 "entity": {
  "type": "project",
  "id": "santiago-smart-meters-suspended",
  "title": "Santiago's Suspended Smart Electricity Meter Rollout",
  "canonicalUrl": "https://1001smartcities.org/projects/santiago-smart-meters-suspended/"
 },
 "currentRevisionId": "2026-08-21-source-dates",
 "revisions": [
  {
   "id": "2026-08-20-claim-baseline",
   "createdAt": "2026-08-21T11:05:00Z",
   "effectiveAt": "2026-07-26",
   "changeType": "baseline",
   "summary": "Created the first structured Evidence Passport with 12 claims and 11 source dossiers.",
   "preparedBy": {
    "type": "automation",
    "label": "AI-assisted evidence preparation",
    "humanApproved": false
   },
   "review": {
    "status": "unreviewed",
    "by": null,
    "date": null,
    "note": "Awaiting operator and domain-expert review; publication of this revision implies neither."
   },
   "changes": [
    {
     "operation": "add",
     "path": "/evidencePassport",
     "summary": "Added claim-level evidence mapping and source dossiers."
    },
    {
     "operation": "add",
     "path": "/revisionHistory",
     "summary": "Established a permanent, hash-addressed baseline revision."
    }
   ],
   "snapshotHash": "sha256:5494ed3872f4465dce04aa4615cbd3a92fe142c848da3bf19a3a29fe42f9740d",
   "snapshot": {
    "asOf": "2026-07-26",
    "projectFingerprint": "sha256:7c7b1caefd0f73fc119910fbc2c418e9e3c31eccfe171c873d7e436fdd71dfe6",
    "assurance": {
     "status": "unreviewed",
     "scope": "evidence-passport-revision",
     "statement": "AI-assisted structural preparation. This revision has not been reviewed by a human or subject-matter expert.",
     "machineChecks": [
      "schema",
      "publication-diff-contract",
      "material-project-fingerprint",
      "claim-text-drift",
      "source-reference-resolution",
      "complete-source-dossier",
      "snapshot-hash"
     ]
    },
    "projectState": {
     "status": "suspended",
     "outcome": "failed",
     "evidenceGrade": "media",
     "timeline": {
      "started": 2018,
      "ended": null
     }
    },
    "governance": {
     "operator": "Enel Distribucion Chile (private distribution concession), under Comision Nacional de Energia rules and SEC supervision",
     "actorTypes": [
      "utility"
     ],
     "fundingModel": "utility",
     "fundingDescription": "Enel Distribucion, recovered through the regulated distribution tariff until the charge was suspended in April 2019",
     "cost": "about US$1,000M projected nationwide (2019); about US$3,000M current government estimate for a restart",
     "ownership": null,
     "decisionRights": null,
     "exitConditions": null
    },
    "claims": [
     {
      "id": "clm-d280e239a3a6a0f0",
      "field": "snippet",
      "text": "A technical standard issued by the Comision Nacional de Energia in December 2017 obliged distributors to replace every household meter with a remotely read device, reaching full coverage by 2025",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-0ae079a48d3e9c19"
      ],
      "supportNote": "The regulator's own register anchors the obligation to the Norma Tecnica de Calidad de Servicio para Sistemas de Distribucion of 18 December 2017 — systems of measurement, monitoring and control, with 100 per cent coverage by 2025 — and records its later replacement by CNE Resolucion Exenta 209/210 of 3 May 2024, which rebuilt the framework after the collapse.",
      "caveat": null,
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-73924918b73334db",
      "field": "snippet",
      "text": "Ley 21.076, published in February 2018, had already transferred ownership of meters and connections from customers to the distributors",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-a5bc236c738ae1de"
      ],
      "supportNote": "The instrument itself, published in the Diario Oficial on 19 February 2018, transferred ownership of meters and connections to the distribution company.",
      "caveat": "This is the pivot of the whole episode and runs opposite to the usual direction of such reforms — the entry cites it for the legal fact alone.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-acd6258727850f0e",
      "field": "snippet",
      "text": "CIPER reported in March 2019 that more than 250,000 meters were already installed in Santiago and that the national bill would reach about US$1,000 million",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-e92be6d725449bdd"
      ],
      "supportNote": "The investigative report of 1 March 2019 that set off the backlash is the sole source for the Santiago-specific figure of more than 250,000 meters already installed by the distributor, and for the US$1,000 million national total over a seven-year horizon to 2025.",
      "caveat": "The distributor's own page carries an undated 'over 200,000 installed' figure that conflicts with this dated one; the undated figure was dropped rather than reconciled, and that page returned an error on repeated attempts.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-228f04b75f998f5c",
      "field": "snippet",
      "text": "On 29 April 2019 the energy minister made replacement voluntary and ordered distributors to refund what they had charged",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-59e58458b21e0aa9"
      ],
      "supportNote": "The primary ministry source dates the suspension to 29 April 2019 and names Minister Susana Jimenez, establishing that a ministerial decision — not a court and not the Contraloria — stopped the mandatory rollout, that charges were suspended and refunded in full, and that installation would continue only on express customer request.",
      "caveat": "The release carries no figures on meters installed or amounts refunded.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-5bea2d49985cda1e",
      "field": "snippet",
