Dhaka WASA District Metered Areas and SCADA
This overview was generated with AI from the public sources listed below and checked against them before publication. It has not had a complete human fact-check — treat it as a starting point and follow the sources.
How this atlas is made · What “last verified” means · What “source-checked” means · The full record behind this page
Dhaka's water utility has spent nearly two decades cutting its distribution network into district metered areas - isolated zones with metered inlets, so the water entering can be compared with the water billed. Two Asian Development Bank projects paid for it: a sector development programme approved in December 2007 rehabilitated 47 DMAs and 2,456 km of mains, and a follow-on loan approved in June 2016 added 85 more across seven of DWASA's ten zones, with SCADA and automated meter reading reported as implemented in all of them. The number of areas planned has itself moved: 164 in 2019, 145 in the utility's 2020-21 annual report, 156 by 2024.
what does this mean?
The strongest source is the operator's or the city's own reporting — an official report, dataset or press release. It grades who did the looking — not how well the project went. All four grades →📊 Impact
Every figure in the argument is DWASA's own. Its Annual Report 2020-21 counts 70 completed DMAs in the managing director's foreword and 71 in the body, and puts non-revenue water inside them at under 4%, at 5% and at 7% in three different passages. DWASA's July 2025 monitoring report for ADB records physical losses in commissioned DMAs down from 40% to an average of 3.44%, while overall physical losses and non-revenue water are still estimated at about 26%; ADB's project data sheet gives 1.6-5.8% in the handed-over areas. In April 2024 the deputy managing director for operations told The Business Standard that 113 of 156 DMAs were finished, that overall system loss was 22%, below 5% inside the DMAs and above 40% in the 43 areas without them. Even the financier's disclosed reporting is the utility's: the July 2025 report says on its own second page that it is a document of the borrower. No independent measurement was found, and in October 2025 DWASA formed an internal committee to determine its actual water production and system loss and to replace faulty meters at its own pumps.
🎓 Lesson
The district is the unit of measurement and the unit of the claim at once: quoting the number from inside its rebuilt areas, the utility can report a single-digit loss rate while its own operations chief puts the rate outside them above 40%. Nothing outside DWASA settles which figure describes Dhaka, and the official numbers do not agree with one another - three government sources in 2026 put groundwater at 66%, 70% and 77% of production. That reading is the one that matters, because the water table under Dhaka is falling by two to three metres a year, and the emergency project the government approved in 2026 to replace, regenerate and add deep tube wells carries 124 more SCADA systems with it.
Sources
Show 5 more sourcesShow fewer
📅 How old is the evidence?
Two clocks, kept apart: when this entry’s sources were published, and what has happened to its record in the atlas. Documented span: since 2007. 6 of 10 sources carry a publication date, from 24 October 2019 to 24 July 2026.
When the sources were published
- United News of Bangladesh - DMA helping Dhaka Wasa curb system loss (press)
- The Business Standard - Wasa suffers water bill loss, consumers made to pay (press)
- DWASA for ADB - 15th Semi-Annual Social Safeguards Monitoring Report, DWSNIP (July 2025)
- The Daily Star - Dhaka Wasa turns to groundwater despite unfinished projects (press)
- Bangladesh Sangbad Sangstha - Govt launches Tk 920.85cr emergency water supply project in Dhaka (state news agency)
- The Daily Star - Tk 32,554cr plan for Dhaka's water future (press)
Show your work What this page rests on and what it can’t tell you · all 19 claims with their sources · the forensic record
Evidence Passport · public beta 19 addressable claims, 10 source dossiers, one permanent baseline. The passport is unreviewed — an AI-assisted structural migration, not a human or expert endorsement. Every revision keeps a permanent copy under revision history.
