Mexico City Water Network Sectorisation and Telemetry

🤖 AI-generated summary · ◆ 1 sourced claim · 🔎 Last verified

This overview was generated with AI from the public sources listed below and checked against them before publication. It has not had a complete human fact-check — treat it as a starting point and follow the sources.

1 sourced claim on this page, none individually verified yet — turn on “Sources in the text” to see each one.

How this atlas is made · What “last verified” means · What “source-checked” means · The full record behind this page

The utility has been cutting its network into metered sectors and has finished 484 of them, 58 percent of the plan. It still loses around 40 percent of its water, and the promised public dashboard never appeared.

Evidence🔬 Peer-reviewed
what does this mean?The strongest source behind this entry is an independent peer-reviewed or academic study. It grades who did the looking — not how well the project went. All four grades →
Scale🏙️ City-wide
Cost≈955.5M MXN on sectorisation to Aug 2022; ≈19bn MXN city water and drainage budget for 2026
FundingMexico City government budget

Part of 1001 Smart Cities — 1,167 documented projects · 🏙️ 7 more in Mexico City · 💧 Water guide · 📡 Data & IoT projects

Mexico City's water utility has been carving its distribution network into roughly 830 metered sectors since 2019, fitting macro-meters, control valves and pressure regulators so leaks can be isolated and pressure managed. It reported 484 sectors finished by August 2022, 58 percent of the plan, and the goal of covering the whole city by 2024 was missed. Telemetry and SCADA stations watch wells, tanks and pumping plants, and residents can look up their neighbourhood's water source and rationing schedule online. What the city does not publish is the measurements themselves: a promised public dashboard of network readings, due at the end of 2022, never appeared.

Live 📅 since 2019

📊 Impact

484 of 847 planned hydraulic sectors were built by August 2022 — 58 percent of the programme by the count in La Razón's report of the utility's progress; most other sources put the plan total near 830 — for 955.5 million pesos, which the utility credited with recovering 550 litres per second across seven boroughs. Sacmex has repeatedly put losses at around 40 percent of supply. A 2023 PLOS Water study surveying 2,595 residents found 73 percent of households in the five eastern boroughs receive water only intermittently, averaging 87 hours a week, and 61 percent had suffered an outage in the previous three years.

🎓 Lesson

Cutting a network into metered sectors only pays if the sectors are then operated and the readings are published. Mexico City has built more than half of them, still loses roughly 40 percent of its water by its own account, and gives residents a schedule lookup instead of the data.