      "text": "In October 2020 the Supreme Court ruled that refund unlawful, holding that a tariff decree cannot be rewritten by administrative act",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-fe58b3d2082051f1"
      ],
      "supportNote": "Reported 30 October 2020: the court struck down the refund, not the meters — a tariff decree can only be changed by unanimous agreement between the companies and the regulator plus a new decree. Third Chamber, rol 50.520-2020, on the regulator's Oficio 15.699 of July 2019.",
      "caveat": "The same report records an ambiguity over whether the ruling binds only the claimant, an electricity cooperative, rather than the sector as a whole.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-cea284d0e837d077",
      "field": "snippet",
      "text": "A bill obliging distributors to install meters at their own cost cleared a Chamber committee in January 2026",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-4920f13e93a5d8cf"
      ],
      "supportNote": "On 26 January 2026 the Chamber's Mining and Energy Commission unanimously approved a bill — motion Boletin 17.850-08, filed September 2025 — obliging distributors to install remote meters at no cost to final customers, with a government cost estimate of about US$3,000 million.",
      "caveat": "A committee stage, not a law. It is why the entry's status is suspended with no end year.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-550f1a8e3741787e",
      "field": "impact",
      "text": "The Comision Nacional de Energia set a regulated unit price of US$132, about CLP 87,500, per meter, and CIPER put the national programme at about US$1,000 million over seven years",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-e92be6d725449bdd"
      ],
      "supportNote": "The report carries the regulator's unit price of US$132 (CLP 87,500), the US$1,000 million national total, the seven-year horizon to 2025, the roughly 6 million devices, and the fact that the meters would be the distributor's property while customers paid through tariffs from September 2018.",
      "caveat": null,
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-fd6f65ef48b3420f",
      "field": "impact",
      "text": "A Senate committee was told in March 2019 that the surcharge would stay under 1% of a bill, roughly CLP 200 to 300 per billing cycle (Senado de Chile)",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-b79ea60c7875e2a3"
      ],
      "supportNote": "The institutional record of the March 2019 session supports the per-household surcharge of roughly CLP 200 to 300 per billing cycle and under 1 per cent of a bill, the seven-year replacement horizon for over 6 million meters, and preliminary installations in the Metropolitan Region. It also records a senator's statement that legislators had been told there would be no tariff effect at all.",
      "caveat": null,
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-1ec35900ac9bffa7",
      "field": "impact",
      "text": "Enel's own estimate of the refund owed was about CLP 1,000 per average residential customer, covering September 2018 to July 2019 and credited from 1 September 2019",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-44b4aad3e4b141c2"
      ],
      "supportNote": "The operator's figure was carried at headline level by four outlets in the first days of August 2019 for the period September 2018 to July 2019, credited from 1 September 2019.",
      "caveat": "Operator-reported, hence the media evidence grade, and not fetched directly. A more precise figure of about CLP 961 plus interest appears in the same reporting but could not be confirmed sentence-level, so the entry uses the rounded CLP 1,000 that four outlets state outright.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-22bb569d34aaf5d0",
      "field": "impact",
      "text": "Sector sources put the industry-wide refund at about US$350 million (La Tercera, October 2020)",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-fe58b3d2082051f1"
      ],
      "supportNote": "The October 2020 report carries the roughly US$350 million sector estimate alongside the ruling that struck the refund down.",
      "caveat": "A sector estimate relayed by the press, not an audited figure.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-505a35c83ceaa938",
      "field": "impact",
      "text": "The 2025 full-coverage target passed unmet; the government's current estimate for a restart is about US$3,000 million",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-32dfe0f3f471266e",
       "src-4920f13e93a5d8cf"
      ],
      "supportNote": "The March 2024 commentary confirms the programme never restarted — the 2018 attempt failed once costs were passed to consumers, and nearly six years on there had been no significant progress, leaving Chile behind Mexico, Brazil, Peru and Colombia. The January 2026 committee report carries the government's cost estimate of about US$3,000 million for the bill that would restart it.",
      "caveat": null,
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-3de7b58266572424",
      "field": "lesson",
      "text": "Chile lost seven years of metering on a question of ownership rather than one of technology or price, and is still legislating a way back",
      "statementKind": "descriptive",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-a5bc236c738ae1de",
       "src-32dfe0f3f471266e",
       "src-4920f13e93a5d8cf"
      ],
      "supportNote": "The 2018 law moved ownership of the meter to the distributor; the 2024 commentary records that nothing significant happened in the six years after the rollout stopped; and in January 2026 a committee was still approving a bill to restart it on different terms.",