Inspect the claims, one by one — verbatim text, sources and caveats for all 19
The text below is copied verbatim from the published record. Each claim names the source dossiers that carry it; caveats stay attached to the claim they qualify.
clm-5176a84ba1875878
descriptive
Every figure in the argument is DWASA's own
Sources carrying this claim
- DWASA for ADB - 15th Semi-Annual Social Safeguards Monitoring Report, DWSNIP (July 2025)
- Dhaka WASA - Annual Report 2020-21 (operator)
- The Business Standard - Wasa suffers water bill loss, consumers made to pay (press)
- ADB - Dhaka Water Supply Network Improvement Project, project data sheet (financier)
clm-9cdd76d0a4d4063d
descriptive
cutting its distribution network into district metered areas - isolated zones with metered inlets, so the water entering can be compared with the water billed
Sources carrying this claim
clm-c4270281d95c5665
quantitative
a sector development programme approved in December 2007 rehabilitated 47 DMAs and 2,456 km of mains
Sources carrying this claim
clm-9c81f4c07d3e351f
quantitative
a follow-on loan approved in June 2016 added 85 more across seven of DWASA's ten zones
Sources carrying this claim
clm-326bfd28ae1298be
descriptive
with SCADA and automated meter reading reported as implemented in all of them
Sources carrying this claim
clm-15431e52930d80ae
quantitative
The number of areas planned has itself moved: 164 in 2019, 145 in the utility's 2020-21 annual report, 156 by 2024
Sources carrying this claim
clm-9c4038b316f855be
quantitative
Its Annual Report 2020-21 counts 70 completed DMAs in the managing director's foreword and 71 in the body
Sources carrying this claim
clm-fb5593ee3415bacb
quantitative
puts non-revenue water inside them at under 4%, at 5% and at 7% in three different passages
Sources carrying this claim
clm-d80c730c5a55f49d
quantitative
DWASA's July 2025 monitoring report for ADB records physical losses in commissioned DMAs down from 40% to an average of 3.44%
Sources carrying this claim
clm-83361c29afc9c4c9
quantitative
while overall physical losses and non-revenue water are still estimated at about 26%
Sources carrying this claim
clm-220d6d968fc0d834
quantitative
ADB's project data sheet gives 1.6-5.8% in the handed-over areas
Sources carrying this claim
clm-e9d012263fdbdf96
quantitative
In April 2024 the deputy managing director for operations told The Business Standard that 113 of 156 DMAs were finished, that overall system loss was 22%, below 5% inside the DMAs and above 40% in the 43 areas without them
Sources carrying this claim
clm-aa10bb5e643cc278
quantitative
Even the financier's disclosed reporting is the utility's: the July 2025 report says on its own second page that it is a document of the borrower
Sources carrying this claim
clm-08db56c8dd874b06
descriptive
No independent measurement was found
Sources carrying this claim
clm-9c8ebd4b77a067f2
quantitative
in October 2025 DWASA formed an internal committee to determine its actual water production and system loss and to replace faulty meters at its own pumps
Sources carrying this claim
clm-902f96c7e8304949
quantitative
quoting the number from inside its rebuilt areas, the utility can report a single-digit loss rate while its own operations chief puts the rate outside them above 40%
Sources carrying this claim
clm-fe2807df58b086f9
quantitative
three government sources in 2026 put groundwater at 66%, 70% and 77% of production
Sources carrying this claim
clm-516d97bebbc90eca
descriptive
the water table under Dhaka is falling by two to three metres a year
Sources carrying this claim
clm-87fefa44a991b8b4
quantitative
the emergency project the government approved in 2026 to replace, regenerate and add deep tube wells carries 124 more SCADA systems with it
Sources carrying this claim
Forensic record — source dossiers, gaps, hashes and the exact revision this page renders
This layer records what is known about each source, what is still missing, and the exact snapshot this page is rendering. A missing date, archive or hash stays visible as missing.