Sources

↗ La Razón — sectorisation at 58 percent (30 Aug 2022)'Se han concluido 484 de los 847 sectores' previstos para 2024, con una inversión de 955 millones de pesos ('484 of the 847 sectors planned for 2024 have been completed', 955 million pesos invested). Same piece: 'Para finales de ese año se preveía un portal de acceso público con mediciones principales de la ciudad' ('a public portal with the city's main measurements was expected by the end of that year') — that portal was not found in 2026. Most other sources give the plan total as 830, not 847.
↗ Diario Basta — sectorisation programme launched (4 Apr 2019)Dates the start of the programme to 2019, beginning in Álvaro Obregón and Benito Juárez under that year's Sacmex works plan. Basis for yearStart.
↗ Excélsior — telemetry stations rehabilitated and added (30 Apr 2024)'Rehabilitación de 35 estaciones de medición y telemetría, así como la implementación de 30 nuevas estaciones' ('rehabilitation of 35 measurement and telemetry stations, plus 30 new stations'), a 30 million peso investment permitting real-time monitoring. The same article's figure of 9,270 litres per second recovered covers wells, springs and pumping plants generally and is deliberately not used here.
↗ El Universal — 2026 water budget funds metering, automation and telemetry (15 Dec 2025)19 billion pesos for water and drainage in 2026, an increase of 26.7 percent; the works contemplate 'medición, automatización y telemetría' to 'incrementar la eficiencia de la infraestructura hidráulica' ('metering, automation and telemetry' to 'increase the efficiency of the hydraulic infrastructure'). Evidence the programme is still live and funded.
↗ Almomento — 2026 Plan Hídrico, leak repair and buried-pipe survey (18 Feb 2026)'Triplicar la reparación de fugas, lo que permitiría recuperar 300 litros por segundo' ('triple leak repairs, which would allow 300 litres per second to be recovered') and 'inteligencia satelital y georradar terrestre, capaces de supervisar 800 kilómetros de infraestructura subterránea' ('satellite intelligence and ground-penetrating radar, able to survey 800 kilometres of underground infrastructure'). Strongest recent source on current state.
Show 5 more sourcesShow fewer
↗ Sacmex/Segiagua — 'Agua en tu colonia' supply-schedule portal (operator)Public lookup returning a neighbourhood's water source and scheduled supply hours. The page is a JavaScript single-page app and served no readable content to an automated fetch; existence and function corroborated by press coverage below. It publishes schedules, not measurements, and offers no download or API.
↗ El Financiero — how residents check the tandeo schedule (30 Jan 2024)Independent corroboration of what the portal does: select borough and neighbourhood to get the water source and the hours when supply is scheduled.
↗ Milenio — Sacmex puts network losses at 40 percent'CdMx pierde 40 por ciento de agua por fugas en redes, revela Sacmex' ('Mexico City loses 40 percent of its water to network leaks, Sacmex reveals'). The figure is the utility's own, reported consistently by El Universal, Crónica and Aristegui Noticias since 2015; it is attributed here rather than asserted. Note: the city's own indicator portal (indicadores.cdmx.gob.mx) is reported to record 52.19 percent unaccounted-for water for 2022, a materially higher figure, but that page returned HTTP 503 on every attempt during review and the number is therefore not used.
↗ Huberts et al., PLOS Water (2023) — household costs of intermittent supplyPublished 8 March 2023 archived copyPeer-reviewed. '73% of surveyed households in those five boroughs reported receiving water intermittently', 'with an average of 87 hours a week, or roughly 12 hours a day'; '61% of surveyed households reported having experienced an outage of their water supply in the last three years'. Survey of 2,595 individuals in Gustavo A. Madero, Venustiano Carranza, Iztacalco, Iztapalapa and Tláhuac.
↗ El Universal — Congress approves replacing Sacmex with SegiaguaPublished 2 October 2024'Con 65 votos a favor se avalaron cambios al Artículo 16 de la Constitución capitalina' so that 'el Sistema de Aguas de la Ciudad de México (Sacmex) pasará a ser la Secretaría de Gestión Integral del Agua' ('with 65 votes in favour, changes to Article 16 of the city constitution were approved' so that Sacmex 'will become the Secretariat for Integrated Water Management'). The change was completed in December 2025; Segiagua is the operator today, Sacmex the name under which most of this work was done.

📅 How old is the evidence?

Two clocks, kept apart: when this entry’s sources were published, and what has happened to its record in the atlas. Documented span: since 2019. 8 of 10 sources carry a publication date, from 4 April 2019 to 18 February 2026.

When the sources were published

  1. Diario Basta · pressDiario Basta — sectorisation programme launched (4 Apr 2019)
  2. La Razón de México · pressLa Razón — sectorisation at 58 percent (30 Aug 2022)
  3. PLOS (Public Library of Science) · researchHuberts et al., PLOS Water (2023) — household costs of intermittent supply
  4. El Financiero · pressEl Financiero — how residents check the tandeo schedule (30 Jan 2024)
  5. Excélsior · pressExcélsior — telemetry stations rehabilitated and added (30 Apr 2024)
  6. El Universal · pressEl Universal — Congress approves replacing Sacmex with Segiagua
  7. El Universal · pressEl Universal — 2026 water budget funds metering, automation and telemetry (15 Dec 2025)
  8. Almomento · pressAlmomento — 2026 Plan Hídrico, leak repair and buried-pipe survey (18 Feb 2026)

Every source, with links ↑

What happened to this record

  1. Sources last read
  2. Entered the record

Every revision, permanent →

Show your work What this page rests on and what it can’t tell you · all 1 claims with their sources · the forensic record

Evidence Passport · public beta 1 addressable claim, 10 source dossiers, one permanent baseline. The passport is unreviewed — an AI-assisted structural migration, not a human or expert endorsement. Every revision keeps a permanent copy under revision history.

Inspect the claims, one by one — verbatim text, sources and caveats for all 1

The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.

Claim 1 clm-aa96f8a6a8cf7ac8 quantitative
A 2023 PLOS Water study surveying 2,595 residents found 73 percent of households in the five eastern boroughs receive water only intermittently, averaging 87 hours a week, and 61 percent had suffered an outage in the previous three years
Published field
impact · verbatim
Mapping
mapped · no interpretation or interpolation added by this passport
What the mapping says
No support note recorded
Caveat
The utility itself still puts network losses at around 40 percent of supply, and the promised public dashboard of network readings never appeared.