      "caveat": "The attribution of the failure to ownership rather than price is the entry's own reading. A peer-reviewed account of the episode exists but returned an error and could not be read, so it supports nothing here; its abstract links the crisis to the October 2019 social outburst, and that link is deliberately kept out of the entry until the paper can be read directly.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     }
    ],
    "sources": [
     {
      "id": "src-59e58458b21e0aa9",
      "title": "Ministerio de Energia — minister confirms voluntary replacement and refunds",
      "url": "https://energia.gob.cl/noticias/nacional/ministra-de-energia-confirma-la-voluntariedad-para-recambio-de-los-medidores-inteligentes-y-anuncia-que-las-distribuidoras-electricas-devolveran-los-dineros-cobrados",
      "publisher": {
       "name": null,
       "domain": "energia.gob.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-228f04b75f998f5c"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Primary. Dates the suspension to 29 April 2019 and names Minister Susana Jimenez; establishes that a ministerial decision, not a court or the Contraloria, stopped the mandatory rollout, that charges were suspended and refunded in full, and that installation would continue only on express customer request. Carries no figures on meters installed or amounts refunded.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-e92be6d725449bdd",
      "title": "CIPER Chile — new smart meters: the US$1,000 million cost falls on customers",
      "url": "https://www.ciperchile.cl/2019/03/01/instalaran-nuevos-medidores-inteligentes-de-electricidad-el-costo-de-us1-000-millones-sera-asumido-por-clientes/",
      "publisher": {
       "name": null,
       "domain": "ciperchile.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-acd6258727850f0e",
       "clm-550f1a8e3741787e"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Investigative report of 1 March 2019 that set off the backlash. Sole source for the Santiago-specific figure of more than 250,000 meters already installed by Enel Distribucion, and for the CNE unit price of US$132 (CLP 87,500), the US$1,000 million national total, the seven-year horizon to 2025, the ~6 million devices, and the fact that meters would be the distributor's property while customers paid through tariffs from September 2018.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-a5bc236c738ae1de",
      "title": "Ley 21.076 — Biblioteca del Congreso Nacional",
      "url": "https://www.bcn.cl/leychile/navegar?idNorma=1115627",
      "publisher": {
       "name": null,
       "domain": "bcn.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-73924918b73334db",
       "clm-3de7b58266572424"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "The instrument itself. Published in the Diario Oficial on 19 February 2018; transferred ownership of meters and connections to the distribution company. Cited for the legal fact of the ownership transfer, which is the pivot of the whole episode and runs opposite to the usual direction of such reforms.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-0ae079a48d3e9c19",
      "title": "Comision Nacional de Energia — technical standards register",
      "url": "https://www.cne.cl/en/normativas/electrica/normas-tecnicas/",
      "publisher": {
       "name": null,
       "domain": "cne.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-d280e239a3a6a0f0"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Regulator's own register. Anchors the obligation to the Norma Tecnica de Calidad de Servicio para Sistemas de Distribucion of 18 December 2017 (systems of measurement, monitoring and control; 100% coverage by 2025) and its later replacement by CNE Resolucion Exenta 209/210 of 3 May 2024, which rebuilt the framework after the collapse.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-b79ea60c7875e2a3",
      "title": "Senado de Chile — committee session on smart meter charges",
      "url": "https://www.senado.cl/comunicaciones/noticias/cobro-de-medidores-inteligentes-empresas-distribuidoras-pagaran-pero-la",
      "publisher": {
       "name": null,
       "domain": "senado.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-fd6f65ef48b3420f"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Institutional record, March 2019. Supports the per-household surcharge of roughly CLP 200 to 300 per billing cycle and under 1% of a bill, the seven-year replacement horizon for over 6 million meters, and preliminary installations in the Metropolitan Region. Also records Senator Letelier's statement that legislators had been told there would be no tariff effect.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-fe58b3d2082051f1",
      "title": "La Tercera / Pulso — Supreme Court declares the refund unlawful",
      "url": "https://www.latercera.com/pulso/noticia/suprema-declara-ilegal-devolucion-de-pagos-por-medidores-inteligentes/VO4M437FEVBI5OWSAGM6Q2PLJY/",
      "publisher": {
       "name": null,
       "domain": "latercera.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-5bea2d49985cda1e",
       "clm-22bb569d34aaf5d0"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Reported 30 October 2020. Establishes that the court struck down the refund, not the meters: a tariff decree can only be changed by unanimous agreement between companies and the CNE plus a new decree. Source for the ~US$350 million sector estimate and for the ambiguity over whether the ruling binds only the claimant, Cooperativa Regional Electrica Llanquihue (Third Chamber, rol 50.520-2020, on SEC Oficio 15.699 of July 2019).",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-44b4aad3e4b141c2",
      "title": "T13 — Enel estimates the refund at about CLP 1,000 per customer",
      "url": "https://www.t13.cl/noticia/negocios/nacional/enel-estima-devolucion-del-cobro-medidores-inteligentes-sera-1.000-cliente",
      "publisher": {
       "name": null,