Awaiting operator and domain-expert review; publication of this revision implies neither.
sha256:fd128ebe1d80c83128b478127267bc5f84492616697f274a5f163f45fe2dc7c9
- 19
- of 19 claims mapped
- 10
- source dossiers
- 5
- publication dates recorded
- 0
- archives linked
- 0
- exact locators
- 0
- content captures hashed
Governance facts carried by the record
- Operator
- Dhaka Water Supply and Sewerage Authority (DWASA)
- Actor types
- utility
- Funding model
- mixed
- Funding description
- ADB loans (US$150M and US$275M) with Government of Bangladesh counterpart funding
- Cost
- ~US$212M (ADB Loan 2382-BAN) and ~US$408M (Loan 3397-BAN), total project costs
- Ownership
- Not recorded
- Decision rights
- Not recorded
- Exit conditions
- Not recorded
10 source dossiers
ADB - Dhaka Water Supply Network Improvement Project, project data sheet (financier)
- Stable source ID
src-4abf857d380c7de6- Publisher
- Name not classified · adb.org
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- 2026-04-24
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-26
- Dossier created
- 2026-08-26
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Loan 3397-BAN, approved 24 June 2016, still active; total project cost US$408M of which ADB US$275M and government counterpart US$133M. Carries the DMA approach across 7 of DWASA's 10 zones, the output statement 'SCADA system implemented in all DMAs and AMR implemented', and non-revenue water in the handed-over DMAs 'measured at a range between 1.6% 5.8% (target: 10.0%)'. Blocks WebFetch (403); read with a browser user-agent.
DWASA for ADB - 15th Semi-Annual Social Safeguards Monitoring Report, DWSNIP (July 2025)
- Stable source ID
src-a489f4d063deab96- Publisher
- Name not classified · adb.org
- Type / language
- pdf · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-26
- Dossier created
- 2026-08-26
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Semestral report for January-June 2025, cover-dated July 2025, prepared by DWASA for ADB. Carries physical losses in commissioned DMAs 'from 40% to less than 10% with the current average of 3.44%', overall physical losses and non-revenue water 'still estimated to be about 26%', the 85 DMAs of DWSNIP and 1,833 km of HDPE pipe laid to 30 June 2025 - and the disclaimer that the report 'is a document of the borrower'.
ADB - Dhaka Water Supply Sector Development Program, project data sheet (financier)
- Stable source ID
src-43ef3e3f0836c597- Publisher
- Name not classified · adb.org
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- 2019-09-18
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-26
- Dossier created
- 2026-08-26
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Loan 2382-BAN, approved 10 December 2007 and closed 22 January 2020; project cost US$212M of which ADB US$150M. Records 47 DMAs rehabilitated over 2,456 km of distribution network and 106,662 house connections, and non-revenue water 'brought down from a high level of more than 50% before the project to less than 10% in most of the completed DMAs'. Blocks WebFetch (403); read with a browser user-agent.
- Claims linked
Dhaka WASA - Annual Report 2020-21 (operator)
- Stable source ID
src-d78622895fd7a0d8- Publisher
- Name not classified · objectstorage.ap-dcc-gazipur-1.oraclecloud15.com
- Type / language
- pdf · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-26
- Dossier created
- 2026-08-26
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
DWASA's own annual report, cover title 'Vision to Turn Around: Go Green and Go Digital - Annual Report 2020-21'. Signed by managing director Taqsem A. Khan. Gives the 145-DMA plan, 70 completed DMAs in the foreword and 71 in the body, non-revenue water inside DMAs at under 4%, 5% and 7% in three separate passages, the SCADA statement, and the Water ATM programme. The copy on dwasa.portal.gov.bd serves a self-signed certificate and returns 503 to automated readers; this government object-storage copy of the same document is readable.
The Business Standard - Wasa suffers water bill loss, consumers made to pay (press)
- Stable source ID
src-2c6b1ee055f229d5- Publisher
- Name not classified · tbsnews.net
- Type / language
- web-page · language not classified
- Published
- 2024-04-26
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-26
- Dossier created
- 2026-08-26
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Carries deputy managing director (operation and management) AKM Shahid Uddin on 22% overall system loss, 113 of a planned 156 DMAs completed, below 5% inside DMAs and above 40% in the 43 areas without them; also reports the paper's own review of DWASA audit and annual reports FY15-FY23.