Sources carrying this claim

  1. Huberts et al., PLOS Water (2023) — household costs of intermittent supply
Forensic record — source dossiers, gaps, hashes and the exact revision this page renders

This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.

unreviewed Revision 2026-08-20-source-dates effective 2026-07-26 · created 2026-08-20

Awaiting operator and domain-expert review; publication of this revision implies neither.

sha256:863968b843fb7afe721dc303b3a676c492885943cbfee1545f140a18ba007875
1
of 1 claims mapped
10
source dossiers
8
publication dates recorded
1
archives linked
0
exact locators
0
content captures hashed

Governance facts carried by the record

Operator
Secretaría de Gestión Integral del Agua (Segiagua), formerly Sacmex
Actor types
utility, city-government
Funding model
public
Funding description
Mexico City government budget
Cost
≈955.5M MXN on sectorisation to Aug 2022; ≈19bn MXN city water and drainage budget for 2026
Ownership
Not recorded
Decision rights
Not recorded
Exit conditions
Not recorded

10 source dossiers

La Razón — sectorisation at 58 percent (30 Aug 2022) razon.com.mx · background

Open original source ↗

Stable source ID
src-bc2f84a67e939c1f
Publisher
Name not classified · razon.com.mx
Type / language
web-page · language not classified
Published
2022-08-30
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-20
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

'Se han concluido 484 de los 847 sectores' previstos para 2024, con una inversión de 955 millones de pesos ('484 of the 847 sectors planned for 2024 have been completed', 955 million pesos invested). Same piece: 'Para finales de ese año se preveía un portal de acceso público con mediciones principales de la ciudad' ('a public portal with the city's main measurements was expected by the end of that year') — that portal was not found in 2026. Most other sources give the plan total as 830, not 847.

Descriptive only — not page/paragraph exact
Claims linked
Background source; no baseline claim points here
Diario Basta — sectorisation programme launched (4 Apr 2019) diariobasta.com · background

Open original source ↗

Stable source ID
src-eede65a00950007f
Publisher
Name not classified · diariobasta.com
Type / language
web-page · language not classified
Published
2019-04-04
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-20
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Dates the start of the programme to 2019, beginning in Álvaro Obregón and Benito Juárez under that year's Sacmex works plan. Basis for yearStart.

Descriptive only — not page/paragraph exact
Claims linked
Background source; no baseline claim points here
Excélsior — telemetry stations rehabilitated and added (30 Apr 2024) excelsior.com.mx · background

Open original source ↗

Stable source ID
src-f0196077f3db909f
Publisher
Name not classified · excelsior.com.mx
Type / language
web-page · language not classified
Published
2024-04-30
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-20
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

'Rehabilitación de 35 estaciones de medición y telemetría, así como la implementación de 30 nuevas estaciones' ('rehabilitation of 35 measurement and telemetry stations, plus 30 new stations'), a 30 million peso investment permitting real-time monitoring. The same article's figure of 9,270 litres per second recovered covers wells, springs and pumping plants generally and is deliberately not used here.

Descriptive only — not page/paragraph exact
Claims linked
Background source; no baseline claim points here
El Universal — 2026 water budget funds metering, automation and telemetry (15 Dec 2025) eluniversal.com.mx · background

Open original source ↗

Stable source ID
src-524a22a68aa00094
Publisher
Name not classified · eluniversal.com.mx
Type / language
web-page · language not classified
Published
2025-12-15
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-20
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

19 billion pesos for water and drainage in 2026, an increase of 26.7 percent; the works contemplate 'medición, automatización y telemetría' to 'incrementar la eficiencia de la infraestructura hidráulica' ('metering, automation and telemetry' to 'increase the efficiency of the hydraulic infrastructure'). Evidence the programme is still live and funded.

Descriptive only — not page/paragraph exact
Claims linked
Background source; no baseline claim points here
Almomento — 2026 Plan Hídrico, leak repair and buried-pipe survey (18 Feb 2026) almomento.mx · background

Open original source ↗

Stable source ID
src-d0eb02f88a03520a
Publisher
Name not classified · almomento.mx
Type / language
web-page · language not classified
Published
2026-02-18
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-20
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

'Triplicar la reparación de fugas, lo que permitiría recuperar 300 litros por segundo' ('triple leak repairs, which would allow 300 litres per second to be recovered') and 'inteligencia satelital y georradar terrestre, capaces de supervisar 800 kilómetros de infraestructura subterránea' ('satellite intelligence and ground-penetrating radar, able to survey 800 kilometres of underground infrastructure'). Strongest recent source on current state.

Descriptive only — not page/paragraph exact
Claims linked
Background source; no baseline claim points here
Sacmex/Segiagua — 'Agua en tu colonia' supply-schedule portal (operator) aguaentucolonia.sacmex.cdmx.gob.mx · background

Open original source ↗

Stable source ID
src-08385970aaf20ab7
Publisher
Name not classified · aguaentucolonia.sacmex.cdmx.gob.mx
Type / language
web-page · language not classified
Published
Not recorded
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-20
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Public lookup returning a neighbourhood's water source and scheduled supply hours. The page is a JavaScript single-page app and served no readable content to an automated fetch; existence and function corroborated by press coverage below. It publishes schedules, not measurements, and offers no download or API.