       "domain": "t13.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-1ec35900ac9bffa7"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "NOT fetched directly; verified through search results, where La Tercera, CNN Chile and BioBioChile carry the same Enel figure at headline level (1-2 August 2019). Operator-reported, hence the media evidence grade. A more precise figure of about CLP 961 plus interest, for September 2018 to July 2019 credited from 1 September 2019, appears in the same reporting but could not be confirmed sentence-level, so the entry uses the rounded CLP 1,000 that four outlets state outright.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-32dfe0f3f471266e",
      "title": "El Mostrador — smart meters and Chile's electrical modernisation",
      "url": "https://www.elmostrador.cl/agenda-pais/agenda-sustentable/2024/03/11/medidores-inteligentes-y-a-la-modernizacion-electrica-de-chile/",
      "publisher": {
       "name": null,
       "domain": "elmostrador.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-505a35c83ceaa938",
       "clm-3de7b58266572424"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Commentary of 11 March 2024 confirming the programme never restarted: the 2018 attempt failed once costs were passed to consumers, and nearly six years on there has been no significant progress, leaving Chile behind Mexico, Brazil, Peru and Colombia. The basis for the failed outcome grade.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-4920f13e93a5d8cf",
      "title": "BioBioChile — Chamber commission backs free smart meter replacement",
      "url": "https://www.biobiochile.cl/noticias/economia/actualidad-economica/2026/01/26/legislaran-idea-de-cambiar-los-medidores-de-la-luz-a-unos-inteligentes-sin-costo-para-los-clientes.shtml",
      "publisher": {
       "name": null,
       "domain": "biobiochile.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-cea284d0e837d077",
       "clm-505a35c83ceaa938",
       "clm-3de7b58266572424"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. 26 January 2026, the currency check. The Chamber's Mining and Energy Commission unanimously approved a bill (motion Boletin 17.850-08, filed September 2025) obliging distributors to install remote meters at no cost to final customers, with a government cost estimate of about US$3,000 million. Confirms the matter is unresolved rather than closed, which is why status is suspended and yearEnd null.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-f9ebb901601f08fc",
      "title": "Vasquez et al., 'The Erratic Implementation of Measuring, Monitoring and Control System (MMCS) in Chile: The crisis on smart meters', Energy Reports 6 (2020)",
      "url": "https://ui.adsabs.harvard.edu/abs/2020EnRep...6.2140V/abstract",
      "publisher": {
       "name": null,
       "domain": "ui.adsabs.harvard.edu",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "background",
      "claimRefs": [],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Peer-reviewed academic account of the episode. ScienceDirect returned HTTP 403 and the ADS record rendered empty, so it could not be read sentence-level and supports nothing in the snippet or impact. Recorded here because its abstract, as surfaced in search, describes the crisis as one contributing element of the October 2019 social outburst and states that the pre-Decreto 5T position was restored in fact rather than by legislative act. That estallido link is deliberately kept out of the entry text until the paper can be read directly.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-c08dd0e5454a8b8a",
      "title": "Enel Distribucion — smart meter replacement process",
      "url": "https://www.eneldistribucion.cl/proceso-cambio-medidores-inteligentes",
      "publisher": {
       "name": null,
       "domain": "eneldistribucion.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "background",
      "claimRefs": [],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-21",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Operator page. Returned HTTP 503 on repeated attempts and is NOT relied upon. Search-surfaced text from it gives an undated 'over 200,000 installed' figure that conflicts with CIPER's dated 250,000; the undated figure was dropped rather than reconciled.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     }
    ],
    "coverage": {
     "claimsTotal": 12,
     "claimsMapped": 12,
     "sourcesTotal": 11,
     "sourcesUsedByClaims": 9,
     "sourcesWithPublicationDate": 0,
     "sourcesWithArchive": 0,
     "sourcesWithExactLocator": 0,
     "sourcesWithContentHash": 0
    },
    "limits": [
     "Publisher names and source languages have not yet been classified; domains are recorded without guessing.",
     "Existing source notes are descriptive locators, not page- or paragraph-exact citations.",
     "A missing archive, publication date or content hash is shown as null rather than inferred.",
     "The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim."
    ]
   }
  },
  {
   "id": "2026-08-21-source-dates",
   "createdAt": "2026-08-22T02:34:00Z",
   "effectiveAt": "2026-07-26",
   "changeType": "update",
   "summary": "Record the publication date of each source that states one; a source that publishes no date is marked null, and one that shows only a revision carries `updated` instead.",
   "preparedBy": {
    "type": "automation",
    "label": "AI-assisted evidence preparation",
    "humanApproved": false
   },
   "review": {
    "status": "unreviewed",
    "by": null,
    "date": null,
    "note": "Awaiting operator and domain-expert review; publication of this revision implies neither."
   },
   "changes": [
    {
     "operation": "replace",
     "path": "/snapshot/projectFingerprint",
     "summary": "Updated projectFingerprint to the current sourced project record."
