed — an AI-assisted structural migration, not a human or expert endorsement. Every revision keeps a permanent copy under revision history.
Inspect the claims, one by one — verbatim text, sources and caveats for all 1
The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-aa96f8a6a8cf7ac8
quantitative
A 2023 PLOS Water study surveying 2,595 residents found 73 percent of households in the five eastern boroughs receive water only intermittently, averaging 87 hours a week, and 61 percent had suffered an outage in the previous three years
Sources carrying this claim
Forensic record — source dossiers, gaps, hashes and the exact revision this page renders
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:863968b843fb7afe721dc303b3a676c492885943cbfee1545f140a18ba007875
- 1
- of 1 claims mapped
- 10
- source dossiers
- 8
- publication dates recorded
- 1
- archives linked
- 0
- exact locators
- 0
- content captures hashed
Governance facts carried by the record
- Operator
- Secretaría de Gestión Integral del Agua (Segiagua), formerly Sacmex
- Actor types
- utility, city-government
- Funding model
- public
- Funding description
- Mexico City government budget
- Cost
- ≈955.5M MXN on sectorisation to Aug 2022; ≈19bn MXN city water and drainage budget for 2026
- Ownership
- Not recorded
- Decision rights
- Not recorded
- Exit conditions
- Not recorded
10 source dossiers
La Razón — sectorisation at 58 percent (30 Aug 2022)
- Stable source ID
src-bc2f84a67e939c1f- Publisher
- Name not classified · razon.com.mx
- Type / language
- web-page · language not classified
- Published
- 2022-08-30
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
'Se han concluido 484 de los 847 sectores' previstos para 2024, con una inversión de 955 millones de pesos ('484 of the 847 sectors planned for 2024 have been completed', 955 million pesos invested). Same piece: 'Para finales de ese año se preveía un portal de acceso público con mediciones principales de la ciudad' ('a public portal with the city's main measurements was expected by the end of that year') — that portal was not found in 2026. Most other sources give the plan total as 830, not 847.
- Claims linked
- Background source; no baseline claim points here
Diario Basta — sectorisation programme launched (4 Apr 2019)
- Stable source ID
src-eede65a00950007f- Publisher
- Name not classified · diariobasta.com
- Type / language
- web-page · language not classified
- Published
- 2019-04-04
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Dates the start of the programme to 2019, beginning in Álvaro Obregón and Benito Juárez under that year's Sacmex works plan. Basis for yearStart.
- Claims linked
- Background source; no baseline claim points here
Excélsior — telemetry stations rehabilitated and added (30 Apr 2024)
- Stable source ID
src-f0196077f3db909f- Publisher
- Name not classified · excelsior.com.mx
- Type / language
- web-page · language not classified
- Published
- 2024-04-30
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
'Rehabilitación de 35 estaciones de medición y telemetría, así como la implementación de 30 nuevas estaciones' ('rehabilitation of 35 measurement and telemetry stations, plus 30 new stations'), a 30 million peso investment permitting real-time monitoring. The same article's figure of 9,270 litres per second recovered covers wells, springs and pumping plants generally and is deliberately not used here.
- Claims linked
- Background source; no baseline claim points here
El Universal — 2026 water budget funds metering, automation and telemetry (15 Dec 2025)
- Stable source ID
src-524a22a68aa00094- Publisher
- Name not classified · eluniversal.com.mx
- Type / language
- web-page · language not classified
- Published
- 2025-12-15
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
19 billion pesos for water and drainage in 2026, an increase of 26.7 percent; the works contemplate 'medición, automatización y telemetría' to 'incrementar la eficiencia de la infraestructura hidráulica' ('metering, automation and telemetry' to 'increase the efficiency of the hydraulic infrastructure'). Evidence the programme is still live and funded.
- Claims linked
- Background source; no baseline claim points here
Almomento — 2026 Plan Hídrico, leak repair and buried-pipe survey (18 Feb 2026)
- Stable source ID
src-d0eb02f88a03520a- Publisher
- Name not classified · almomento.mx
- Type / language
- web-page · language not classified
- Published
- 2026-02-18
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
'Triplicar la reparación de fugas, lo que permitiría recuperar 300 litros por segundo' ('triple leak repairs, which would allow 300 litres per second to be recovered') and 'inteligencia satelital y georradar terrestre, capaces de supervisar 800 kilómetros de infraestructura subterránea' ('satellite intelligence and ground-penetrating radar, able to survey 800 kilometres of underground infrastructure'). Strongest recent source on current state.