Descriptive only — not page/paragraph exact
Claims linked
Background source; no baseline claim points here
El Financiero — how residents check the tandeo schedule (30 Jan 2024) elfinanciero.com.mx · background

Open original source ↗

Stable source ID
src-54501ed7544594a3
Publisher
Name not classified · elfinanciero.com.mx
Type / language
web-page · language not classified
Published
2024-01-30
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-20
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

Independent corroboration of what the portal does: select borough and neighbourhood to get the water source and the hours when supply is scheduled.

Descriptive only — not page/paragraph exact
Claims linked
Background source; no baseline claim points here
Milenio — Sacmex puts network losses at 40 percent milenio.com · background

Open original source ↗

Stable source ID
src-3bf462f37ab09e44
Publisher
Name not classified · milenio.com
Type / language
web-page · language not classified
Published
Not recorded
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-20
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

'CdMx pierde 40 por ciento de agua por fugas en redes, revela Sacmex' ('Mexico City loses 40 percent of its water to network leaks, Sacmex reveals'). The figure is the utility's own, reported consistently by El Universal, Crónica and Aristegui Noticias since 2015; it is attributed here rather than asserted. Note: the city's own indicator portal (indicadores.cdmx.gob.mx) is reported to record 52.19 percent unaccounted-for water for 2022, a materially higher figure, but that page returned HTTP 503 on every attempt during review and the number is therefore not used.

Descriptive only — not page/paragraph exact
Claims linked
Background source; no baseline claim points here
Huberts et al., PLOS Water (2023) — household costs of intermittent supply journals.plos.org · 1 linked claim

Open original source ↗

Stable source ID
src-c91cdcc8f0181e59
Publisher
Name not classified · journals.plos.org
Type / language
web-page · language not classified
Published
2023-03-08
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-20
Retrieved copy
No local capture recorded
Archive
Open archived copy ↗ · 2026-04-13
Content hash
No captured content hash
Locator
Open the recorded source note

Peer-reviewed. '73% of surveyed households in those five boroughs reported receiving water intermittently', 'with an average of 87 hours a week, or roughly 12 hours a day'; '61% of surveyed households reported having experienced an outage of their water supply in the last three years'. Survey of 2,595 individuals in Gustavo A. Madero, Venustiano Carranza, Iztacalco, Iztapalapa and Tláhuac.

Descriptive only — not page/paragraph exact
El Universal — Congress approves replacing Sacmex with Segiagua eluniversal.com.mx · background

Open original source ↗

Stable source ID
src-b02c2cfc68dbfd13
Publisher
Name not classified · eluniversal.com.mx
Type / language
web-page · language not classified
Published
2024-10-02
Updated
Not recorded
Source last checked
No source-level check date
Record last verified
2026-07-26
Dossier created
2026-08-20
Retrieved copy
No local capture recorded
Archive
No archived copy linked
Content hash
No captured content hash
Locator
Open the recorded source note

'Con 65 votos a favor se avalaron cambios al Artículo 16 de la Constitución capitalina' so that 'el Sistema de Aguas de la Ciudad de México (Sacmex) pasará a ser la Secretaría de Gestión Integral del Agua' ('with 65 votes in favour, changes to Article 16 of the city constitution were approved' so that Sacmex 'will become the Secretariat for Integrated Water Management'). The change was completed in December 2025; Segiagua is the operator today, Sacmex the name under which most of this work was done.

Descriptive only — not page/paragraph exact
Claims linked
Background source; no baseline claim points here
Known limits of this passport
  • Publisher names and source languages have not yet been classified; domains are recorded without guessing.
  • Existing source notes are descriptive locators, not page- or paragraph-exact citations.
  • A missing archive, publication date or content hash is shown as null rather than inferred.
  • The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim.
📎 Cite this project

1001 Smart Cities (2026). “Mexico City Water Network Sectorisation and Telemetry” — Mexico City, Mexico. The Smart City Atlas. https://1001smartcities.org/projects/mexico-city-water-monitoring/ (last verified 2026-07-26). Data: CC BY 4.0.

The underlying data is free to reuse with attribution — see the open data page.

✉️ Get the next source-checked smart-city project in your inbox

One short email a week: the Landmark, one Insight, the new cities. No spam, one-click unsubscribe. About the newsletter · RSS