    },
    {
     "operation": "replace",
     "path": "/snapshot/sources",
     "summary": "Updated sources to the current sourced project record."
    }
   ],
   "snapshotHash": "sha256:69bcbd74276945e227da8ef0d309b2d9bc0a1456a3489732396a9a92f97c370c",
   "snapshot": {
    "asOf": "2026-07-26",
    "projectFingerprint": "sha256:cc653365a154d0d8bea7df27b6fddcfda5ed154c87a8dd64fa5b5e202047f3d5",
    "assurance": {
     "status": "unreviewed",
     "scope": "evidence-passport-revision",
     "statement": "AI-assisted structural preparation. This revision has not been reviewed by a human or subject-matter expert.",
     "machineChecks": [
      "schema",
      "publication-diff-contract",
      "material-project-fingerprint",
      "claim-text-drift",
      "source-reference-resolution",
      "complete-source-dossier",
      "snapshot-hash"
     ]
    },
    "projectState": {
     "status": "suspended",
     "outcome": "failed",
     "evidenceGrade": "media",
     "timeline": {
      "started": 2018,
      "ended": null
     }
    },
    "governance": {
     "operator": "Enel Distribucion Chile (private distribution concession), under Comision Nacional de Energia rules and SEC supervision",
     "actorTypes": [
      "utility"
     ],
     "fundingModel": "utility",
     "fundingDescription": "Enel Distribucion, recovered through the regulated distribution tariff until the charge was suspended in April 2019",
     "cost": "about US$1,000M projected nationwide (2019); about US$3,000M current government estimate for a restart",
     "ownership": null,
     "decisionRights": null,
     "exitConditions": null
    },
    "claims": [
     {
      "id": "clm-d280e239a3a6a0f0",
      "field": "snippet",
      "text": "A technical standard issued by the Comision Nacional de Energia in December 2017 obliged distributors to replace every household meter with a remotely read device, reaching full coverage by 2025",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-0ae079a48d3e9c19"
      ],
      "supportNote": "The regulator's own register anchors the obligation to the Norma Tecnica de Calidad de Servicio para Sistemas de Distribucion of 18 December 2017 — systems of measurement, monitoring and control, with 100 per cent coverage by 2025 — and records its later replacement by CNE Resolucion Exenta 209/210 of 3 May 2024, which rebuilt the framework after the collapse.",
      "caveat": null,
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-73924918b73334db",
      "field": "snippet",
      "text": "Ley 21.076, published in February 2018, had already transferred ownership of meters and connections from customers to the distributors",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-a5bc236c738ae1de"
      ],
      "supportNote": "The instrument itself, published in the Diario Oficial on 19 February 2018, transferred ownership of meters and connections to the distribution company.",
      "caveat": "This is the pivot of the whole episode and runs opposite to the usual direction of such reforms — the entry cites it for the legal fact alone.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-acd6258727850f0e",
      "field": "snippet",
      "text": "CIPER reported in March 2019 that more than 250,000 meters were already installed in Santiago and that the national bill would reach about US$1,000 million",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-e92be6d725449bdd"
      ],
      "supportNote": "The investigative report of 1 March 2019 that set off the backlash is the sole source for the Santiago-specific figure of more than 250,000 meters already installed by the distributor, and for the US$1,000 million national total over a seven-year horizon to 2025.",
      "caveat": "The distributor's own page carries an undated 'over 200,000 installed' figure that conflicts with this dated one; the undated figure was dropped rather than reconciled, and that page returned an error on repeated attempts.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-228f04b75f998f5c",
      "field": "snippet",
      "text": "On 29 April 2019 the energy minister made replacement voluntary and ordered distributors to refund what they had charged",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-59e58458b21e0aa9"
      ],
      "supportNote": "The primary ministry source dates the suspension to 29 April 2019 and names Minister Susana Jimenez, establishing that a ministerial decision — not a court and not the Contraloria — stopped the mandatory rollout, that charges were suspended and refunded in full, and that installation would continue only on express customer request.",
      "caveat": "The release carries no figures on meters installed or amounts refunded.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-5bea2d49985cda1e",
      "field": "snippet",
      "text": "In October 2020 the Supreme Court ruled that refund unlawful, holding that a tariff decree cannot be rewritten by administrative act",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-fe58b3d2082051f1"
      ],
      "supportNote": "Reported 30 October 2020: the court struck down the refund, not the meters — a tariff decree can only be changed by unanimous agreement between the companies and the regulator plus a new decree. Third Chamber, rol 50.520-2020, on the regulator's Oficio 15.699 of July 2019.",
      "caveat": "The same report records an ambiguity over whether the ruling binds only the claimant, an electricity cooperative, rather than the sector as a whole.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-cea284d0e837d077",
      "field": "snippet",
