Houston Water's Decade-Long Smart Meter Replacement
Houston Public Works began replacing the remote-read sensors on the city's roughly 480,000 water meters in 2021, aiming to finish within a decade — but by December 2023 only 78,905–85,000 had actually been swapped, and more than 125,000 of the older 1998–2010-era remote-read sensors already installed elsewhere in the system had stopped transmitting, meaning some customers were being billed on estimates rather than real readings. After a multi-year local-news investigation ('DRAINED') into unexplained bill spikes, City Council approved an $8.5 million pilot in August 2025 to install 25,000 fully solid-state smart meters with near-real-time online usage data, testing installation logistics across every council district ahead of a wider rollout.
📊 Impact
More than 125,000 of the roughly 480,000-meter fleet's existing remote-read sensors had stopped transmitting by early 2024, versus only 78,905–85,000 meters upgraded under the 2021-started replacement project by December 2023.
🎓 Lesson
A 'smart' meter upgrade that can't outrun its own maintenance backlog isn't smart yet — it's just newer hardware queued to fail the same way the old hardware did.
📖 Terms in this entry: Non-revenue water (NRW) · Adaptive traffic signals · Digital twin
Sources
This overview was generated with AI from the public sources listed above and checked against them before publication. It has not had a complete human fact-check — treat it as a starting point and follow the sources.
Continue exploring
Compare this project
Explore the wider context
📎 Cite this project
1001 Smart Cities (2026). “Houston Water's Decade-Long Smart Meter Replacement” — Houston, United States. The Smart City Atlas. https://1001smartcities.org/projects/houston-water-smart-metering/ (last verified 2026-08-02). Data: CC BY 4.0.
The underlying data is free to reuse with attribution — see the open data page.