Dhaka Tribune - Wasa forms body to assess water production, system loss (press)
- Stable source ID
src-0a0e9820a8d41d9e- Publisher
- Name not classified · dhakatribune.com
- Type / language
- web-page · language not classified
- Published
- Not recorded
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-26
- Dossier created
- 2026-08-26
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Reports that DWASA formed a committee under chief engineer Abdus Salam Bepary to determine actual water production and system loss, visiting pumps to examine meter installations and replace faulty meters, reporting to the managing director within 30 working days. The host returns 403 to every automated reader tried, including a Wayback replay; existence and content confirmed through search results only, so no publication date is recorded here.
- Claims linked
United News of Bangladesh - DMA helping Dhaka Wasa curb system loss (press)
- Stable source ID
src-06fd15fc60d98064- Publisher
- Name not classified · unb.com.bd
- Type / language
- web-page · language not classified
- Published
- 2019-10-24
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-26
- Dossier created
- 2026-08-26
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
The earliest of the DMA counts used here: 'The government initially decided to introduce 164 DMAs. Of them, the process to introduce 62 DMAs has been completed', with overall system loss then at 20 percent, all attributed to an official document.
- Claims linked
The Daily Star - Dhaka Wasa turns to groundwater despite unfinished projects (press)
- Stable source ID
src-44a7076fef9b34a4- Publisher
- Name not classified · thedailystar.net
- Type / language
- web-page · language not classified
- Published
- 2026-04-06
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-26
- Dossier created
- 2026-08-26
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
The Tk 920.85 crore Emergency Water Supply in Dhaka City project as it went to Ecnec: 'A SCADA system will be introduced for real-time monitoring.' Also project focal person Abdul Majid on demand of about 320 crore litres a day 'with 70 percent currently supplied from deep tube wells', former Wasa chairman Ghulam Mostafa on a water table 'falling by about one metre each year', and Gandharbpur Phase 1 about 50% and Saidabad Phase 3 about 20% complete.
Bangladesh Sangbad Sangstha - Govt launches Tk 920.85cr emergency water supply project in Dhaka (state news agency)
- Stable source ID
src-4d4b9f66fc60a9cc- Publisher
- Name not classified · bssnews.net
- Type / language
- web-page · language not classified
- Published
- 2026-05-11
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-26
- Dossier created
- 2026-08-26
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
State news agency on the same project after approval: 'This project has already got approval by the Executive Committee of the National Economic Council (ECNEC) in its last meeting', 450 pump motor sets, 450 variable frequency drives and 124 SCADA systems, 388 deep tube wells replaced, 280 regenerated and 60 rehabilitated over 361 square kilometres of DNCC and DSCC. Gives DWASA production of about 2,977 MLD and groundwater at 66 percent of total water production against 34 percent surface water.
- Claims linked
The Daily Star - Tk 32,554cr plan for Dhaka's water future (press)
- Stable source ID
src-1050dfc21b05c6a4- Publisher
- Name not classified · thedailystar.net
- Type / language
- web-page · language not classified
- Published
- 2026-07-24
- Updated
- Not recorded
- Source last checked
- No source-level check date
- Record last verified
- 2026-08-26
- Dossier created
- 2026-08-26
- Retrieved copy
- No local capture recorded
- Archive
- No archived copy linked
- Content hash
- No captured content hash
- Locator
- Descriptive only — not page/paragraph exact
Open the recorded source note
Institute of Water Modelling report presented to Ecnec: Dhaka needs about 3.13 billion litres a day against DWASA production of about 3.0 billion, and 'Nearly 77 percent of the city's water comes from 1,388 deep tube wells, causing groundwater levels to fall by 2-3 metres a year.'
- Claims linked
Known limits of this passport
- Publisher names and source languages have not yet been classified; domains are recorded without guessing.
- Existing source notes are descriptive locators, not page- or paragraph-exact citations.
- A missing archive, publication date or content hash is shown as null rather than inferred.
- The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim.
Continue exploring
Compare this project
Explore the wider context
📎 Cite this project
1001 Smart Cities (2026). “Dhaka WASA District Metered Areas and SCADA” — Dhaka, Bangladesh. The Smart City Atlas. https://1001smartcities.org/projects/dhaka-wasa-dma-network/ (last verified 2026-08-26). Data: CC BY 4.0.
The underlying data is free to reuse with attribution — see the open data page.