      "text": "A bill obliging distributors to install meters at their own cost cleared a Chamber committee in January 2026",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-4920f13e93a5d8cf"
      ],
      "supportNote": "On 26 January 2026 the Chamber's Mining and Energy Commission unanimously approved a bill — motion Boletin 17.850-08, filed September 2025 — obliging distributors to install remote meters at no cost to final customers, with a government cost estimate of about US$3,000 million.",
      "caveat": "A committee stage, not a law. It is why the entry's status is suspended with no end year.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-550f1a8e3741787e",
      "field": "impact",
      "text": "The Comision Nacional de Energia set a regulated unit price of US$132, about CLP 87,500, per meter, and CIPER put the national programme at about US$1,000 million over seven years",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-e92be6d725449bdd"
      ],
      "supportNote": "The report carries the regulator's unit price of US$132 (CLP 87,500), the US$1,000 million national total, the seven-year horizon to 2025, the roughly 6 million devices, and the fact that the meters would be the distributor's property while customers paid through tariffs from September 2018.",
      "caveat": null,
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-fd6f65ef48b3420f",
      "field": "impact",
      "text": "A Senate committee was told in March 2019 that the surcharge would stay under 1% of a bill, roughly CLP 200 to 300 per billing cycle (Senado de Chile)",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-b79ea60c7875e2a3"
      ],
      "supportNote": "The institutional record of the March 2019 session supports the per-household surcharge of roughly CLP 200 to 300 per billing cycle and under 1 per cent of a bill, the seven-year replacement horizon for over 6 million meters, and preliminary installations in the Metropolitan Region. It also records a senator's statement that legislators had been told there would be no tariff effect at all.",
      "caveat": null,
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-1ec35900ac9bffa7",
      "field": "impact",
      "text": "Enel's own estimate of the refund owed was about CLP 1,000 per average residential customer, covering September 2018 to July 2019 and credited from 1 September 2019",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-44b4aad3e4b141c2"
      ],
      "supportNote": "The operator's figure was carried at headline level by four outlets in the first days of August 2019 for the period September 2018 to July 2019, credited from 1 September 2019.",
      "caveat": "Operator-reported, hence the media evidence grade, and not fetched directly. A more precise figure of about CLP 961 plus interest appears in the same reporting but could not be confirmed sentence-level, so the entry uses the rounded CLP 1,000 that four outlets state outright.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-22bb569d34aaf5d0",
      "field": "impact",
      "text": "Sector sources put the industry-wide refund at about US$350 million (La Tercera, October 2020)",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-fe58b3d2082051f1"
      ],
      "supportNote": "The October 2020 report carries the roughly US$350 million sector estimate alongside the ruling that struck the refund down.",
      "caveat": "A sector estimate relayed by the press, not an audited figure.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-505a35c83ceaa938",
      "field": "impact",
      "text": "The 2025 full-coverage target passed unmet; the government's current estimate for a restart is about US$3,000 million",
      "statementKind": "quantitative",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-32dfe0f3f471266e",
       "src-4920f13e93a5d8cf"
      ],
      "supportNote": "The March 2024 commentary confirms the programme never restarted — the 2018 attempt failed once costs were passed to consumers, and nearly six years on there had been no significant progress, leaving Chile behind Mexico, Brazil, Peru and Colombia. The January 2026 committee report carries the government's cost estimate of about US$3,000 million for the bill that would restart it.",
      "caveat": null,
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     },
     {
      "id": "clm-3de7b58266572424",
      "field": "lesson",
      "text": "Chile lost seven years of metering on a question of ownership rather than one of technology or price, and is still legislating a way back",
      "statementKind": "descriptive",
      "textMode": "verbatim-from-project-record",
      "mappingStatus": "mapped",
      "sourceRefs": [
       "src-a5bc236c738ae1de",
       "src-32dfe0f3f471266e",
       "src-4920f13e93a5d8cf"
      ],
      "supportNote": "The 2018 law moved ownership of the meter to the distributor; the 2024 commentary records that nothing significant happened in the six years after the rollout stopped; and in January 2026 a committee was still approving a bill to restart it on different terms.",
      "caveat": "The attribution of the failure to ownership rather than price is the entry's own reading. A peer-reviewed account of the episode exists but returned an error and could not be read, so it supports nothing here; its abstract links the crisis to the October 2019 social outburst, and that link is deliberately kept out of the entry until the paper can be read directly.",
      "interpretation": {
       "added": false,
       "interpolation": false,
       "note": "The passport copies the published claim and its recorded source mapping without adding a conclusion."