- Claims linked
- Background source; no baseline claim points here
Sacmex/Segiagua — 'Agua en tu colonia' supply-schedule portal (operator)
- Stable source ID
src-08385970aaf20ab7- Publisher
- Name not classified · aguaentucolonia.sacmex.cdmx.gob.mx
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Public lookup returning a neighbourhood's water source and scheduled supply hours. The page is a JavaScript single-page app and served no readable content to an automated fetch; existence and function corroborated by press coverage below. It publishes schedules, not measurements, and offers no download or API.
- Claims linked
- Background source; no baseline claim points here
El Financiero — how residents check the tandeo schedule (30 Jan 2024)
- Stable source ID
src-54501ed7544594a3- Publisher
- Name not classified · elfinanciero.com.mx
- Type / language
- web-page · language not classified
- Published
- 2024-01-30
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Independent corroboration of what the portal does: select borough and neighbourhood to get the water source and the hours when supply is scheduled.
- Claims linked
- Background source; no baseline claim points here
Milenio — Sacmex puts network losses at 40 percent
- Stable source ID
src-3bf462f37ab09e44- Publisher
- Name not classified · milenio.com
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
'CdMx pierde 40 por ciento de agua por fugas en redes, revela Sacmex' ('Mexico City loses 40 percent of its water to network leaks, Sacmex reveals'). The figure is the utility's own, reported consistently by El Universal, Crónica and Aristegui Noticias since 2015; it is attributed here rather than asserted. Note: the city's own indicator portal (indicadores.cdmx.gob.mx) is reported to record 52.19 percent unaccounted-for water for 2022, a materially higher figure, but that page returned HTTP 503 on every attempt during review and the number is therefore not used.
- Claims linked
- Background source; no baseline claim points here
Huberts et al., PLOS Water (2023) — household costs of intermittent supply
- Stable source ID
src-c91cdcc8f0181e59- Publisher
- Name not classified · journals.plos.org
- Type / language
- web-page · language not classified
- Published
- 2023-03-08
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- Open archived copy ↗ · 2026-04-13
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Peer-reviewed. '73% of surveyed households in those five boroughs reported receiving water intermittently', 'with an average of 87 hours a week, or roughly 12 hours a day'; '61% of surveyed households reported having experienced an outage of their water supply in the last three years'. Survey of 2,595 individuals in Gustavo A. Madero, Venustiano Carranza, Iztacalco, Iztapalapa and Tláhuac.
- Claims linked
El Universal — Congress approves replacing Sacmex with Segiagua
- Stable source ID
src-b02c2cfc68dbfd13- Publisher
- Name not classified · eluniversal.com.mx
- Type / language
- web-page · language not classified
- Published
- 2024-10-02
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-07-26
- Dossier created
- 2026-08-20
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
'Con 65 votos a favor se avalaron cambios al Artículo 16 de la Constitución capitalina' so that 'el Sistema de Aguas de la Ciudad de México (Sacmex) pasará a ser la Secretaría de Gestión Integral del Agua' ('with 65 votes in favour, changes to Article 16 of the city constitution were approved' so that Sacmex 'will become the Secretariat for Integrated Water Management'). The change was completed in December 2025; Segiagua is the operator today, Sacmex the name under which most of this work was done.
- Claims linked
- Background source; no baseline claim points here
Known limits of this passport
- Publisher names and source languages have not yet been classified; domains are recorded without guessing.
- Existing source notes are descriptive locators, not page- or paragraph-exact citations.
- A missing archive, publication date or content hash is shown as null rather than inferred.
- The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim.
Continue exploring
Compare this project
Explore the wider context
📎 Cite this project
1001 Smart Cities (2026). “Mexico City Water Network Sectorisation and Telemetry” — Mexico City, Mexico. The Smart City Atlas. https://1001smartcities.org/projects/mexico-city-water-monitoring/ (last verified 2026-07-26). Data: CC BY 4.0.
The underlying data is free to reuse with attribution — see the open data page.