      }
     }
    ],
    "sources": [
     {
      "id": "src-59e58458b21e0aa9",
      "title": "Ministerio de Energia — minister confirms voluntary replacement and refunds",
      "url": "https://energia.gob.cl/noticias/nacional/ministra-de-energia-confirma-la-voluntariedad-para-recambio-de-los-medidores-inteligentes-y-anuncia-que-las-distribuidoras-electricas-devolveran-los-dineros-cobrados",
      "publisher": {
       "name": null,
       "domain": "energia.gob.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-228f04b75f998f5c"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Primary. Dates the suspension to 29 April 2019 and names Minister Susana Jimenez; establishes that a ministerial decision, not a court or the Contraloria, stopped the mandatory rollout, that charges were suspended and refunded in full, and that installation would continue only on express customer request. Carries no figures on meters installed or amounts refunded.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-e92be6d725449bdd",
      "title": "CIPER Chile — new smart meters: the US$1,000 million cost falls on customers",
      "url": "https://www.ciperchile.cl/2019/03/01/instalaran-nuevos-medidores-inteligentes-de-electricidad-el-costo-de-us1-000-millones-sera-asumido-por-clientes/",
      "publisher": {
       "name": null,
       "domain": "ciperchile.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-acd6258727850f0e",
       "clm-550f1a8e3741787e"
      ],
      "temporal": {
       "publishedAt": "2019-03-01",
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "publication-and-record-dates-recorded"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Investigative report of 1 March 2019 that set off the backlash. Sole source for the Santiago-specific figure of more than 250,000 meters already installed by Enel Distribucion, and for the CNE unit price of US$132 (CLP 87,500), the US$1,000 million national total, the seven-year horizon to 2025, the ~6 million devices, and the fact that meters would be the distributor's property while customers paid through tariffs from September 2018.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-a5bc236c738ae1de",
      "title": "Ley 21.076 — Biblioteca del Congreso Nacional",
      "url": "https://www.bcn.cl/leychile/navegar?idNorma=1115627",
      "publisher": {
       "name": null,
       "domain": "bcn.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-73924918b73334db",
       "clm-3de7b58266572424"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "The instrument itself. Published in the Diario Oficial on 19 February 2018; transferred ownership of meters and connections to the distribution company. Cited for the legal fact of the ownership transfer, which is the pivot of the whole episode and runs opposite to the usual direction of such reforms.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-0ae079a48d3e9c19",
      "title": "Comision Nacional de Energia — technical standards register",
      "url": "https://www.cne.cl/en/normativas/electrica/normas-tecnicas/",
      "publisher": {
       "name": null,
       "domain": "cne.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-d280e239a3a6a0f0"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Regulator's own register. Anchors the obligation to the Norma Tecnica de Calidad de Servicio para Sistemas de Distribucion of 18 December 2017 (systems of measurement, monitoring and control; 100% coverage by 2025) and its later replacement by CNE Resolucion Exenta 209/210 of 3 May 2024, which rebuilt the framework after the collapse.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-b79ea60c7875e2a3",
      "title": "Senado de Chile — committee session on smart meter charges",
      "url": "https://www.senado.cl/comunicaciones/noticias/cobro-de-medidores-inteligentes-empresas-distribuidoras-pagaran-pero-la",
      "publisher": {
       "name": null,
       "domain": "senado.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-fd6f65ef48b3420f"
      ],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Institutional record, March 2019. Supports the per-household surcharge of roughly CLP 200 to 300 per billing cycle and under 1% of a bill, the seven-year replacement horizon for over 6 million meters, and preliminary installations in the Metropolitan Region. Also records Senator Letelier's statement that legislators had been told there would be no tariff effect.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-fe58b3d2082051f1",
      "title": "La Tercera / Pulso — Supreme Court declares the refund unlawful",
      "url": "https://www.latercera.com/pulso/noticia/suprema-declara-ilegal-devolucion-de-pagos-por-medidores-inteligentes/VO4M437FEVBI5OWSAGM6Q2PLJY/",
      "publisher": {
       "name": null,
       "domain": "latercera.com",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-5bea2d49985cda1e",
       "clm-22bb569d34aaf5d0"
      ],
      "temporal": {
       "publishedAt": "2020-10-30",
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "publication-and-record-dates-recorded"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Reported 30 October 2020. Establishes that the court struck down the refund, not the meters: a tariff decree can only be changed by unanimous agreement between companies and the CNE plus a new decree. Source for the ~US$350 million sector estimate and for the ambiguity over whether the ruling binds only the claimant, Cooperativa Regional Electrica Llanquihue (Third Chamber, rol 50.520-2020, on SEC Oficio 15.699 of July 2019).",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-44b4aad3e4b141c2",
      "title": "T13 — Enel estimates the refund at about CLP 1,000 per customer",
      "url": "https://www.t13.cl/noticia/negocios/nacional/enel-estima-devolucion-del-cobro-medidores-inteligentes-sera-1.000-cliente",
      "publisher": {
       "name": null,
       "domain": "t13.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-1ec35900ac9bffa7"
      ],
      "temporal": {
       "publishedAt": "2019-08-01",
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "publication-and-record-dates-recorded"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "NOT fetched directly; verified through search results, where La Tercera, CNN Chile and BioBioChile carry the same Enel figure at headline level (1-2 August 2019). Operator-reported, hence the media evidence grade. A more precise figure of about CLP 961 plus interest, for September 2018 to July 2019 credited from 1 September 2019, appears in the same reporting but could not be confirmed sentence-level, so the entry uses the rounded CLP 1,000 that four outlets state outright.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-32dfe0f3f471266e",
      "title": "El Mostrador — smart meters and Chile's electrical modernisation",
      "url": "https://www.elmostrador.cl/agenda-pais/agenda-sustentable/2024/03/11/medidores-inteligentes-y-a-la-modernizacion-electrica-de-chile/",
      "publisher": {
       "name": null,
       "domain": "elmostrador.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-505a35c83ceaa938",
       "clm-3de7b58266572424"
      ],
      "temporal": {
       "publishedAt": "2024-03-11",
       "updatedAt": "2024-03-12",
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "publication-and-record-dates-recorded"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. Commentary of 11 March 2024 confirming the programme never restarted: the 2018 attempt failed once costs were passed to consumers, and nearly six years on there has been no significant progress, leaving Chile behind Mexico, Brazil, Peru and Colombia. The basis for the failed outcome grade.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-4920f13e93a5d8cf",
      "title": "BioBioChile — Chamber commission backs free smart meter replacement",
      "url": "https://www.biobiochile.cl/noticias/economia/actualidad-economica/2026/01/26/legislaran-idea-de-cambiar-los-medidores-de-la-luz-a-unos-inteligentes-sin-costo-para-los-clientes.shtml",
      "publisher": {
       "name": null,
       "domain": "biobiochile.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "claim-evidence",
      "claimRefs": [
       "clm-cea284d0e837d077",
       "clm-505a35c83ceaa938",
       "clm-3de7b58266572424"
      ],
      "temporal": {
       "publishedAt": "2026-01-26",
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "publication-and-record-dates-recorded"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Fetched. 26 January 2026, the currency check. The Chamber's Mining and Energy Commission unanimously approved a bill (motion Boletin 17.850-08, filed September 2025) obliging distributors to install remote meters at no cost to final customers, with a government cost estimate of about US$3,000 million. Confirms the matter is unresolved rather than closed, which is why status is suspended and yearEnd null.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-f9ebb901601f08fc",
      "title": "Vasquez et al., 'The Erratic Implementation of Measuring, Monitoring and Control System (MMCS) in Chile: The crisis on smart meters', Energy Reports 6 (2020)",
      "url": "https://ui.adsabs.harvard.edu/abs/2020EnRep...6.2140V/abstract",
      "publisher": {
       "name": null,
       "domain": "ui.adsabs.harvard.edu",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "background",
      "claimRefs": [],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Peer-reviewed academic account of the episode. ScienceDirect returned HTTP 403 and the ADS record rendered empty, so it could not be read sentence-level and supports nothing in the snippet or impact. Recorded here because its abstract, as surfaced in search, describes the crisis as one contributing element of the October 2019 social outburst and states that the pre-Decreto 5T position was restored in fact rather than by legislative act. That estallido link is deliberately kept out of the entry text until the paper can be read directly.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     },
     {
      "id": "src-c08dd0e5454a8b8a",
      "title": "Enel Distribucion — smart meter replacement process",
      "url": "https://www.eneldistribucion.cl/proceso-cambio-medidores-inteligentes",
      "publisher": {
       "name": null,
       "domain": "eneldistribucion.cl",
       "classification": "not-classified"
      },
      "sourceType": "web-page",
      "language": "und",
      "role": "background",
      "claimRefs": [],
      "temporal": {
       "publishedAt": null,
       "updatedAt": null,
       "sourceCheckedAt": null,
       "recordLastVerifiedAt": "2026-07-26",
       "dossierCreatedAt": "2026-08-22",
       "retrievedAt": null,
       "status": "record-date-only"
      },
      "locator": {
       "type": "descriptive-source-note",
       "value": "Operator page. Returned HTTP 503 on repeated attempts and is NOT relied upon. Search-surfaced text from it gives an undated 'over 200,000 installed' figure that conflicts with CIPER's dated 250,000; the undated figure was dropped rather than reconciled.",
       "exact": false
      },
      "preservation": {
       "archiveUrl": null,
       "archivedAt": null,
       "contentHash": null,
       "status": "not-captured"
      }
     }
    ],
    "coverage": {
     "claimsTotal": 12,
     "claimsMapped": 12,
     "sourcesTotal": 11,
     "sourcesUsedByClaims": 9,
     "sourcesWithPublicationDate": 5,
     "sourcesWithArchive": 0,
     "sourcesWithExactLocator": 0,
     "sourcesWithContentHash": 0
    },
    "limits": [
     "Publisher names and source languages have not yet been classified; domains are recorded without guessing.",
     "Existing source notes are descriptive locators, not page- or paragraph-exact citations.",
     "A missing archive, publication date or content hash is shown as null rather than inferred.",
     "The project-level evidence grade ranks the strongest source in the entry; it is not a truth score for every claim."
    ]
   }
  }
 ]
}